The Oasis
by M/s. Universal Infra Developers · Parsik Hill, ThaneAlso near CBD Belapur, Vashi, Agroli Belapur
Possession: The Oasis is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700004362. Status: Completed. 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about The Oasis?
How the possession date of The Oasis has moved
30 April 2020
Completion date given when the project was registered
31 October 2021
Extended at the builder's request (MahaRERA application EXT51700009098)
Reason the builder gave MahaRERA:
“We have obtained consent u/s 7(3) from the Association of Allottee being registered society. Kindly note that construction of the building is fully completed and Occupancy Certificate is held up owing to certain technical reasons and now we…” Read the full reason
“We have obtained consent u/s 7(3) from the Association of Allottee being registered society. Kindly note that construction of the building is fully completed and Occupancy Certificate is held up owing to certain technical reasons and now we are expecting to get Occupancy Certificate on or before 31st October, 2021. Kindly, therefore, grant us extension u/s 7(3) of the Act which is duly supported by majority resolution of associatio of allottees.”30 April 2022
Revised completion date on MahaRERA
Source: The Oasis’s extension records on MahaRERA (P51700004362), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on The Oasis
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints and 2 court cases, and how it ended
- Construction pace against the April 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700004362
- Status
- Completed
- Builder
- M/s. Universal Infra Developers
- Location
- Parsik Hill, Thane · 400614
- Project type
- Others
- Registered on
- 9 Aug 2017
- Completion date at registration
- April 2020
- Latest completion date
- April 2022
- Delay so far
- 24 months
- Homes
- 90
- Towers
- 4
- Complaints on MahaRERA
- 5
- Court cases listed
- 2
- Appeals at the tribunal
- 2
- Title report on file
- Not found
Construction progress of The Oasis, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A | 100% | 100% | 80% | 90% |
| Wing B | 100% | 100% | 80% | 90% |
| Wing C | 100% | 100% | 80% | 90% |
| Commercial building | 100% | 100% | 80% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Oasis every month.
The Oasis: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing A (17 floors) · Wing B (18 floors) · Wing C (18 floors) · Commercial building (2 floors)
- Land: 3,680 sq m (about 0.9 acres) · sanctioned built-up 5,506 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of The Oasis →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
The Oasis: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about The Oasis
What is the possession date of The Oasis?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for The Oasis in Parsik Hill, Thane is 30 April 2022 — 24 months later than 30 April 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for The Oasis?
Builders and listing sites often quote an earlier "target" date for handover. The completion date The Oasis's builder has filed on MahaRERA, the official one, is 30 April 2022, already 24 months later than the 30 April 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of The Oasis extended?
According to GharKundli's check of MahaRERA records (updated November 2026), The Oasis's builder applied to MahaRERA to extend the completion date once: to 31 October 2021, giving the reason "We have obtained consent u/s 7(3) from the Association of Allottee being registered society. Kindly note that construction of the building is fully completed and Occupancy Certificate is held up owing to certain technical reasons and now we are expecting to get Occupancy Certificate on or before 31st October, 2021. Kindly, therefore, grant us extension u/s 7(3) of the Act which is duly supported by majority resolution of associatio of allottees.".
What is the RERA number of The Oasis?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of The Oasis in Parsik Hill, Thane is P51700004362.
Is The Oasis registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Oasis is registered as P51700004362 and its status is "Completed".
What is the construction status of The Oasis?
According to GharKundli's check of MahaRERA records (updated November 2026), The Oasis's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does The Oasis have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is The Oasis safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), The Oasis is registered on MahaRERA as P51700004362, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if The Oasis's possession date changes?
The latest dates are on The Oasis's MahaRERA page (P51700004362). GharKundli's Kundli Watch sends a free WhatsApp update on The Oasis every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does The Oasis have?
According to GharKundli's check of MahaRERA records (updated November 2026), The Oasis has 4 buildings filed: Wing A with 17 floors; Wing B with 18 floors; Wing C with 18 floors; Commercial building with 2 floors.
How big is the land of The Oasis?
According to GharKundli's check of MahaRERA records (updated November 2026), The Oasis stands on 3,680 sq m of land (about 0.9 acres), with 5,506 sq m of sanctioned built-up area.
Where can I read reviews of The Oasis?
Google Maps has reviews of The Oasis written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is The Oasis?
The Oasis by M/s. Universal Infra Developers is in Parsik Hill, Thane (pincode 400614), near CBD Belapur, Vashi, Agroli Belapur, Maharashtra, and is registered on MahaRERA as P51700004362, per GharKundli's check of MahaRERA records.
How many homes are in The Oasis?
According to GharKundli's check of MahaRERA records (updated November 2026), The Oasis has 90 homes in 4 towers registered on MahaRERA.
When was The Oasis registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Oasis was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on The Oasis?
2 court cases are listed for The Oasis on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of The Oasis?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/s. Universal Infra Developers.
Check it yourself on MahaRERA
- How to check the possession date of The Oasis
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- MAULI KRUPA
- GURUKRUPA NITYAM
- ASAVARI CO OP HSG SOC LTD
- Mahavir Breeze Phase 1
- Panache
- LOTUS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.