Gaurav Excellency
by Ravi Developments · Harkesh Uday Nagar, ThaneAlso near Mira Road, Village Ghodbunder, Vinay Nagar
Possession date of Gaurav Excellency: 31 March 2027, moved from 30 December 2023 (39 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700006232, and currently active. 35 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Gaurav Excellency?
How the possession date of Gaurav Excellency has moved
30 December 2023
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700018582)
Reason the builder gave MahaRERA:
“The project was impacted by the COVID-19 outbreak in 2020 and 2021, and the subsequent slow market conditions and labour shortages made it difficult for us to complete the project on time. Therefore, we are requesting an extension of time w…” Read the full reason
“The project was impacted by the COVID-19 outbreak in 2020 and 2021, and the subsequent slow market conditions and labour shortages made it difficult for us to complete the project on time. Therefore, we are requesting an extension of time within which the project shall be completed by the promoter to 31st December 2025.”31 March 2027
Extended at the builder's request (MahaRERA application EA26032620390)
Reason the builder gave MahaRERA:
“1.The Commencement Certificate (CC) granted in respect of the project was subsequently found to be erroneous. Consequently, all projects undertaken by Ravi Developments were restrained from proceeding further, resulting in unavoidable delay…” Read the full reason
“1.The Commencement Certificate (CC) granted in respect of the project was subsequently found to be erroneous. Consequently, all projects undertaken by Ravi Developments were restrained from proceeding further, resulting in unavoidable delay in the construction and completion of the project. 2.The Promoter has suffered severe financial constraints on account of adverse and unforeseen economic conditions prevailing in the Indian real estate sector, which have materially affected the execution of the project. 3. The overall slowdown in the real estate market, coupled with shortage of labour, s…”
Source: Gaurav Excellency’s extension records on MahaRERA (P51700006232), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Gaurav Excellency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 35 complaints, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700006232
- Status
- Registered and active
- Builder
- Ravi Developments
- Location
- Harkesh Uday Nagar, Thane · 400107
- Project type
- Others
- Registered on
- 14 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- March 2027
- Delay so far
- 39 months
- Homes
- 489
- Sold or booked
- 76%
- Towers
- 5
- Complaints on MahaRERA
- 35
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 13
Construction progress of Gaurav Excellency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 5 | 100% | 77.91% | 44.21% | 15% |
| Building no 6 | 100% | 77.91% | 44.21% | 15% |
| Building No 7 | 100% | 77.91% | 44.21% | 15% |
| Building No 8 | 100% | 77.91% | 44.21% | 15% |
| Building No 9 | 100% | 77.91% | 44.21% | 15% |
Commencement certificate (CC), as filed on MahaRERA
- Building No 5: covers 21 Floor
- Building no 6: covers 21 Floor
- Building No 7: covers 21 Floor
- Building No 8: covers 21 Floor
- Building No 9: covers 21 Floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gaurav Excellency every month.
Gaurav Excellency: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 5 (27 floors, 123 units) · Building no 6 (27 floors, 123 units) · Building No 7 (27 floors, 81 units) · Building No 8 (27 floors, 81 units) · Building No 9 (27 floors, 81 units)
- Land: 11,682 sq m (about 2.9 acres) · sanctioned built-up 10,683 sq m · recreational space 629 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 4 finished, all within the promised date; 15 still being built, 8 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects.
Read Google reviews of Gaurav Excellency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Gaurav Excellency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Gaurav Excellency
What is the possession date of Gaurav Excellency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gaurav Excellency in Harkesh Uday Nagar, Thane is 31 March 2027 — 39 months later than 30 December 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Gaurav Excellency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Gaurav Excellency's builder has filed on MahaRERA, the official one, is 31 March 2027, already 39 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Gaurav Excellency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Excellency's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "The project was impacted by the COVID-19 outbreak in 2020 and 2021, and the subsequent slow market conditions and labour shortages made it difficult for us to complete the project on time. Therefore, we are requesting an extension of time within which the project shall be completed by the promoter to 31st December 2025."; to 31 March 2027, giving the reason "1.The Commencement Certificate (CC) granted in respect of the project was subsequently found to be erroneous. Consequently, all projects undertaken by Ravi Developments were restrained from proceeding further, resulting in unavoidable delay in the construction and completion of the project. 2.The Promoter has suffered severe financial constraints on account of adverse and unforeseen economic conditions prevailing in the Indian real estate sector, which have materially affected the execution of the project. 3. The overall slowdown in the real estate market, coupled with shortage of labour, s…".
What is the RERA number of Gaurav Excellency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gaurav Excellency in Harkesh Uday Nagar, Thane is P51700006232.
Is Gaurav Excellency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Excellency is registered as P51700006232 and its status is "Registered and active".
What is the construction status of Gaurav Excellency?
According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Excellency's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 77.91% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does Gaurav Excellency have complaints on MahaRERA?
35 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Gaurav Excellency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Excellency is registered on MahaRERA as P51700006232, its completion date has moved 39 months since registration and 35 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Gaurav Excellency's possession date changes?
The latest dates are on Gaurav Excellency's MahaRERA page (P51700006232). GharKundli's Kundli Watch sends a free WhatsApp update on Gaurav Excellency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Gaurav Excellency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Excellency has 5 buildings filed: Building No 5 with 27 floors and 123 units; Building no 6 with 27 floors and 123 units; Building No 7 with 27 floors and 81 units; Building No 8 with 27 floors and 81 units; Building No 9 with 27 floors and 81 units.
How big is the land of Gaurav Excellency?
According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Excellency stands on 11,682 sq m of land (about 2.9 acres), with 10,683 sq m of sanctioned built-up area and 629 sq m of recreational open space.
What is the track record of Gaurav Excellency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 4 finished, all within the promised date; 15 still being built, 8 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Gaurav Excellency?
Google Maps has reviews of Gaurav Excellency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 35 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Gaurav Excellency?
Gaurav Excellency by Ravi Developments is in Harkesh Uday Nagar, Thane (pincode 400107), near Mira Road, Village Ghodbunder, Vinay Nagar, Maharashtra, and is registered on MahaRERA as P51700006232, per GharKundli's check of MahaRERA records.
How many homes are in Gaurav Excellency?
According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Excellency has 489 homes in 5 towers registered on MahaRERA, and 76% of them are sold or booked.
When was Gaurav Excellency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Excellency was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Gaurav Excellency?
No court cases are listed for Gaurav Excellency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Gaurav Excellency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ravi Developments, which has 13 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Gaurav Excellency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
Other projects by Ravi Developments
All Thane projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.