KARRM PANCHTATVA - 2

by KARRM INFRASTRUCTURE PRIVATE LIMITED · Shahapur S.O (Thane), Thane

Possession date of KARRM PANCHTATVA - 2: 30 December 2022. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700010325. Status: Lapsed (registration period ended). 39 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2022) has passed.

What do you want to know about KARRM PANCHTATVA - 2?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on KARRM PANCHTATVA - 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 39 complaints, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700010325
Status
Lapsed (registration period ended)
Builder
KARRM INFRASTRUCTURE PRIVATE LIMITED
Location
Shahapur S.O (Thane), Thane · 421601
Project type
Residential / Group Housing
Registered on
24 Aug 2017
Completion date at registration
December 2022
Latest completion date
December 2022
Homes
4,128
Towers
53
Complaints on MahaRERA
39
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of KARRM PANCHTATVA - 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A10%0%0%0%
A20%0%0%0%
A3100%90%0%0%
A40%0%0%0%
A100%0%0%0%
A110%0%0%0%
B10%0%0%0%
B20%0%0%0%
B30%0%0%0%
C50%0%0%0%
D590%0%0%0%
D8100%0%0%0%
D1290%0%0%0%
E590%0%0%0%
E60%0%0%0%
E70%0%0%0%
E80%0%0%0%
G30%0%0%0%
F250%0%0%0%
G60%0%0%0%
G70%0%0%0%
A60%0%0%0%
A70%0%0%0%
A860%0%0%0%
A90%0%0%0%
B40%0%0%0%
B50%0%0%0%
B60%0%0%0%
C1100%0%0%0%
C20%0%0%0%

Showing 30 of 53 towers.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KARRM PANCHTATVA - 2 every month.

KARRM PANCHTATVA - 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: A1 (5 floors) · A2 (5 floors) · A3 (5 floors) · A4 (5 floors) · A10 (5 floors) · A11 (5 floors) · B1 (5 floors) · B2 (5 floors) · and 22 more
  • Land: 1,00,373 sq m (about 24.8 acres) · sanctioned built-up 94,280 sq m · recreational space 10,037 sq m

The builder’s record and reviews

Karrm Infrastructure has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 5 lapsed. 140 complaints on MahaRERA across 5 projects.

Read Google reviews of KARRM PANCHTATVA - 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KARRM PANCHTATVA - 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KARRM PANCHTATVA - 2

What is the possession date of KARRM PANCHTATVA - 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KARRM PANCHTATVA - 2 in Shahapur S.O (Thane), Thane is 30 December 2022. That date has already passed.

Is the builder's possession date different from the MahaRERA date for KARRM PANCHTATVA - 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KARRM PANCHTATVA - 2's builder has filed on MahaRERA, the official one, is 30 December 2022, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of KARRM PANCHTATVA - 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KARRM PANCHTATVA - 2 in Shahapur S.O (Thane), Thane is P51700010325.

Is KARRM PANCHTATVA - 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KARRM PANCHTATVA - 2 is registered as P51700010325 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of KARRM PANCHTATVA - 2?

According to GharKundli's check of MahaRERA records (updated November 2026), KARRM PANCHTATVA - 2's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 90% across 30 towers. GharKundli's full report compares construction progress with the deadline.

Does KARRM PANCHTATVA - 2 have complaints on MahaRERA?

39 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is KARRM PANCHTATVA - 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), KARRM PANCHTATVA - 2 is registered on MahaRERA as P51700010325, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder, 39 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does KARRM PANCHTATVA - 2 have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: KARRM PANCHTATVA -1 (P51700009304, possession 30 Oct 2020); KARRM PANCHTATVA-3 (P51700007680, possession 30 Dec 2023). Check that your agreement names the registration of your own wing.

How can I get updates if KARRM PANCHTATVA - 2's possession date changes?

The latest dates are on KARRM PANCHTATVA - 2's MahaRERA page (P51700010325). GharKundli's Kundli Watch sends a free WhatsApp update on KARRM PANCHTATVA - 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KARRM PANCHTATVA - 2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), KARRM PANCHTATVA - 2 has 30 buildings filed: A1 with 5 floors; A2 with 5 floors; A3 with 5 floors; A4 with 5 floors; A10 with 5 floors; A11 with 5 floors; and 24 more.

How big is the land of KARRM PANCHTATVA - 2?

According to GharKundli's check of MahaRERA records (updated November 2026), KARRM PANCHTATVA - 2 stands on 1,00,373 sq m of land (about 24.8 acres), with 94,280 sq m of sanctioned built-up area and 10,037 sq m of recreational open space.

What is the track record of KARRM PANCHTATVA - 2's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Karrm Infrastructure has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 5 lapsed. 140 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of KARRM PANCHTATVA - 2?

Google Maps has reviews of KARRM PANCHTATVA - 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 39 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KARRM PANCHTATVA - 2?

KARRM PANCHTATVA - 2 by KARRM INFRASTRUCTURE PRIVATE LIMITED is in Shahapur S.O (Thane), Thane (pincode 421601), Maharashtra, and is registered on MahaRERA as P51700010325, per GharKundli's check of MahaRERA records.

How many homes are in KARRM PANCHTATVA - 2?

According to GharKundli's check of MahaRERA records (updated November 2026), KARRM PANCHTATVA - 2 has 4,128 homes in 53 towers registered on MahaRERA.

When was KARRM PANCHTATVA - 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KARRM PANCHTATVA - 2 was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on KARRM PANCHTATVA - 2?

No court cases are listed for KARRM PANCHTATVA - 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of KARRM PANCHTATVA - 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KARRM INFRASTRUCTURE PRIVATE LIMITED, which has 4 other projects registered on MahaRERA.

Other projects in pincode 421601

All 184 projects in Shahapur (421601) →

Other projects by KARRM INFRASTRUCTURE PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.