Mohan Altezza II

by MOHAN LIFESPACES LLP · Kalyan, Thane

Possession: Mohan Altezza II is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700007011. Status: Completed. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Mohan Altezza II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Mohan Altezza II has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT51700005394)

    Reason the builder gave MahaRERA:
    “This is with reference to our project Mohan Altezza II, comprises of one building named as Crest, bearing RERA Registration number P51700007011. The original date of completion of the project was proposed at 31st December 2019. However due…” Read the full reason“This is with reference to our project Mohan Altezza II, comprises of one building named as Crest, bearing RERA Registration number P51700007011. The original date of completion of the project was proposed at 31st December 2019. However due to some uncontrolled reasons such as non-availability of some contractors and their laborers on time and also irregular/short supply of water caused delay in completion of project. Hence we are filing this application for project extension. Kindly accept our application and oblige.”
  3. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51700010429)

    Reason the builder gave MahaRERA:
    “The construction of project Mohan Altezza II was expected to be completed by December 2020. However due to an unprecedented challenge in form of pandemic Covid-19, the construction activity of project is adversely affected. In last year, th…” Read the full reason“The construction of project Mohan Altezza II was expected to be completed by December 2020. However due to an unprecedented challenge in form of pandemic Covid-19, the construction activity of project is adversely affected. In last year, the construction activity of the project halted for 4-5 months as per the government lockdown regulations. Even after the relaxation of lockdown, the construction activity could not be started fully due to migration of labour and irregular supply of material. We were able to take-up regular construction speed in the month of November 2020 only, however agai…”
  4. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51700013573)

    Reason the builder gave MahaRERA:
    “This is with reference to our project Mohan Altezza II, bearing RERA Registration number P51700007011. The construction of project was expected to be completed by 31st December 2022. However due to unprecedented challenge in form of pandemi…” Read the full reason“This is with reference to our project Mohan Altezza II, bearing RERA Registration number P51700007011. The construction of project was expected to be completed by 31st December 2022. However due to unprecedented challenge in form of pandemic Covid-19 and some uncontrolled issues such as non-availability of contractors and their laborers on time and also non-availability of material on time caused delay in completion of project. Further, there was Search of income tax department on our firm in the month of June 2022, the income department queries and our submissions took considerable time of…”

Source: Mohan Altezza II’s extension records on MahaRERA (P51700007011), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mohan Altezza II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints and 2 court cases, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700007011
Status
Completed
Builder
MOHAN LIFESPACES LLP
Location
Kalyan, Thane · 421301
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2023
Delay so far
48 months
Homes
135
Towers
1
Complaints on MahaRERA
2
Court cases listed
2
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
23

Construction progress of Mohan Altezza II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
C Wing - Crest100%100%90%80%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mohan Altezza II every month.

Mohan Altezza II: buildings, flats and land, as filed on MahaRERA

  • Buildings: C Wing - Crest (35 floors)
  • Land: 3,720 sq m (about 0.9 acres) · sanctioned built-up 11,078 sq m · recreational space 2,626 sq m

The builder’s record and reviews

Mohan Lifespaces (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 19 finished, 8 within the promised date and 11 needed more time (typically 12 months); 6 still being built, none past the promised date yet. 21 complaints on MahaRERA across 6 projects.

Read Google reviews of Mohan Altezza II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mohan Altezza II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Mohan Altezza II

What is the possession date of Mohan Altezza II?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mohan Altezza II in Kalyan, Thane is 31 December 2023 — 48 months later than 31 December 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Mohan Altezza II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mohan Altezza II's builder has filed on MahaRERA, the official one, is 31 December 2023, already 48 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Mohan Altezza II extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Altezza II's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "This is with reference to our project Mohan Altezza II, comprises of one building named as Crest, bearing RERA Registration number P51700007011. The original date of completion of the project was proposed at 31st December 2019. However due to some uncontrolled reasons such as non-availability of some contractors and their laborers on time and also irregular/short supply of water caused delay in completion of project. Hence we are filing this application for project extension. Kindly accept our application and oblige."; to 30 June 2022, giving the reason "The construction of project Mohan Altezza II was expected to be completed by December 2020. However due to an unprecedented challenge in form of pandemic Covid-19, the construction activity of project is adversely affected. In last year, the construction activity of the project halted for 4-5 months as per the government lockdown regulations. Even after the relaxation of lockdown, the construction activity could not be started fully due to migration of labour and irregular supply of material. We were able to take-up regular construction speed in the month of November 2020 only, however agai…"; to 31 December 2023, giving the reason "This is with reference to our project Mohan Altezza II, bearing RERA Registration number P51700007011. The construction of project was expected to be completed by 31st December 2022. However due to unprecedented challenge in form of pandemic Covid-19 and some uncontrolled issues such as non-availability of contractors and their laborers on time and also non-availability of material on time caused delay in completion of project. Further, there was Search of income tax department on our firm in the month of June 2022, the income department queries and our submissions took considerable time of…".

What is the RERA number of Mohan Altezza II?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mohan Altezza II in Kalyan, Thane is P51700007011.

Is Mohan Altezza II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Altezza II is registered as P51700007011 and its status is "Completed".

What is the construction status of Mohan Altezza II?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Altezza II's status on MahaRERA is "Completed". As filed by the builder, slab work on C Wing - Crest is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does Mohan Altezza II have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Mohan Altezza II safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Altezza II is registered on MahaRERA as P51700007011, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Mohan Altezza II have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Mohan Altezza I (P51700004557, possession 30 Jun 2018); Mohan Altezza III (P51700050807, possession 30 Apr 2028). Check that your agreement names the registration of your own wing.

How can I get updates if Mohan Altezza II's possession date changes?

The latest dates are on Mohan Altezza II's MahaRERA page (P51700007011). GharKundli's Kundli Watch sends a free WhatsApp update on Mohan Altezza II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mohan Altezza II have?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Altezza II has one building filed: C Wing - Crest with 35 floors.

How big is the land of Mohan Altezza II?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Altezza II stands on 3,720 sq m of land (about 0.9 acres), with 11,078 sq m of sanctioned built-up area and 2,626 sq m of recreational open space.

What is the track record of Mohan Altezza II's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Lifespaces (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 19 finished, 8 within the promised date and 11 needed more time (typically 12 months); 6 still being built, none past the promised date yet. 21 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Mohan Altezza II?

Google Maps has reviews of Mohan Altezza II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Mohan Altezza II?

Mohan Altezza II by MOHAN LIFESPACES LLP is in Kalyan, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700007011, per GharKundli's check of MahaRERA records.

How many homes are in Mohan Altezza II?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Altezza II has 135 homes in 1 tower registered on MahaRERA.

When was Mohan Altezza II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Altezza II was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Mohan Altezza II?

2 court cases are listed for Mohan Altezza II on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Mohan Altezza II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MOHAN LIFESPACES LLP, which has 23 other projects registered on MahaRERA.

Other projects in pincode 421301

All 582 projects in Kalyan (421301) →

Other projects by MOHAN LIFESPACES LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.