MORYA HEIGHTS
by MORYA INFRACONSTRUCT PRIVATE LIMITED · Hajuri, ThaneAlso near Panchpakhadi, Wagle Estate, Naupada
Possession date of MORYA HEIGHTS: 31 December 2027, moved from 30 December 2024 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700005511, and currently active. 23 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MORYA HEIGHTS?
How the possession date of MORYA HEIGHTS has moved
30 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700025726)
Reason the builder gave MahaRERA:
“1.The allottees of the project have already paid significant amount of consideration towards their respective flats in the project. To secure their funds and to deliver their flats, it is necessary to have the MahaRERA project registration…” Read the full reason
“1.The allottees of the project have already paid significant amount of consideration towards their respective flats in the project. To secure their funds and to deliver their flats, it is necessary to have the MahaRERA project registration extension certificate granted. 2.One of the major requirements for the allottees to register their agreement for sale and pay the stamp duty to the government is a valid MahaRERA Project Registration Certificate without which their agreement cannot be registered and the project cannot receive their payments which will lead to further delay and hardships t…”31 December 2027
Extended at the builder's request (MahaRERA application EA03022619687)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project. The construction was delayed mainly due to COVID, which severely impacted on the real estate sector. Medium-scale developers like Morya Infraconstruct Private Limited faced a liqu…” Read the full reason
“We apologize for the delay in the completion of the project. The construction was delayed mainly due to COVID, which severely impacted on the real estate sector. Medium-scale developers like Morya Infraconstruct Private Limited faced a liquidity crunch as flat sales remained stagnant for a long period and demand declined due to unemployment and recession. Despite these challenges, we successfully completed Rehab Tower-1 (SRA building) and handed over possession to 130 tenants. The building plans were revised in January 2024, and approval for additional floors on both SRA towers was granted…”
Source: MORYA HEIGHTS’s extension records on MahaRERA (P51700005511), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MORYA HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 23 complaints, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700005511
- Status
- Registered and active
- Builder
- MORYA INFRACONSTRUCT PRIVATE LIMITED
- Location
- Hajuri, Thane · 400604
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2017
- Completion date at registration
- December 2024
- Latest completion date
- December 2027
- Delay so far
- 36 months
- Homes
- 240
- Sold or booked
- 68%
- Towers
- 1
- Complaints on MahaRERA
- 23
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of MORYA HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MORYA HEIGHTS REHAB 2 | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- MORYA HEIGHTS REHAB 2: covers 16 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MORYA HEIGHTS every month.
MORYA HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: MORYA HEIGHTS REHAB 2 (23 floors, 255 units)
- Land: 3,379 sq m (about 0.8 acres) · sanctioned built-up 3,379 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Morya Infraconstruct has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 8 months late). 24 complaints on MahaRERA across 2 projects.
Read Google reviews of MORYA HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MORYA HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MORYA HEIGHTS
What is the possession date of MORYA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MORYA HEIGHTS in Hajuri, Thane is 31 December 2027 — 36 months later than 30 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for MORYA HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MORYA HEIGHTS's builder has filed on MahaRERA, the official one, is 31 December 2027, already 36 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MORYA HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA HEIGHTS's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "1.The allottees of the project have already paid significant amount of consideration towards their respective flats in the project. To secure their funds and to deliver their flats, it is necessary to have the MahaRERA project registration extension certificate granted. 2.One of the major requirements for the allottees to register their agreement for sale and pay the stamp duty to the government is a valid MahaRERA Project Registration Certificate without which their agreement cannot be registered and the project cannot receive their payments which will lead to further delay and hardships t…"; to 31 December 2027, giving the reason "We apologize for the delay in the completion of the project. The construction was delayed mainly due to COVID, which severely impacted on the real estate sector. Medium-scale developers like Morya Infraconstruct Private Limited faced a liquidity crunch as flat sales remained stagnant for a long period and demand declined due to unemployment and recession. Despite these challenges, we successfully completed Rehab Tower-1 (SRA building) and handed over possession to 130 tenants. The building plans were revised in January 2024, and approval for additional floors on both SRA towers was granted…".
What is the RERA number of MORYA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MORYA HEIGHTS in Hajuri, Thane is P51700005511.
Is MORYA HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA HEIGHTS is registered as P51700005511 and its status is "Registered and active".
What is the construction status of MORYA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MORYA HEIGHTS REHAB 2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does MORYA HEIGHTS have complaints on MahaRERA?
23 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is MORYA HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA HEIGHTS is registered on MahaRERA as P51700005511, its completion date has moved 36 months since registration and 23 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MORYA HEIGHTS's possession date changes?
The latest dates are on MORYA HEIGHTS's MahaRERA page (P51700005511). GharKundli's Kundli Watch sends a free WhatsApp update on MORYA HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MORYA HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA HEIGHTS has one building filed: MORYA HEIGHTS REHAB 2 with 23 floors and 255 units.
How big is the land of MORYA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA HEIGHTS stands on 3,379 sq m of land (about 0.8 acres), with 3,379 sq m of sanctioned built-up area.
What is the track record of MORYA HEIGHTS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Infraconstruct has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 8 months late). 24 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MORYA HEIGHTS?
Google Maps has reviews of MORYA HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 23 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MORYA HEIGHTS?
MORYA HEIGHTS by MORYA INFRACONSTRUCT PRIVATE LIMITED is in Hajuri, Thane (pincode 400604), near Panchpakhadi, Wagle Estate, Naupada, Maharashtra, and is registered on MahaRERA as P51700005511, per GharKundli's check of MahaRERA records.
How many homes are in MORYA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA HEIGHTS has 240 homes in 1 tower registered on MahaRERA, and 68% of them are sold or booked.
When was MORYA HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA HEIGHTS was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MORYA HEIGHTS?
No court cases are listed for MORYA HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of MORYA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MORYA INFRACONSTRUCT PRIVATE LIMITED, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MORYA HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Thane
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- GURUKRUPA NITYAM
- MAULI KRUPA
- ASAVARI CO OP HSG SOC LTD
- LOTUS
- Panache
- Mahavir Breeze Phase 1
Other projects by MORYA INFRACONSTRUCT PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.