by Maa Vaishnavi Builders & Developers · Kalyan, Thane 421301Registered on MahaRERA as “Capsule Business Hub”

What’s in the report? →

Possession date of MAA Capsule Business Hub (MahaRERA P51700015836): 30 April 2027, moved from 30 June 2021 (66 months later). No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700015836, and currently active. Its completion date has moved from June 2021 to April 2027: 66 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700015836, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about MAA Capsule Business Hub?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of MAA Capsule Business Hub has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51700009804)

    Reason the builder gave MahaRERA:
    “Respected Sir, We, Maa Vaishnavi, have registered for our real estate project "Capsule Business " bearing registration no. P517000185836. The date of completion of the project was given as 30.12.2020 at the time of registration which was ex…” Read the full reason“Respected Sir, We, Maa Vaishnavi, have registered for our real estate project "Capsule Business " bearing registration no. P517000185836. The date of completion of the project was given as 30.12.2020 at the time of registration which was extended to 30.06.2021. However, we couldn’t complete said project within the stipulated period due Covid-19 pandemic, inadequate labour supply and changes in DC rules. We have sold/booked only 2 units out of total 53 units. We have obtained 100% consent from them for extension of the project till 31.12.2023 as per Section 7(3) and circular no. 07/2019 date…”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51700024327)

    Reason the builder gave MahaRERA: “As per Attachment”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MAA Capsule Business Hub’s extension records on MahaRERA (P51700015836), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MAA Capsule Business Hub

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700015836
Status
Registered and active
Builder
Maa Vaishnavi Builders & Developers
Location
Kalyan, Thane · 421301
Project type
Others
Registered on
27 Mar 2018
Completion date at registration
June 2021
Latest completion date
April 2027
Delay so far
66 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of MAA Capsule Business Hub, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Capsule Business Hub100%100%30%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MAA Capsule Business Hub every 1–2 months.

MAA Capsule Business Hub: buildings, flats and land, as filed on MahaRERA

  • Buildings: Capsule Business Hub (9 floors)
  • Land: 742 sq m (about 0.2 acres) · sanctioned built-up 912 sq m
  • Boundaries filed include: Hotel Ramdev, 24Mtrs KDMC Road
  • Land, as filed: 2848A/1/1
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MAA Capsule Business Hub →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MAA Capsule Business Hub: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about MAA Capsule Business Hub

What is the possession date of MAA Capsule Business Hub?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MAA Capsule Business Hub in Kalyan, Thane is 30 April 2027 — 66 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 66 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for MAA Capsule Business Hub?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MAA Capsule Business Hub's builder has filed on MahaRERA, the official one, is 30 April 2027, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MAA Capsule Business Hub extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MAA Capsule Business Hub's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2023, giving the reason "Respected Sir, We, Maa Vaishnavi, have registered for our real estate project "Capsule Business " bearing registration no. P517000185836. The date of completion of the project was given as 30.12.2020 at the time of registration which was extended to 30.06.2021. However, we couldn’t complete said project within the stipulated period due Covid-19 pandemic, inadequate labour supply and changes in DC rules. We have sold/booked only 2 units out of total 53 units. We have obtained 100% consent from them for extension of the project till 31.12.2023 as per Section 7(3) and circular no. 07/2019 date…"; to 31 December 2026, giving the reason "As per Attachment". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of MAA Capsule Business Hub?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MAA Capsule Business Hub in Kalyan, Thane is P51700015836.

Is MAA Capsule Business Hub registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAA Capsule Business Hub is registered as P51700015836 and its status is "Registered and active".

What is the current construction status of MAA Capsule Business Hub? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), MAA Capsule Business Hub's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Capsule Business Hub is 100% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.

Does MAA Capsule Business Hub have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is MAA Capsule Business Hub safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MAA Capsule Business Hub is registered on MahaRERA as P51700015836, its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in MAA Capsule Business Hub?

MAA Capsule Business Hub is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in MAA Capsule Business Hub?

For a flat in MAA Capsule Business Hub (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has MAA Capsule Business Hub received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), MAA Capsule Business Hub is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has MAA Capsule Business Hub uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for MAA Capsule Business Hub was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if MAA Capsule Business Hub's possession date changes?

The latest dates are on MAA Capsule Business Hub's MahaRERA page (P51700015836). GharKundli's Kundli Watch sends a free WhatsApp update on MAA Capsule Business Hub every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MAA Capsule Business Hub have?

According to GharKundli's check of MahaRERA records (updated October 2026), MAA Capsule Business Hub has one building filed: Capsule Business Hub with 9 floors.

How big is the land of MAA Capsule Business Hub?

According to GharKundli's check of MahaRERA records (updated October 2026), MAA Capsule Business Hub stands on 742 sq m of land (about 0.2 acres), with 912 sq m of sanctioned built-up area.

What are the reviews of MAA Capsule Business Hub?

Google Maps has reviews of MAA Capsule Business Hub written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of MAA Capsule Business Hub?

MAA Capsule Business Hub by Maa Vaishnavi Builders & Developers is in Kalyan, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700015836, per GharKundli's check of MahaRERA records. Its boundaries filed there include Hotel Ramdev, 24Mtrs KDMC Road. Its land is filed as 2848A/1/1. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).

When was MAA Capsule Business Hub registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAA Capsule Business Hub was registered on MahaRERA on 27 March 2018. GharKundli did not find a title report on the land on file there.

Does MAA Capsule Business Hub have any legal issues or court cases?

No court cases are listed for MAA Capsule Business Hub on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of MAA Capsule Business Hub?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Maa Vaishnavi Builders & Developers, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan (421301)

All 582 projects in Kalyan (421301) →

Other projects by Maa Vaishnavi Builders & Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.