Skip to content
GharKundli

Surbhi Apartment

by DIVA BEAMTECH · Malad, Mumbai 400064Also near Borivali West, Goregaon West, Worli

What’s in the report? →

Possession date of Surbhi Apartment (MahaRERA PR1180002501576): 30 October 2028. It has 55 homes (1 BHK, 2 BHK and 3 BHK, 345–919 sq ft carpet), 11% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002501576, and currently active. Its completion date is now October 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002501576, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Surbhi Apartment?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Surbhi Apartment has moved

  1. 30 June 2028

    Completion date given when the project was registered

  2. 30 October 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Surbhi Apartment’s extension records on MahaRERA (PR1180002501576), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Surbhi Apartment

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the October 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002501576
Status
Registered and active
Builder
DIVA BEAMTECH
Location
Malad, Mumbai · 400064
Project type
Residential / Group Housing
Registered on
25 Nov 2025
Completion date at registration
June 2028
Latest completion date
October 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
55
Sold or booked
11%
Towers
3
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of Surbhi Apartment, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building / Wing A100%100%0%0%
Building / Wing B100%100%0%0%
Building / Wing C100%100%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Building: covers Stilt slab level
  • Building: covers Stilt slab level
  • Building: covers Stilt slab level

Latest CC order on MahaRERA: dated 30/06/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Surbhi Apartment every 1–2 months.

Surbhi Apartment: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK779 – 91926
2 BHK605 – 74915
1 BHK345 – 52414
  • Buildings: Building (9 floors, 16 units) · Building (9 floors, 23 units) · Building (10 floors, 16 units)
  • Car parking: 48 covered
  • Land: 1,415 sq m (about 0.3 acres) · sanctioned built-up 3,819 sq m · recreational space 212 sq m
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Surbhi Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Surbhi Apartment: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Surbhi Apartment

What is the possession date of Surbhi Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Surbhi Apartment in Malad, Mumbai is 30 October 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Surbhi Apartment?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Surbhi Apartment's builder has filed on MahaRERA, the official one, is 30 October 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Surbhi Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Surbhi Apartment in Malad, Mumbai is PR1180002501576.

Is Surbhi Apartment registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Surbhi Apartment is registered as PR1180002501576 and its status is "Registered and active".

What is the current construction status of Surbhi Apartment? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Surbhi Apartment's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Surbhi Apartment have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Surbhi Apartment safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Surbhi Apartment is registered on MahaRERA as PR1180002501576, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Surbhi Apartment?

Surbhi Apartment is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Surbhi Apartment are 345 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Surbhi Apartment?

For a flat in Surbhi Apartment (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Surbhi Apartment received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Surbhi Apartment is still under construction, with 30 October 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Surbhi Apartment a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Surbhi Apartment is a redevelopment: 46 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Surbhi Apartment uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Surbhi Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Surbhi Apartment's possession date changes?

The latest dates are on Surbhi Apartment's MahaRERA page (PR1180002501576). GharKundli's Kundli Watch sends a free WhatsApp update on Surbhi Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Surbhi Apartment have?

According to GharKundli's check of MahaRERA records (updated October 2026), Surbhi Apartment has 3 buildings filed: Building with 9 floors and 16 units; Building with 9 floors and 23 units; Building with 10 floors and 16 units.

What are the flat sizes (carpet area) in Surbhi Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Surbhi Apartment: 3 BHK: 779 to 919 sq ft carpet (26 homes); 2 BHK: 605 to 749 sq ft carpet (15 homes); 1 BHK: 345 to 524 sq ft carpet (14 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Surbhi Apartment have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 48 covered car parking spaces for Surbhi Apartment.

How big is the land of Surbhi Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), Surbhi Apartment stands on 1,415 sq m of land (about 0.3 acres), with 3,819 sq m of sanctioned built-up area and 212 sq m of recreational open space.

What are the reviews of Surbhi Apartment?

Google Maps has reviews of Surbhi Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Surbhi Apartment?

Surbhi Apartment by DIVA BEAMTECH is in Malad, Mumbai, pincode 400064 (near Borivali West, Goregaon West, Worli), Maharashtra, and is registered on MahaRERA as PR1180002501576, per GharKundli's check of MahaRERA records. GharKundli lists all 301 MahaRERA projects in Malad West (400064).

How many flats are in Surbhi Apartment, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Surbhi Apartment has 55 homes in 3 towers registered on MahaRERA, and 11% of them are sold or booked.

When was Surbhi Apartment registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Surbhi Apartment was registered on MahaRERA on 25 November 2025. GharKundli did not find a title report on the land on file there.

Does Surbhi Apartment have any legal issues or court cases?

1 court case is listed for Surbhi Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Surbhi Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DIVA BEAMTECH.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Malad West (400064)

All 301 projects in Malad West (400064) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.