Possession date of Mickey Heights (MahaRERA PM1180002600431): 30 April 2031. It has 41 homes (1 Room Kitchen, 2 BHK and 3 BHK, 374–1264 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1180002600431, and currently active. Its completion date is now April 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PM1180002600431, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Mickey Heights?

4 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Mickey Heights has moved

  1. 30 December 2030

    Completion date given when the project was registered

  2. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Mickey Heights’s extension records on MahaRERA (PM1180002600431), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mickey Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 court cases, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1180002600431
Status
Registered and active
Builder
Murarilal Surajmal Mody
Location
Kandivali West, Mumbai · 400067
Project type
Mixed
Registered on
15 May 2026
Completion date at registration
December 2030
Latest completion date
April 2031
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
41
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
4
Title report on file
Not found

Construction progress of Mickey Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Charkop Sushobhit CHS LTD0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Charkop Sushobhit CHS LTD: covers PLINTH LEVEL

Latest CC order on MahaRERA: dated 23/09/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mickey Heights every 1–2 months.

Mickey Heights: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK472 – 63823
3 BHK665 – 1,26417
Shops88 – 3634
Office Space7531
1 Room Kitchen3741

The builder’s record and reviews

Murarilal Mody has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Mickey Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mickey Heights: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Mickey Heights

What is the possession date of Mickey Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mickey Heights in Kandivali West, Mumbai is 30 April 2031, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Mickey Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mickey Heights's builder has filed on MahaRERA, the official one, is 30 April 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Mickey Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mickey Heights in Kandivali West, Mumbai is PM1180002600431.

Is Mickey Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mickey Heights is registered as PM1180002600431 and its status is "Registered and active".

What is the current construction status of Mickey Heights? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Mickey Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Charkop Sushobhit CHS LTD is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Mickey Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Mickey Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Mickey Heights is registered on MahaRERA as PM1180002600431, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Mickey Heights?

Mickey Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Mickey Heights are 374 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Mickey Heights?

For a flat in Mickey Heights (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Mickey Heights received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Mickey Heights is still under construction, with 30 April 2031 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Mickey Heights a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Mickey Heights is a redevelopment: 21 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Mickey Heights uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Mickey Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Mickey Heights's possession date changes?

The latest dates are on Mickey Heights's MahaRERA page (PM1180002600431). GharKundli's Kundli Watch sends a free WhatsApp update on Mickey Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mickey Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Mickey Heights has one building filed: Charkop Sushobhit CHS LTD with 16 floors and 46 units.

What are the flat sizes (carpet area) in Mickey Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Mickey Heights: 2 BHK: 472 to 638 sq ft carpet (23 homes); 3 BHK: 665 to 1264 sq ft carpet (17 homes); 1 Room Kitchen: 374 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Mickey Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 45 open car parking spaces for Mickey Heights.

How big is the land of Mickey Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Mickey Heights stands on 750 sq m of land (about 0.2 acres), with 3,026 sq m of sanctioned built-up area.

What is the track record of Mickey Heights's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Murarilal Mody has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Mickey Heights?

Google Maps has reviews of Mickey Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Mickey Heights?

Mickey Heights by Murarilal Surajmal Mody is in Kandivali West, Mumbai, pincode 400067 (near Charkop), Maharashtra, and is registered on MahaRERA as PM1180002600431, per GharKundli's check of MahaRERA records. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).

How many flats are in Mickey Heights, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Mickey Heights has 41 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Mickey Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mickey Heights was registered on MahaRERA on 15 May 2026. GharKundli did not find a title report on the land on file there.

Does Mickey Heights have any legal issues or court cases?

4 court cases are listed for Mickey Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Mickey Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Murarilal Surajmal Mody.

All projects with possession due in 2031 in Mumbai Suburban →

Other projects in Kandivali West (400067)

All 318 projects in Kandivali West (400067) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.