GAURAV WOODS II

by Ravi Developments · Beverly Park Mira road, ThaneAlso near Mira Road East, Village Navghar, Mira-Bhayander

Possession date of GAURAV WOODS II: 31 December 2028, moved from 30 December 2023 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800011407, and currently active. 17 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about GAURAV WOODS II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GAURAV WOODS II has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700018358)

    Reason the builder gave MahaRERA:
    “The project was impacted by the COVID-19 outbreak in 2020 and 2021, and the subsequent slow market conditions and labour shortages made it difficult for us to complete the project on time. Therefore, we are requesting an extension of time w…” Read the full reason“The project was impacted by the COVID-19 outbreak in 2020 and 2021, and the subsequent slow market conditions and labour shortages made it difficult for us to complete the project on time. Therefore, we are requesting an extension of time within which the project shall be completed by the promoter to 31st December 2025.”
  3. 31 December 2028

    Extended at the builder's request (MahaRERA application EA04032620077)

    Reason the builder gave MahaRERA:
    “1. The Commencement Certificate (CC) granted in respect of the project was subsequently found to be erroneous. Consequently, all projects undertaken by Ravi Developments were restrained from proceeding further, resulting in unavoidable dela…” Read the full reason“1. The Commencement Certificate (CC) granted in respect of the project was subsequently found to be erroneous. Consequently, all projects undertaken by Ravi Developments were restrained from proceeding further, resulting in unavoidable delay in the construction and completion of the project. 2. The Promoter has suffered severe financial constraints on account of adverse and unforeseen economic conditions prevailing in the Indian real estate sector, which have materially affected the execution of the project. 3. The overall slowdown in the real estate market, coupled with shortage of labour,…”

Source: GAURAV WOODS II’s extension records on MahaRERA (P51800011407), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GAURAV WOODS II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 17 complaints and 4 court cases, and how it ended
  • Construction pace against the December 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800011407
Status
Registered and active
Builder
Ravi Developments
Location
Beverly Park Mira road, Thane · 401107
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2023
Latest completion date
December 2028
Delay so far
60 months
Homes
495
Sold or booked
58%
Towers
3
Complaints on MahaRERA
17
Court cases listed
4
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
13

Construction progress of GAURAV WOODS II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
G1100%70.83%53.76%0%
G2100%8.33%0.63%0%
G3100%62.5%59.68%25%

Commencement certificate (CC), as filed on MahaRERA

  • G1: covers 21 Floor
  • G2: covers 21 Floor
  • G3: covers 21 Floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GAURAV WOODS II every month.

GAURAV WOODS II: buildings, flats and land, as filed on MahaRERA

  • Buildings: G1 (25 floors, 165 units) · G2 (25 floors, 165 units) · G3 (25 floors, 165 units)
  • Car parking: 3 covered
  • Land: 6,581 sq m (about 1.6 acres) · sanctioned built-up 10,014 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 4 finished, all within the promised date; 15 still being built, 8 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects.

Read Google reviews of GAURAV WOODS II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GAURAV WOODS II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GAURAV WOODS II

What is the possession date of GAURAV WOODS II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GAURAV WOODS II in Beverly Park Mira road, Thane is 31 December 2028 — 60 months later than 30 December 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for GAURAV WOODS II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GAURAV WOODS II's builder has filed on MahaRERA, the official one, is 31 December 2028, already 60 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GAURAV WOODS II extended?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV WOODS II's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "The project was impacted by the COVID-19 outbreak in 2020 and 2021, and the subsequent slow market conditions and labour shortages made it difficult for us to complete the project on time. Therefore, we are requesting an extension of time within which the project shall be completed by the promoter to 31st December 2025."; to 31 December 2028, giving the reason "1. The Commencement Certificate (CC) granted in respect of the project was subsequently found to be erroneous. Consequently, all projects undertaken by Ravi Developments were restrained from proceeding further, resulting in unavoidable delay in the construction and completion of the project. 2. The Promoter has suffered severe financial constraints on account of adverse and unforeseen economic conditions prevailing in the Indian real estate sector, which have materially affected the execution of the project. 3. The overall slowdown in the real estate market, coupled with shortage of labour,…".

What is the RERA number of GAURAV WOODS II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GAURAV WOODS II in Beverly Park Mira road, Thane is P51800011407.

Is GAURAV WOODS II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV WOODS II is registered as P51800011407 and its status is "Registered and active". On MahaRERA's own list: Sales frozen by MahaRERA: quarterly reports not filed. MahaRERA has put this project in abeyance for not filing its quarterly progress reports (August 2017). Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.

What is the construction status of GAURAV WOODS II?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV WOODS II's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 8.33% to 70.83% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does GAURAV WOODS II have complaints on MahaRERA?

17 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is GAURAV WOODS II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV WOODS II is registered on MahaRERA as P51800011407, its completion date has moved 60 months since registration, 17 complaints are listed against it and it is on MahaRERA's list "Sales frozen by MahaRERA: quarterly reports not filed". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GAURAV WOODS II's possession date changes?

The latest dates are on GAURAV WOODS II's MahaRERA page (P51800011407). GharKundli's Kundli Watch sends a free WhatsApp update on GAURAV WOODS II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GAURAV WOODS II have?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV WOODS II has 3 buildings filed: G1 with 25 floors and 165 units; G2 with 25 floors and 165 units; G3 with 25 floors and 165 units.

How much parking does GAURAV WOODS II have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 3 covered car parking spaces for GAURAV WOODS II.

How big is the land of GAURAV WOODS II?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV WOODS II stands on 6,581 sq m of land (about 1.6 acres), with 10,014 sq m of sanctioned built-up area.

What is the track record of GAURAV WOODS II's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 4 finished, all within the promised date; 15 still being built, 8 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of GAURAV WOODS II?

Google Maps has reviews of GAURAV WOODS II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 17 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GAURAV WOODS II?

GAURAV WOODS II by Ravi Developments is in Beverly Park Mira road, Thane (pincode 401107), near Mira Road East, Village Navghar, Mira-Bhayander, Maharashtra, and is registered on MahaRERA as P51800011407, per GharKundli's check of MahaRERA records.

How many homes are in GAURAV WOODS II?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV WOODS II has 495 homes in 3 towers registered on MahaRERA, and 58% of them are sold or booked.

When was GAURAV WOODS II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV WOODS II was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on GAURAV WOODS II?

4 court cases are listed for GAURAV WOODS II on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of GAURAV WOODS II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ravi Developments, which has 13 other projects registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in pincode 401107

All 322 projects in Mira Road East (401107) →

Other projects by Ravi Developments

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.