by Ravi Developments · Near GCC Club, ThaneAlso near Mira Road East, Bhayander, Village Navghar

Possession date of Gaurav Crest: 30 June 2026, moved from 30 December 2023 (30 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700004316. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (June 2026) has passed.

What do you want to know about Gaurav Crest?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Gaurav Crest has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51700018287)

    Reason the builder gave MahaRERA:
    “The project was impacted by the COVID-19 outbreak in 2020 and 2021, and the subsequent slow market conditions and labour shortages made it difficult for us to complete the project on time. Therefore, we are requesting an extension of time w…” Read the full reason“The project was impacted by the COVID-19 outbreak in 2020 and 2021, and the subsequent slow market conditions and labour shortages made it difficult for us to complete the project on time. Therefore, we are requesting an extension of time within which the project shall be completed by the promoter to 31st December 2024.”
  3. 30 June 2026

    Extended at the builder's request (MahaRERA application EXT51700027246)

    Reason the builder gave MahaRERA:
    “The project is under construction but because of the following reasons we could not get the project finally completed: 1. The promoter has suffered from financial difficulties due to adverse economic condition in the Indian Real Estate Mark…” Read the full reason“The project is under construction but because of the following reasons we could not get the project finally completed: 1. The promoter has suffered from financial difficulties due to adverse economic condition in the Indian Real Estate Market. 2. The Parliamentary General election – 2024 & Maharashtra Assembly election - 2024 caused the halt to construction activities due to the absence of Staff. 3. The promoter was not able to procure the skilled labour for the construction due to unfavourable labour market, whereby the labour migrated to their home state to exercise their electoral franch…”

Source: Gaurav Crest’s extension records on MahaRERA (P51700004316), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Gaurav Crest

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700004316
Status
Lapsed (registration period ended)
Builder
Ravi Developments
Location
Near GCC Club, Thane · 400107
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
December 2023
Latest completion date
June 2026
Delay so far
30 months
Homes
157
Sold or booked
97%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
13

Construction progress of Gaurav Crest, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Gaurav Crest100%100%100%73.57%

Commencement certificate (CC), as filed on MahaRERA

  • Gaurav Crest: covers 22 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gaurav Crest every month.

Gaurav Crest: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 4 finished, all within the promised date; 15 still being built, 8 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects.

Read Google reviews of Gaurav Crest →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Gaurav Crest: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Gaurav Crest

What is the possession date of Gaurav Crest?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gaurav Crest in Near GCC Club, Thane is 30 June 2026 — 30 months later than 30 December 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Gaurav Crest?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Gaurav Crest's builder has filed on MahaRERA, the official one, is 30 June 2026, already 30 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Gaurav Crest extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Crest's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2024, giving the reason "The project was impacted by the COVID-19 outbreak in 2020 and 2021, and the subsequent slow market conditions and labour shortages made it difficult for us to complete the project on time. Therefore, we are requesting an extension of time within which the project shall be completed by the promoter to 31st December 2024."; to 30 June 2026, giving the reason "The project is under construction but because of the following reasons we could not get the project finally completed: 1. The promoter has suffered from financial difficulties due to adverse economic condition in the Indian Real Estate Market. 2. The Parliamentary General election – 2024 & Maharashtra Assembly election - 2024 caused the halt to construction activities due to the absence of Staff. 3. The promoter was not able to procure the skilled labour for the construction due to unfavourable labour market, whereby the labour migrated to their home state to exercise their electoral franch…".

What is the RERA number of Gaurav Crest?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gaurav Crest in Near GCC Club, Thane is P51700004316.

Is Gaurav Crest registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Crest is registered as P51700004316 and its status is "Lapsed (registration period ended)".

What is the construction status of Gaurav Crest?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Crest's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Gaurav Crest is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Gaurav Crest have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Gaurav Crest safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Crest is registered on MahaRERA as P51700004316, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Gaurav Crest's possession date changes?

The latest dates are on Gaurav Crest's MahaRERA page (P51700004316). GharKundli's Kundli Watch sends a free WhatsApp update on Gaurav Crest every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Gaurav Crest have?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Crest has one building filed: Gaurav Crest with 24 floors and 159 units.

How big is the land of Gaurav Crest?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Crest stands on 611 sq m of land (about 0.2 acres), with 961 sq m of sanctioned built-up area.

What is the track record of Gaurav Crest's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 4 finished, all within the promised date; 15 still being built, 8 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Gaurav Crest?

Google Maps has reviews of Gaurav Crest written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Gaurav Crest?

Gaurav Crest by Ravi Developments is in Near GCC Club, Thane (pincode 400107), near Mira Road East, Bhayander, Village Navghar, Maharashtra, and is registered on MahaRERA as P51700004316, per GharKundli's check of MahaRERA records.

How many homes are in Gaurav Crest?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Crest has 157 homes in 1 tower registered on MahaRERA, and 97% of them are sold or booked.

When was Gaurav Crest registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaurav Crest was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Gaurav Crest?

No court cases are listed for Gaurav Crest on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Gaurav Crest?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ravi Developments, which has 13 other projects registered on MahaRERA.