Possession date of The Redevelopment of You and I CHSL (MahaRERA PR1180002500668): 7 June 2029. It has 31 homes (2 BHK, 535–707 sq ft carpet), 73% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002500668, and currently active. Its completion date is now June 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002500668, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about The Redevelopment of You and I CHSL?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of The Redevelopment of You and I CHSL has moved

  1. 7 February 2029

    Completion date given when the project was registered

  2. 7 June 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: The Redevelopment of You and I CHSL’s extension records on MahaRERA (PR1180002500668), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The Redevelopment of You and I CHSL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002500668
Status
Registered and active
Builder
PRANAV CONSTRUCTIONS LIMITED
Location
Andheri West, Mumbai · 400053
Project type
Residential / Group Housing
Registered on
26 Aug 2025
Completion date at registration
February 2029
Latest completion date
June 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
31
Sold or booked
73%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
46

Construction progress of The Redevelopment of You and I CHSL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
You & I CHSL90%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • You & I CHSL: covers Upto top of the stilt slab

Latest CC order on MahaRERA: dated 07/08/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Redevelopment of You and I CHSL every 1–2 months.

The Redevelopment of You and I CHSL: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK535 – 70731

The builder’s record and reviews

Pranav Constructions has 47 projects on MahaRERA since 2017, this one included. Of the 47 GharKundli has checked: 24 finished, all within the promised date; 23 still being built, none past the promised date yet. 4 complaints on MahaRERA across 4 projects.

Read Google reviews of The Redevelopment of You and I CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Redevelopment of You and I CHSL: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about The Redevelopment of You and I CHSL

What is the possession date of The Redevelopment of You and I CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Redevelopment of You and I CHSL in Andheri West, Mumbai is 7 June 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for The Redevelopment of You and I CHSL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Redevelopment of You and I CHSL's builder has filed on MahaRERA, the official one, is 7 June 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of The Redevelopment of You and I CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Redevelopment of You and I CHSL in Andheri West, Mumbai is PR1180002500668.

Is The Redevelopment of You and I CHSL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Redevelopment of You and I CHSL is registered as PR1180002500668 and its status is "Registered and active".

What is the current construction status of The Redevelopment of You and I CHSL? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), The Redevelopment of You and I CHSL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on You & I CHSL is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does The Redevelopment of You and I CHSL have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is The Redevelopment of You and I CHSL safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), The Redevelopment of You and I CHSL is registered on MahaRERA as PR1180002500668, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in The Redevelopment of You and I CHSL?

The Redevelopment of You and I CHSL is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in The Redevelopment of You and I CHSL are 535 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in The Redevelopment of You and I CHSL?

For a flat in The Redevelopment of You and I CHSL (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has The Redevelopment of You and I CHSL received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), The Redevelopment of You and I CHSL is still under construction, with 7 June 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is The Redevelopment of You and I CHSL a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), The Redevelopment of You and I CHSL is a redevelopment: 20 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has The Redevelopment of You and I CHSL uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for The Redevelopment of You and I CHSL was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if The Redevelopment of You and I CHSL's possession date changes?

The latest dates are on The Redevelopment of You and I CHSL's MahaRERA page (PR1180002500668). GharKundli's Kundli Watch sends a free WhatsApp update on The Redevelopment of You and I CHSL every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Redevelopment of You and I CHSL have?

According to GharKundli's check of MahaRERA records (updated October 2026), The Redevelopment of You and I CHSL has one building filed: You & I CHSL with 9 floors and 31 units.

What are the flat sizes (carpet area) in The Redevelopment of You and I CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for The Redevelopment of You and I CHSL: 2 BHK: 535 to 707 sq ft carpet (31 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does The Redevelopment of You and I CHSL have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 44 covered car parking spaces for The Redevelopment of You and I CHSL.

How big is the land of The Redevelopment of You and I CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), The Redevelopment of You and I CHSL stands on 835 sq m of land (about 0.2 acres), with 1,896 sq m of sanctioned built-up area.

What is the track record of The Redevelopment of You and I CHSL's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Pranav Constructions has 47 projects on MahaRERA since 2017, this one included. Of the 47 GharKundli has checked: 24 finished, all within the promised date; 23 still being built, none past the promised date yet. 4 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of The Redevelopment of You and I CHSL?

Google Maps has reviews of The Redevelopment of You and I CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of The Redevelopment of You and I CHSL?

The Redevelopment of You and I CHSL by PRANAV CONSTRUCTIONS LIMITED is in Andheri West, Mumbai, pincode 400053 (near Ambivali, Four Bungalows, Versova, Four Bungalow, Versova), Maharashtra, and is registered on MahaRERA as PR1180002500668, per GharKundli's check of MahaRERA records. GharKundli lists all 162 MahaRERA projects in Andheri West (400053).

How many flats are in The Redevelopment of You and I CHSL, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), The Redevelopment of You and I CHSL has 31 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.

When was The Redevelopment of You and I CHSL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Redevelopment of You and I CHSL was registered on MahaRERA on 26 August 2025. GharKundli did not find a title report on the land on file there.

Does The Redevelopment of You and I CHSL have any legal issues or court cases?

No court cases are listed for The Redevelopment of You and I CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of The Redevelopment of You and I CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRANAV CONSTRUCTIONS LIMITED, which has 46 other projects registered on MahaRERA.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Andheri West (400053)

All 162 projects in Andheri West (400053) →

Other projects by PRANAV CONSTRUCTIONS LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.