Skip to content
GharKundli

Matushree Poddar Vasundhara

by MATUSHREE REAL ESTATE DEVELOPERS PRIVATE LIMITED · Vile Parle East, Mumbai 400057Also near Vile Parle West, Vileparle East, Andheri WestRegistered on MahaRERA as “PODDAR VASUNDHARA”

What’s in the report? →

Possession date of Matushree Poddar Vasundhara (MahaRERA PR1180002502310): 15 April 2028. It has 23 homes (1 BHK, 2 BHK and 3 BHK, 299–967 sq ft carpet), 8% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002502310, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002502310, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Matushree Poddar Vasundhara?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Matushree Poddar Vasundhara has moved

  1. 15 December 2027

    Completion date given when the project was registered

  2. 15 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Matushree Poddar Vasundhara’s extension records on MahaRERA (PR1180002502310), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Matushree Poddar Vasundhara

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002502310
Status
Registered and active
Builder
MATUSHREE REAL ESTATE DEVELOPERS PRIVATE LIMITED
Location
Vile Parle East, Mumbai · 400057
Project type
Residential / Group Housing
Registered on
10 Feb 2026
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
23
Sold or booked
8%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Matushree Poddar Vasundhara, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ARUNODAYA CO OPERATIVE HOUSING SOCIETY LIMITED100%28%10%0%

Commencement certificate (CC), as filed on MahaRERA

  • ARUNODAYA CO OPERATIVE HOUSING SOCIETY LIMITED: covers C.C. up to top of Basement/Plinth

Latest CC order on MahaRERA: dated 11/09/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Matushree Poddar Vasundhara every 1–2 months.

Matushree Poddar Vasundhara: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK627 – 80612
Shops177 – 3595
3 BHK891 – 9675
1 BHK441 – 6294
Multi Purpose Room299 – 3212

The builder’s record and reviews

Matushree Real Estate Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 1 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Matushree Poddar Vasundhara →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Matushree Poddar Vasundhara: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Matushree Poddar Vasundhara

What is the possession date of Matushree Poddar Vasundhara?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Matushree Poddar Vasundhara in Vile Parle East, Mumbai is 15 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Matushree Poddar Vasundhara?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Matushree Poddar Vasundhara's builder has filed on MahaRERA, the official one, is 15 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Matushree Poddar Vasundhara?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Matushree Poddar Vasundhara in Vile Parle East, Mumbai is PR1180002502310.

Is Matushree Poddar Vasundhara registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Matushree Poddar Vasundhara is registered as PR1180002502310 and its status is "Registered and active".

What is the current construction status of Matushree Poddar Vasundhara? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Matushree Poddar Vasundhara's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ARUNODAYA CO OPERATIVE HOUSING SOCIETY LIMITED is 28% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.

Does Matushree Poddar Vasundhara have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Matushree Poddar Vasundhara safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Matushree Poddar Vasundhara is registered on MahaRERA as PR1180002502310, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Matushree Poddar Vasundhara?

Matushree Poddar Vasundhara is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Matushree Poddar Vasundhara are 299 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Matushree Poddar Vasundhara?

For a flat in Matushree Poddar Vasundhara (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Matushree Poddar Vasundhara received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Matushree Poddar Vasundhara is still under construction, with 15 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Matushree Poddar Vasundhara a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Matushree Poddar Vasundhara is a redevelopment: 16 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Matushree Poddar Vasundhara uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Matushree Poddar Vasundhara was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Matushree Poddar Vasundhara's possession date changes?

The latest dates are on Matushree Poddar Vasundhara's MahaRERA page (PR1180002502310). GharKundli's Kundli Watch sends a free WhatsApp update on Matushree Poddar Vasundhara every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Matushree Poddar Vasundhara have?

According to GharKundli's check of MahaRERA records (updated October 2026), Matushree Poddar Vasundhara has one building filed: ARUNODAYA CO OPERATIVE HOUSING SOCIETY LIMITED with 8 floors and 28 units.

What are the flat sizes (carpet area) in Matushree Poddar Vasundhara?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Matushree Poddar Vasundhara: 2 BHK: 627 to 806 sq ft carpet (12 homes); 3 BHK: 891 to 967 sq ft carpet (5 homes); 1 BHK: 441 to 629 sq ft carpet (4 homes); Multi Purpose Room: 299 to 321 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Matushree Poddar Vasundhara have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 22 covered car parking spaces for Matushree Poddar Vasundhara.

How big is the land of Matushree Poddar Vasundhara?

According to GharKundli's check of MahaRERA records (updated October 2026), Matushree Poddar Vasundhara stands on 609 sq m of land (about 0.2 acres), with 1,808 sq m of sanctioned built-up area.

What is the track record of Matushree Poddar Vasundhara's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Matushree Real Estate Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 1 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Matushree Poddar Vasundhara?

Google Maps has reviews of Matushree Poddar Vasundhara written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Matushree Poddar Vasundhara?

Matushree Poddar Vasundhara by MATUSHREE REAL ESTATE DEVELOPERS PRIVATE LIMITED is in Vile Parle East, Mumbai, pincode 400057 (near Vile Parle West, Vileparle East, Andheri West), Maharashtra, and is registered on MahaRERA as PR1180002502310, per GharKundli's check of MahaRERA records. Its boundaries filed there include SUBASH ROAD. GharKundli lists all 251 MahaRERA projects in Vile Parle East (400057).

How many flats are in Matushree Poddar Vasundhara, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Matushree Poddar Vasundhara has 23 homes in 1 tower registered on MahaRERA, and 8% of them are sold or booked.

When was Matushree Poddar Vasundhara registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Matushree Poddar Vasundhara was registered on MahaRERA on 10 February 2026. GharKundli did not find a title report on the land on file there.

Does Matushree Poddar Vasundhara have any legal issues or court cases?

No court cases are listed for Matushree Poddar Vasundhara on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Matushree Poddar Vasundhara?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MATUSHREE REAL ESTATE DEVELOPERS PRIVATE LIMITED, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Vile Parle East (400057)

All 251 projects in Vile Parle East (400057) →

Other projects by MATUSHREE REAL ESTATE DEVELOPERS PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.