Skip to content
GharKundli

Kaustubh Park 91

by Kaustubh Construction Private Limited · Magathane, Borivali East, Mumbai

Registered on MahaRERA under PR1180002503020, and currently active. Its completion date has moved from December 2030 to April 2031, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

MahaRERA registration
PR1180002503020
Status
Registered and active
Builder
Kaustubh Construction Private Limited
Location
Magathane, Borivali East, Mumbai · 400091
Project type
Residential / Group Housing
Registered on
23 Mar 2026
Completion date at registration
December 2030
Latest completion date
April 2031
Delay so far
4 months
Homes
234
Sold or booked
5%
Towers
4
Complaints on MahaRERA
0
Court cases listed
7
Title report on file
Not found
Builder's other MahaRERA projects
7

GharKundli’s full report on Kaustubh Park 91

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Kundli Watch

Kaustubh Park 91: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Kaustubh Park 91

Is Kaustubh Park 91 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kaustubh Park 91 is registered as PR1180002503020 and its status is "Registered and active".

Where is Kaustubh Park 91?

Kaustubh Park 91 by Kaustubh Construction Private Limited is in Magathane, Borivali East, Mumbai (pincode 400091), Maharashtra, and is registered on MahaRERA as PR1180002503020, per GharKundli's check of MahaRERA records.

When is possession of Kaustubh Park 91 due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kaustubh Park 91 in Magathane, Borivali East, Mumbai is 30 April 2031 — 4 months later than 30 December 2030, the date given at registration.

Does Kaustubh Park 91 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Kaustubh Park 91?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kaustubh Construction Private Limited, which has 7 other projects registered on MahaRERA.

Other projects in pincode 400091

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.