Skip to content
GharKundli

Euro Ville Phase II

by Vastu Rachana JV · Naupada, Thane

Possession: Euro Ville Phase II is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700001090. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Euro Ville Phase II?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Euro Ville Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700001090
Status
Completed
Builder
Vastu Rachana JV
Location
Naupada, Thane · 421601
Project type
Mixed
Registered on
26 Jul 2017
Completion date at registration
December 2022
Latest completion date
December 2022
Homes
167
Towers
167
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Euro Ville Phase II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A Type Villa No1100%100%100%100%
A Type Villa No2100%100%100%100%
A Type Villa No3100%100%100%100%
A Type Villa No4100%100%100%100%
A Type Villa No50%0%0%0%
A Type Villa No60%0%0%0%
A Type Villa No70%0%0%0%
A Type Villa No80%0%0%0%
A Type Villa No90%0%0%0%
B Type Villa No1100%100%100%100%
B Type Villa No2100%100%100%100%
B Type Villa No3100%100%100%100%
B Type Villa No4100%100%100%100%
B Type Villa No5100%100%100%100%
B Type Villa No6100%100%100%100%
B Type Villa No7100%100%100%100%
B Type Villa No8100%100%100%100%
B Type Villa No9100%100%100%100%
B Type Villa No10100%100%100%100%
B Type Villa No11100%100%100%100%
B Type Villa No12100%100%100%100%
B Type villa No13100%100%100%100%
B Type Villa No14100%100%100%100%
B Type Villa No15100%100%100%100%
B Type Villa No16100%100%100%100%
B Type Villa No17100%100%100%100%
B Type Villa No18100%100%100%100%
B Type Villa No19100%100%100%100%
B Type Villa No200%0%0%0%
B Type Villa No210%0%0%0%

Showing 30 of 167 towers.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Euro Ville Phase II every month.

Euro Ville Phase II: buildings, flats and land, as filed on MahaRERA

  • Buildings: A Type Villa No1 (1 floors) · A Type Villa No2 (1 floors) · A Type Villa No3 (1 floors) · A Type Villa No4 (1 floors) · A Type Villa No5 (1 floors) · A Type Villa No6 (1 floors) · A Type Villa No7 (1 floors) · A Type Villa No8 (1 floors) · and 22 more
  • Land: 1,07,800 sq m (about 26.6 acres) · sanctioned built-up 17,148 sq m · recreational space 10,520 sq m

The builder’s record and reviews

Bhide Lifespaces (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 78 months late). 13 complaints on MahaRERA across 1 project.

Read Google reviews of Euro Ville Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Euro Ville Phase II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Euro Ville Phase II

What is the possession date of Euro Ville Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Euro Ville Phase II in Naupada, Thane is 30 December 2022.

Is the builder's possession date different from the MahaRERA date for Euro Ville Phase II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Euro Ville Phase II's builder has filed on MahaRERA, the official one, is 30 December 2022, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Euro Ville Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Euro Ville Phase II in Naupada, Thane is P51700001090.

Is Euro Ville Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Euro Ville Phase II is registered as P51700001090 and its status is "Completed".

What is the construction status of Euro Ville Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), Euro Ville Phase II's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 0% to 100% across 30 towers. GharKundli's full report compares construction progress with the deadline.

Does Euro Ville Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Euro Ville Phase II safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Euro Ville Phase II is registered on MahaRERA as P51700001090, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Euro Ville Phase II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Euro Ville Phase I (P51700001003, possession 30 Dec 2022). Check that your agreement names the registration of your own wing.

How can I get updates if Euro Ville Phase II's possession date changes?

The latest dates are on Euro Ville Phase II's MahaRERA page (P51700001090). GharKundli's Kundli Watch sends a free WhatsApp update on Euro Ville Phase II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Euro Ville Phase II have?

According to GharKundli's check of MahaRERA records (updated November 2026), Euro Ville Phase II has 30 buildings filed: A Type Villa No1 with 1 floors; A Type Villa No2 with 1 floors; A Type Villa No3 with 1 floors; A Type Villa No4 with 1 floors; A Type Villa No5 with 1 floors; A Type Villa No6 with 1 floors; and 24 more.

How big is the land of Euro Ville Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), Euro Ville Phase II stands on 1,07,800 sq m of land (about 26.6 acres), with 17,148 sq m of sanctioned built-up area and 10,520 sq m of recreational open space.

What is the track record of Euro Ville Phase II's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Bhide Lifespaces (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 78 months late). 13 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Euro Ville Phase II?

Google Maps has reviews of Euro Ville Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Euro Ville Phase II?

Euro Ville Phase II by Vastu Rachana JV is in Naupada, Thane (pincode 421601), Maharashtra, and is registered on MahaRERA as P51700001090, per GharKundli's check of MahaRERA records.

How many homes are in Euro Ville Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), Euro Ville Phase II has 167 homes in 167 towers registered on MahaRERA.

When was Euro Ville Phase II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Euro Ville Phase II was registered on MahaRERA on 26 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Euro Ville Phase II?

No court cases are listed for Euro Ville Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Euro Ville Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Vastu Rachana JV, which has 1 other project registered on MahaRERA.