by Modirealty Constructions LLP (Modispaces) · Malad West, Mumbai 400064Also near Borivali West, Kandivali West, Goregaon West

What’s in the report? →

Possession date of Modirealty Olive (MahaRERA PM1180002502051): 30 October 2029. It has 8 homes (1 BHK and 2 BHK, 456–610 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1180002502051, and currently active. Its completion date is now October 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PM1180002502051, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Modirealty Olive?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Modirealty Olive has moved

  1. 30 June 2029

    Completion date given when the project was registered

  2. 30 October 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Modirealty Olive’s extension records on MahaRERA (PM1180002502051), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Modirealty Olive

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1180002502051
Status
Registered and active
Builder
Modirealty Constructions LLP
Location
Malad West, Mumbai · 400064
Project type
Mixed
Registered on
12 Jan 2026
Completion date at registration
June 2029
Latest completion date
October 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
8
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Modirealty Olive, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Modirealty Olive100%5%0%10%

Commencement certificate (CC), as filed on MahaRERA

  • Modirealty Olive: covers Plinth

Latest CC order on MahaRERA: dated 26/06/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Modirealty Olive every 1–2 months.

Modirealty Olive: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK4566
Shops377 – 5234
Office Space967 – 1,0652
2 BHK6102

The builder’s record and reviews

Modispaces Real Estate (a group of 4 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 11 finished, all within the promised date; 7 still being built, 1 past the promised date (typically 7 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Modirealty Olive →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Modirealty Olive: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Modirealty Olive

What is the possession date of Modirealty Olive?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Modirealty Olive in Malad West, Mumbai is 30 October 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Modirealty Olive?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Modirealty Olive's builder has filed on MahaRERA, the official one, is 30 October 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Modirealty Olive?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Modirealty Olive in Malad West, Mumbai is PM1180002502051.

Is Modirealty Olive registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Modirealty Olive is registered as PM1180002502051 and its status is "Registered and active".

What is the current construction status of Modirealty Olive? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Modirealty Olive's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Modirealty Olive is 5% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Modirealty Olive have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Modirealty Olive safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Modirealty Olive is registered on MahaRERA as PM1180002502051, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Modirealty Olive?

Modirealty Olive is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Modirealty Olive are 456 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Modirealty Olive?

For a flat in Modirealty Olive (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Modirealty Olive received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Modirealty Olive is still under construction, with 30 October 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Modirealty Olive a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Modirealty Olive's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.

Has Modirealty Olive uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Modirealty Olive was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Modirealty Olive's possession date changes?

The latest dates are on Modirealty Olive's MahaRERA page (PM1180002502051). GharKundli's Kundli Watch sends a free WhatsApp update on Modirealty Olive every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Modirealty Olive have?

According to GharKundli's check of MahaRERA records (updated October 2026), Modirealty Olive has one building filed: Modirealty Olive with 4 floors and 14 units.

What are the flat sizes (carpet area) in Modirealty Olive?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Modirealty Olive: 1 BHK: 456 sq ft carpet (6 homes); 2 BHK: 610 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Modirealty Olive have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 14 covered car parking spaces for Modirealty Olive.

How big is the land of Modirealty Olive?

According to GharKundli's check of MahaRERA records (updated October 2026), Modirealty Olive stands on 780 sq m of land (about 0.2 acres), with 767 sq m of sanctioned built-up area.

What is the track record of Modirealty Olive's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Modispaces Real Estate (a group of 4 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 11 finished, all within the promised date; 7 still being built, 1 past the promised date (typically 7 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Modirealty Olive?

Google Maps has reviews of Modirealty Olive written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Modirealty Olive?

Modirealty Olive by Modirealty Constructions LLP (Modispaces) is in Malad West, Mumbai, pincode 400064 (near Borivali West, Kandivali West, Goregaon West), Maharashtra, and is registered on MahaRERA as PM1180002502051, per GharKundli's check of MahaRERA records. GharKundli lists all 301 MahaRERA projects in Malad West (400064).

How many flats are in Modirealty Olive, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Modirealty Olive has 8 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Modirealty Olive registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Modirealty Olive was registered on MahaRERA on 12 January 2026. GharKundli did not find a title report on the land on file there.

Does Modirealty Olive have any legal issues or court cases?

No court cases are listed for Modirealty Olive on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Modirealty Olive?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Modirealty Constructions LLP, the company Modispaces files this project under.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Malad West (400064)

All 301 projects in Malad West (400064) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.