Skip to content
GharKundli

Navkarmik Shiv Sneh

by NAVKARMIK LANDSPACES LLP · Borivali, Mumbai 400095Also near Malad West, Kandivali west, KharodiRegistered on MahaRERA as “Shiv Sneh”

What’s in the report? →

Possession date of Navkarmik Shiv Sneh (MahaRERA PM1180002600989): 4 September 2029. It has 31 homes (1 BHK and 2 BHK, 320–845 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1180002600989, and currently active. Its completion date is now September 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PM1180002600989, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Navkarmik Shiv Sneh?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Navkarmik Shiv Sneh has moved

  1. 4 May 2029

    Completion date given when the project was registered

  2. 4 September 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Navkarmik Shiv Sneh’s extension records on MahaRERA (PM1180002600989), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Navkarmik Shiv Sneh

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1180002600989
Status
Registered and active
Builder
NAVKARMIK LANDSPACES LLP
Location
Borivali, Mumbai · 400095
Project type
Mixed
Registered on
30 Jun 2026
Completion date at registration
May 2029
Latest completion date
September 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
31
Sold or booked
0%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Navkarmik Shiv Sneh, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Shiv Sneh / Wing A0%0%0%0%
Shiv Sneh / Wing B0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Shiv Sneh: covers Plinth Level
  • Shiv Sneh: covers Plinth Level

Latest CC order on MahaRERA: dated 27/04/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Navkarmik Shiv Sneh every 1–2 months.

Navkarmik Shiv Sneh: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK483 – 84522
1 BHK320 – 4379
Office Space149 – 4238
Shops168 – 4375

The builder’s record and reviews

Navkarmik Homes LLP Urvi Construction (a group of 2 linked companies) has 2 projects on MahaRERA since 2026, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Navkarmik Shiv Sneh →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Navkarmik Shiv Sneh: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Navkarmik Shiv Sneh

What is the possession date of Navkarmik Shiv Sneh?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Navkarmik Shiv Sneh in Borivali, Mumbai is 4 September 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Navkarmik Shiv Sneh?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Navkarmik Shiv Sneh's builder has filed on MahaRERA, the official one, is 4 September 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Navkarmik Shiv Sneh?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Navkarmik Shiv Sneh in Borivali, Mumbai is PM1180002600989.

Is Navkarmik Shiv Sneh registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkarmik Shiv Sneh is registered as PM1180002600989 and its status is "Registered and active".

What is the current construction status of Navkarmik Shiv Sneh? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkarmik Shiv Sneh's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Navkarmik Shiv Sneh have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Navkarmik Shiv Sneh safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkarmik Shiv Sneh is registered on MahaRERA as PM1180002600989, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Navkarmik Shiv Sneh?

Navkarmik Shiv Sneh is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Navkarmik Shiv Sneh are 320 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Navkarmik Shiv Sneh?

For a flat in Navkarmik Shiv Sneh (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Navkarmik Shiv Sneh received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Navkarmik Shiv Sneh is still under construction, with 4 September 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Navkarmik Shiv Sneh a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkarmik Shiv Sneh is a redevelopment: 21 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Navkarmik Shiv Sneh uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Navkarmik Shiv Sneh was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Navkarmik Shiv Sneh's possession date changes?

The latest dates are on Navkarmik Shiv Sneh's MahaRERA page (PM1180002600989). GharKundli's Kundli Watch sends a free WhatsApp update on Navkarmik Shiv Sneh every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Navkarmik Shiv Sneh have?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkarmik Shiv Sneh has 2 buildings filed: Shiv Sneh with 6 floors and 13 units; Shiv Sneh with 12 floors and 31 units.

What are the flat sizes (carpet area) in Navkarmik Shiv Sneh?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Navkarmik Shiv Sneh: 2 BHK: 483 to 845 sq ft carpet (22 homes); 1 BHK: 320 to 437 sq ft carpet (9 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Navkarmik Shiv Sneh have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 85 covered car parking spaces for Navkarmik Shiv Sneh.

How big is the land of Navkarmik Shiv Sneh?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkarmik Shiv Sneh stands on 1,677 sq m of land (about 0.4 acres), with 2,207 sq m of sanctioned built-up area.

What is the track record of Navkarmik Shiv Sneh's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkarmik Homes LLP Urvi Construction (a group of 2 linked companies) has 2 projects on MahaRERA since 2026, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Navkarmik Shiv Sneh?

Google Maps has reviews of Navkarmik Shiv Sneh written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Navkarmik Shiv Sneh?

Navkarmik Shiv Sneh by NAVKARMIK LANDSPACES LLP is in Borivali, Mumbai, pincode 400095 (near Malad West, Kandivali west, Kharodi), Maharashtra, and is registered on MahaRERA as PM1180002600989, per GharKundli's check of MahaRERA records. Its boundaries filed there include Garden. GharKundli lists all 52 MahaRERA projects in Malad West (400095).

How many flats are in Navkarmik Shiv Sneh, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkarmik Shiv Sneh has 31 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.

When was Navkarmik Shiv Sneh registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkarmik Shiv Sneh was registered on MahaRERA on 30 June 2026. GharKundli did not find a title report on the land on file there.

Does Navkarmik Shiv Sneh have any legal issues or court cases?

No court cases are listed for Navkarmik Shiv Sneh on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Navkarmik Shiv Sneh?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NAVKARMIK LANDSPACES LLP.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Malad West (400095)

All 52 projects in Malad West (400095) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.