THE CURVE

by METRO LIFESPACE · Malad (West),, Mumbai

Registered on MahaRERA under PC1180002600481, and currently active. Its completion date has moved from March 2028 to July 2028, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

MahaRERA registration
PC1180002600481
Status
Registered and active
Builder
METRO LIFESPACE
Location
Malad (West),, Mumbai · 400064
Project type
Commercial
Registered on
20 May 2026
Completion date at registration
March 2028
Latest completion date
July 2028
Delay so far
4 months
Homes
0
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

GharKundli’s full report on THE CURVE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Kundli Watch

THE CURVE: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about THE CURVE

Is THE CURVE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), THE CURVE is registered as PC1180002600481 and its status is "Registered and active".

Where is THE CURVE?

THE CURVE by METRO LIFESPACE is in Malad (West),, Mumbai (pincode 400064), Maharashtra, and is registered on MahaRERA as PC1180002600481, per GharKundli's check of MahaRERA records.

When is possession of THE CURVE due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE CURVE in Malad (West),, Mumbai is 31 July 2028 — 4 months later than 31 March 2028, the date given at registration.

Does THE CURVE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of THE CURVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is METRO LIFESPACE.

Other projects in pincode 400064

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.