Tridev Ambe Mahal Centre One
by Tridev Realty & Construction Private Limited · Mulund West, Mumbai 400080Also near Mulund EastRegistered on MahaRERA as “Ambe Mahal Centre One”
What’s in the report? →Possession date of Tridev Ambe Mahal Centre One (MahaRERA P51800080551): 30 April 2029. It has 97 homes (1 BHK and 2 BHK, 300–798 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800080551, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800080551, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Tridev Ambe Mahal Centre One?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Tridev Ambe Mahal Centre One has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Tridev Ambe Mahal Centre One’s extension records on MahaRERA (P51800080551), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Tridev Ambe Mahal Centre One
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800080551
- Status
- Registered and active
- Builder
- Tridev Realty & Construction Private Limited
- Location
- Mulund West, Mumbai · 400080
- Project type
- Others
- Registered on
- 16 Jun 2025
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 97
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Tridev Ambe Mahal Centre One, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Ambe Mahal Centre One | 70% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Ambe Mahal Centre One: covers Plinth Level
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tridev Ambe Mahal Centre One every 1–2 months.
Tridev Ambe Mahal Centre One: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 300 – 424 | 81 |
| 2 BHK | 675 – 798 | 16 |
| Office Space | 215 – 2,020 | 13 |
| Shops | 114 – 1,685 | 11 |
- Buildings: Ambe Mahal Centre One (23 floors, 121 units)
- Land: 1,668 sq m (about 0.4 acres) · sanctioned built-up 5,389 sq m · recreational space 135 sq m
- Land, as filed: C.T.S. No. 938, 938/1 To 938/28
- Map: Get directions
The builder’s record and reviews
Tridev Realty AND Construction (a group of 5 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 10 still being built, 7 past the promised date (typically 22 months late). 32 complaints on MahaRERA across 5 projects.
Read Google reviews of Tridev Ambe Mahal Centre One →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Tridev Ambe Mahal Centre One: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Tridev Ambe Mahal Centre One
What is the possession date of Tridev Ambe Mahal Centre One?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tridev Ambe Mahal Centre One in Mulund West, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Tridev Ambe Mahal Centre One?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Tridev Ambe Mahal Centre One's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Tridev Ambe Mahal Centre One?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tridev Ambe Mahal Centre One in Mulund West, Mumbai is P51800080551.
Is Tridev Ambe Mahal Centre One registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Ambe Mahal Centre One is registered as P51800080551 and its status is "Registered and active".
What is the current construction status of Tridev Ambe Mahal Centre One? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Ambe Mahal Centre One's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Ambe Mahal Centre One is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Tridev Ambe Mahal Centre One have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Tridev Ambe Mahal Centre One safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Ambe Mahal Centre One is registered on MahaRERA as P51800080551, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Tridev Ambe Mahal Centre One?
Tridev Ambe Mahal Centre One is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Tridev Ambe Mahal Centre One are 300 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Tridev Ambe Mahal Centre One?
For a flat in Tridev Ambe Mahal Centre One (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Tridev Ambe Mahal Centre One received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Ambe Mahal Centre One is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Tridev Ambe Mahal Centre One uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Tridev Ambe Mahal Centre One was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Tridev Ambe Mahal Centre One's possession date changes?
The latest dates are on Tridev Ambe Mahal Centre One's MahaRERA page (P51800080551). GharKundli's Kundli Watch sends a free WhatsApp update on Tridev Ambe Mahal Centre One every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Tridev Ambe Mahal Centre One have?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Ambe Mahal Centre One has one building filed: Ambe Mahal Centre One with 23 floors and 121 units.
What are the flat sizes (carpet area) in Tridev Ambe Mahal Centre One?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Tridev Ambe Mahal Centre One: 1 BHK: 300 to 424 sq ft carpet (81 homes); 2 BHK: 675 to 798 sq ft carpet (16 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Tridev Ambe Mahal Centre One?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Ambe Mahal Centre One stands on 1,668 sq m of land (about 0.4 acres), with 5,389 sq m of sanctioned built-up area and 135 sq m of recreational open space.
What is the track record of Tridev Ambe Mahal Centre One's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Realty AND Construction (a group of 5 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 10 still being built, 7 past the promised date (typically 22 months late). 32 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Tridev Ambe Mahal Centre One?
Google Maps has reviews of Tridev Ambe Mahal Centre One written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Tridev Ambe Mahal Centre One?
Tridev Ambe Mahal Centre One by Tridev Realty & Construction Private Limited is in Mulund West, Mumbai, pincode 400080 (near Mulund East), Maharashtra, and is registered on MahaRERA as P51800080551, per GharKundli's check of MahaRERA records. Its land is filed as C.T.S. No. 938, 938/1 To 938/28. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).
How many flats are in Tridev Ambe Mahal Centre One, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Ambe Mahal Centre One has 97 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Tridev Ambe Mahal Centre One registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Ambe Mahal Centre One was registered on MahaRERA on 16 June 2025. GharKundli did not find a title report on the land on file there.
Does Tridev Ambe Mahal Centre One have any legal issues or court cases?
No court cases are listed for Tridev Ambe Mahal Centre One on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Tridev Ambe Mahal Centre One?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Tridev Realty & Construction Private Limited, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Tridev Ambe Mahal Centre One
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in Mulund West (400080)
- Malhar Guide
- Arihant Royale
- The Sanctuary - Tower 5
- Keshavpada
- Dhanraj Tower
- Old Hemant Villa Co. Op. Housing Soc. LTD.
- Madhuvan Nivanta
- Shraddha Paradise Enclave
Other projects by Tridev Realty & Construction Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.