Anand Villa
by Ivaan Buildcon LLP · Chakala Midc, Mumbai
Registered on MahaRERA under PR1180002501890, and currently active. Its completion date has moved from December 2027 to April 2028, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
- MahaRERA registration
- PR1180002501890
- Status
- Registered and active
- Builder
- Ivaan Buildcon LLP
- Location
- Chakala Midc, Mumbai · 400093
- Project type
- Residential / Group Housing
- Registered on
- 26 Dec 2025
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- Delay so far
- 4 months
- Homes
- 6
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
GharKundli’s full report on Anand Villa
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Kundli Watch
Anand Villa: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Anand Villa
Is Anand Villa registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Villa is registered as PR1180002501890 and its status is "Registered and active".
Where is Anand Villa?
Anand Villa by Ivaan Buildcon LLP is in Chakala Midc, Mumbai (pincode 400093), Maharashtra, and is registered on MahaRERA as PR1180002501890, per GharKundli's check of MahaRERA records.
When is possession of Anand Villa due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Anand Villa in Chakala Midc, Mumbai is 30 April 2028 — 4 months later than 31 December 2027, the date given at registration.
Does Anand Villa have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Anand Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ivaan Buildcon LLP.
Other projects in pincode 400093
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.