Possession date of DURGA IMPERIAL: 28 February 2027, moved from 30 October 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700007962, and currently active. Its completion date has moved from October 2023 to February 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about DURGA IMPERIAL?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DURGA IMPERIAL has moved

  1. 30 October 2023

    Completion date given when the project was registered

  2. 31 October 2026

    Extended at the builder's request (MahaRERA application EXT51700011166)

    Reason the builder gave MahaRERA:
    “Dear Sir We are applying for extension As there is Revision in Commencement Certificate as per revised KDMC norms, Increase in Sanctioned floors of Building A wing from 20 floors to 29 floors Building B wing from 8 floors to 20 floors Short…” Read the full reason“Dear Sir We are applying for extension As there is Revision in Commencement Certificate as per revised KDMC norms, Increase in Sanctioned floors of Building A wing from 20 floors to 29 floors Building B wing from 8 floors to 20 floors Shortage of Labour post Covid 19 & Financial issues . OVERALL DELAY IN CONSTRUCTION INDUSTRY , SLOWDOWN & PANDEMIC COVID 19 We Request You to extend the Above project upto 30 Oct 2026. Thanks you”
  3. 28 February 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: DURGA IMPERIAL’s extension records on MahaRERA (P51700007962), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DURGA IMPERIAL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the February 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700007962
Status
Registered and active
Builder
G K MALI & C K MALI
Location
Kalyan East, Thane · 421306
Project type
Others
Registered on
18 Aug 2017
Completion date at registration
October 2023
Latest completion date
February 2027
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
302
Towers
1
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found

Construction progress of DURGA IMPERIAL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DURGA IMPERIAL A,B WING100%31%10%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DURGA IMPERIAL every month.

DURGA IMPERIAL: buildings, flats and land, as filed on MahaRERA

  • Buildings: DURGA IMPERIAL A,B WING (31 floors)
  • Land: 6,600 sq m (about 1.6 acres) · sanctioned built-up 12,951 sq m · recreational space 891 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of DURGA IMPERIAL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DURGA IMPERIAL: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DURGA IMPERIAL

What is the possession date of DURGA IMPERIAL?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DURGA IMPERIAL in Kalyan East, Thane is 28 February 2027 — 36 months later than 30 October 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for DURGA IMPERIAL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DURGA IMPERIAL's builder has filed on MahaRERA, the official one, is 28 February 2027, already 36 months later than the 30 October 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DURGA IMPERIAL extended?

According to GharKundli's check of MahaRERA records (updated October 2026), DURGA IMPERIAL's builder applied to MahaRERA to extend the completion date once: to 31 October 2026, giving the reason "Dear Sir We are applying for extension As there is Revision in Commencement Certificate as per revised KDMC norms, Increase in Sanctioned floors of Building A wing from 20 floors to 29 floors Building B wing from 8 floors to 20 floors Shortage of Labour post Covid 19 & Financial issues . OVERALL DELAY IN CONSTRUCTION INDUSTRY , SLOWDOWN & PANDEMIC COVID 19 We Request You to extend the Above project upto 30 Oct 2026. Thanks you". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of DURGA IMPERIAL?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DURGA IMPERIAL in Kalyan East, Thane is P51700007962.

Is DURGA IMPERIAL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DURGA IMPERIAL is registered as P51700007962 and its status is "Registered and active".

What is the construction status of DURGA IMPERIAL?

According to GharKundli's check of MahaRERA records (updated October 2026), DURGA IMPERIAL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on DURGA IMPERIAL A,B WING is 31% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.

Does DURGA IMPERIAL have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is DURGA IMPERIAL safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), DURGA IMPERIAL is registered on MahaRERA as P51700007962, its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DURGA IMPERIAL's possession date changes?

The latest dates are on DURGA IMPERIAL's MahaRERA page (P51700007962). GharKundli's Kundli Watch sends a free WhatsApp update on DURGA IMPERIAL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DURGA IMPERIAL have?

According to GharKundli's check of MahaRERA records (updated October 2026), DURGA IMPERIAL has one building filed: DURGA IMPERIAL A,B WING with 31 floors.

How big is the land of DURGA IMPERIAL?

According to GharKundli's check of MahaRERA records (updated October 2026), DURGA IMPERIAL stands on 6,600 sq m of land (about 1.6 acres), with 12,951 sq m of sanctioned built-up area and 891 sq m of recreational open space.

Where can I read reviews of DURGA IMPERIAL?

Google Maps has reviews of DURGA IMPERIAL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DURGA IMPERIAL?

DURGA IMPERIAL by G K MALI & C K MALI is in Kalyan East, Thane (pincode 421306), Maharashtra, and is registered on MahaRERA as P51700007962, per GharKundli's check of MahaRERA records.

How many homes are in DURGA IMPERIAL?

According to GharKundli's check of MahaRERA records (updated October 2026), DURGA IMPERIAL has 302 homes in 1 tower registered on MahaRERA.

When was DURGA IMPERIAL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DURGA IMPERIAL was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on DURGA IMPERIAL?

1 court case is listed for DURGA IMPERIAL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of DURGA IMPERIAL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is G K MALI & C K MALI.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan East

All 270 projects in Kalyan East (421306) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.