OSTWAL DARSHAN
by SHREE OSTWAL BUILDERS LTD · Bhayander East, ThaneAlso near Navghar, Bhayandar West, Goddev
Possession: OSTWAL DARSHAN is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700004905. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about OSTWAL DARSHAN?
How the possession date of OSTWAL DARSHAN has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51700018500)
Reason the builder gave MahaRERA: “DUE TO REVISED CC WORK TO BE COMPLETED AND APPLICATION OF FULL OC TO BE DONE”
Source: OSTWAL DARSHAN’s extension records on MahaRERA (P51700004905), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on OSTWAL DARSHAN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 4 court cases, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700004905
- Status
- Completed
- Builder
- SHREE OSTWAL BUILDERS LTD
- Location
- Bhayander East, Thane · 401105
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- December 2024
- Delay so far
- 12 months
- Homes
- 116
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 4
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 19
Construction progress of OSTWAL DARSHAN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| OSTWAL DARSHAN | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on OSTWAL DARSHAN every month.
OSTWAL DARSHAN: buildings, flats and land, as filed on MahaRERA
- Buildings: OSTWAL DARSHAN (26 floors)
- Land: 4,044 sq m (about 1.0 acres) · sanctioned built-up 5,228 sq m · recreational space 813 sq m
- Boundaries filed include: UNITED PARK, KRISHNA PARK, MBMC GARDEN
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shree Ostwal Builders (a group of 3 linked companies) has 22 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 5 finished, all within the promised date; 12 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.
Read Google reviews of OSTWAL DARSHAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
OSTWAL DARSHAN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about OSTWAL DARSHAN
What is the possession date of OSTWAL DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for OSTWAL DARSHAN in Bhayander East, Thane is 29 December 2024 — 12 months later than 30 December 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for OSTWAL DARSHAN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date OSTWAL DARSHAN's builder has filed on MahaRERA, the official one, is 29 December 2024, already 12 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of OSTWAL DARSHAN extended?
According to GharKundli's check of MahaRERA records (updated October 2026), OSTWAL DARSHAN's builder applied to MahaRERA to extend the completion date once: to 29 December 2024, giving the reason "DUE TO REVISED CC WORK TO BE COMPLETED AND APPLICATION OF FULL OC TO BE DONE".
What is the RERA number of OSTWAL DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of OSTWAL DARSHAN in Bhayander East, Thane is P51700004905.
Is OSTWAL DARSHAN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), OSTWAL DARSHAN is registered as P51700004905 and its status is "Completed".
What is the construction status of OSTWAL DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), OSTWAL DARSHAN's status on MahaRERA is "Completed". As filed by the builder, slab work on OSTWAL DARSHAN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does OSTWAL DARSHAN have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is OSTWAL DARSHAN safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), OSTWAL DARSHAN is registered on MahaRERA as P51700004905, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if OSTWAL DARSHAN's possession date changes?
The latest dates are on OSTWAL DARSHAN's MahaRERA page (P51700004905). GharKundli's Kundli Watch sends a free WhatsApp update on OSTWAL DARSHAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does OSTWAL DARSHAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), OSTWAL DARSHAN has one building filed: OSTWAL DARSHAN with 26 floors.
How big is the land of OSTWAL DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), OSTWAL DARSHAN stands on 4,044 sq m of land (about 1.0 acres), with 5,228 sq m of sanctioned built-up area and 813 sq m of recreational open space.
What is the track record of OSTWAL DARSHAN's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Ostwal Builders (a group of 3 linked companies) has 22 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 5 finished, all within the promised date; 12 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of OSTWAL DARSHAN?
Google Maps has reviews of OSTWAL DARSHAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is OSTWAL DARSHAN?
OSTWAL DARSHAN by SHREE OSTWAL BUILDERS LTD is in Bhayander East, Thane (pincode 401105), near Navghar, Bhayandar West, Goddev, Maharashtra, and is registered on MahaRERA as P51700004905, per GharKundli's check of MahaRERA records. Its boundaries filed there include UNITED PARK, KRISHNA PARK, MBMC GARDEN.
How many homes are in OSTWAL DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), OSTWAL DARSHAN has 116 homes in 1 tower registered on MahaRERA.
When was OSTWAL DARSHAN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), OSTWAL DARSHAN was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on OSTWAL DARSHAN?
4 court cases are listed for OSTWAL DARSHAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of OSTWAL DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE OSTWAL BUILDERS LTD, which has 19 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of OSTWAL DARSHAN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401105
All 99 projects in Bhayander East (401105) →Other projects by SHREE OSTWAL BUILDERS LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.