Rander 25 RBC
by Rander Bandhu Corporation LLP · Borivali, Mumbai 400091Also near Daulat Nagar, Eksar, KanheriRegistered on MahaRERA as “25 RBC”
What’s in the report? →Possession date of Rander 25 RBC (MahaRERA PM1180002501734): 31 July 2029. It has 78 homes (2 BHK and 3 BHK, 516–874 sq ft carpet), 8% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PM1180002501734, and currently active. Its completion date is now July 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PM1180002501734, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Rander 25 RBC?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Rander 25 RBC has moved
31 March 2029
Completion date given when the project was registered
31 July 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Rander 25 RBC’s extension records on MahaRERA (PM1180002501734), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Rander 25 RBC
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1180002501734
- Status
- Registered and active
- Builder
- Rander Bandhu Corporation LLP
- Location
- Borivali, Mumbai · 400091
- Project type
- Mixed
- Registered on
- 10 Dec 2025
- Completion date at registration
- March 2029
- Latest completion date
- July 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 78
- Sold or booked
- 8%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Rander 25 RBC, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Pancham CHSL / Wing A | 100% | 0% | 0% | 0% |
| Pancham CHSL / Wing B | 100% | 0% | 0% | 0% |
| Pancham CHSL / Wing C | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Pancham CHSL: covers upto plinth level
- Pancham CHSL: covers upto plinth level
- Pancham CHSL: covers upto plinth level
Latest CC order on MahaRERA: dated 07/08/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rander 25 RBC every 1–2 months.
Rander 25 RBC: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 516 – 732 | 39 |
| 3 BHK | 715 – 874 | 39 |
| Shops | 194 – 628 | 14 |
| Office Space | 911 – 1,131 | 5 |
- Buildings: Pancham CHSL (14 floors, 46 units) · Pancham CHSL (14 floors, 46 units) · Pancham CHSL (5 floors, 5 units)
- Car parking: 125 covered
- Land: 2,926 sq m (about 0.7 acres) · sanctioned built-up 6,443 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Rander Bandhu Corporation (a group of 3 linked companies) has 4 projects on MahaRERA since 2023, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA.
Read Google reviews of Rander 25 RBC →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Rander 25 RBC: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Rander 25 RBC
What is the possession date of Rander 25 RBC?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Rander 25 RBC in Borivali, Mumbai is 31 July 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Rander 25 RBC?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Rander 25 RBC's builder has filed on MahaRERA, the official one, is 31 July 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Rander 25 RBC?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Rander 25 RBC in Borivali, Mumbai is PM1180002501734.
Is Rander 25 RBC registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rander 25 RBC is registered as PM1180002501734 and its status is "Registered and active".
What is the current construction status of Rander 25 RBC? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Rander 25 RBC's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Rander 25 RBC have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Rander 25 RBC safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Rander 25 RBC is registered on MahaRERA as PM1180002501734, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Rander 25 RBC?
Rander 25 RBC is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Rander 25 RBC are 516 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Rander 25 RBC?
For a flat in Rander 25 RBC (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Rander 25 RBC received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Rander 25 RBC is still under construction, with 31 July 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Rander 25 RBC a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Rander 25 RBC is a redevelopment: 58 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Rander 25 RBC uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Rander 25 RBC was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Rander 25 RBC's possession date changes?
The latest dates are on Rander 25 RBC's MahaRERA page (PM1180002501734). GharKundli's Kundli Watch sends a free WhatsApp update on Rander 25 RBC every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Rander 25 RBC have?
According to GharKundli's check of MahaRERA records (updated October 2026), Rander 25 RBC has 3 buildings filed: Pancham CHSL with 14 floors and 46 units; Pancham CHSL with 14 floors and 46 units; Pancham CHSL with 5 floors and 5 units.
What are the flat sizes (carpet area) in Rander 25 RBC?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Rander 25 RBC: 2 BHK: 516 to 732 sq ft carpet (39 homes); 3 BHK: 715 to 874 sq ft carpet (39 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Rander 25 RBC have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 125 covered car parking spaces for Rander 25 RBC.
How big is the land of Rander 25 RBC?
According to GharKundli's check of MahaRERA records (updated October 2026), Rander 25 RBC stands on 2,926 sq m of land (about 0.7 acres), with 6,443 sq m of sanctioned built-up area.
What is the track record of Rander 25 RBC's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Rander Bandhu Corporation (a group of 3 linked companies) has 4 projects on MahaRERA since 2023, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Rander 25 RBC?
Google Maps has reviews of Rander 25 RBC written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Rander 25 RBC?
Rander 25 RBC by Rander Bandhu Corporation LLP is in Borivali, Mumbai, pincode 400091 (near Daulat Nagar, Eksar, Kanheri), Maharashtra, and is registered on MahaRERA as PM1180002501734, per GharKundli's check of MahaRERA records. GharKundli lists all 69 MahaRERA projects in Borivali West (400091).
How many flats are in Rander 25 RBC, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Rander 25 RBC has 78 homes in 3 towers registered on MahaRERA, and 8% of them are sold or booked.
When was Rander 25 RBC registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rander 25 RBC was registered on MahaRERA on 10 December 2025. GharKundli did not find a title report on the land on file there.
Does Rander 25 RBC have any legal issues or court cases?
No court cases are listed for Rander 25 RBC on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Rander 25 RBC?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Rander Bandhu Corporation LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Rander 25 RBC
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in Borivali West (400091)
- Bhoomi Pratishtha
- Legacy
- Avyukta Parijat
- Borivali Veer Dhaval
- DTG Azure
- Rashmi Square
- Kaustubh Capital
- Bank of India Employees Sukhada CHSL
Other projects by Rander Bandhu Corporation LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.