KARRM RESIDENCY -4
by KARRM INFRASTRUCTURE PRIVATE LIMITED · Shahapur S.O (Thane), Thane
Possession date of KARRM RESIDENCY -4: 30 November 2020, moved from 31 May 2019 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700003215. Status: Lapsed (registration period ended). 47 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (November 2020) has passed.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about KARRM RESIDENCY -4?
How the possession date of KARRM RESIDENCY -4 has moved
31 May 2019
Completion date given when the project was registered
31 May 2020
Extended at the builder's request (MahaRERA application EXT51700001826)
Reason the builder gave MahaRERA:
“We state that due to unavoidable circumstances and that to beyond the control of the promoter we shall be unable to deliver the above mentioned project or on before 31/05/2019 as per registration granted under section 5 of the Real Estate (…” Read the full reason
“We state that due to unavoidable circumstances and that to beyond the control of the promoter we shall be unable to deliver the above mentioned project or on before 31/05/2019 as per registration granted under section 5 of the Real Estate (regulation and Development) Act,2016.further ,adding to that due to lack of liquidity and defaulter allottees we are lagging behind to complete the project or on before 31/05/2019. We expect to deliver the project on or before 31/05/2020”30 November 2020
Revised completion date on MahaRERA
Source: KARRM RESIDENCY -4’s extension records on MahaRERA (P51700003215), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KARRM RESIDENCY -4
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 47 complaints and 1 court case, and how it ended
- Construction pace against the November 2020 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700003215
- Status
- Lapsed (registration period ended)
- Builder
- KARRM INFRASTRUCTURE PRIVATE LIMITED
- Location
- Shahapur S.O (Thane), Thane · 421601
- Project type
- Residential / Group Housing
- Registered on
- 5 Aug 2017
- Completion date at registration
- May 2019
- Latest completion date
- November 2020
- Delay so far
- 18 months
- Homes
- 740
- Towers
- 14
- Complaints on MahaRERA
- 47
- Court cases listed
- 1
- Appeals at the tribunal
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of KARRM RESIDENCY -4, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DARPAN | 100% | 100% | 90% | 0% |
| SATHI | 100% | 100% | 85% | 0% |
| AAZAD | 100% | 100% | 85% | 0% |
| ANURODH | 100% | 100% | 85% | 0% |
| ANCHAL | 100% | 100% | 80% | 0% |
| ANDAAZ | 100% | 100% | 85% | 0% |
| AMRIT | 100% | 100% | 85% | 0% |
| SANGAM | 100% | 100% | 95% | 0% |
| PAWAN | 100% | 100% | 95% | 0% |
| NASEEB | 100% | 100% | 85% | 0% |
| ZINDAGI | 100% | 100% | 90% | 0% |
| KRANTI | 100% | 100% | 95% | 20% |
| ARPAN | 100% | 100% | 85% | 0% |
| JYOTI | 100% | 100% | 90% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KARRM RESIDENCY -4 every month.
KARRM RESIDENCY -4: buildings, flats and land, as filed on MahaRERA
- Buildings: DARPAN (5 floors) · SATHI (5 floors) · AAZAD (5 floors) · ANURODH (5 floors) · ANCHAL (5 floors) · ANDAAZ (5 floors) · AMRIT (5 floors) · SANGAM (5 floors) · and 6 more
- Land: 36,867 sq m (about 9.1 acres) · sanctioned built-up 30,605 sq m · recreational space 22,208 sq m
The builder’s record and reviews
Karrm Infrastructure has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 5 lapsed. 140 complaints on MahaRERA across 5 projects.
Read Google reviews of KARRM RESIDENCY -4 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KARRM RESIDENCY -4: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KARRM RESIDENCY -4
What is the possession date of KARRM RESIDENCY -4?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KARRM RESIDENCY -4 in Shahapur S.O (Thane), Thane is 30 November 2020 — 18 months later than 31 May 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for KARRM RESIDENCY -4?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KARRM RESIDENCY -4's builder has filed on MahaRERA, the official one, is 30 November 2020, already 18 months later than the 31 May 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KARRM RESIDENCY -4 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), KARRM RESIDENCY -4's builder applied to MahaRERA to extend the completion date once: to 31 May 2020, giving the reason "We state that due to unavoidable circumstances and that to beyond the control of the promoter we shall be unable to deliver the above mentioned project or on before 31/05/2019 as per registration granted under section 5 of the Real Estate (regulation and Development) Act,2016.further ,adding to that due to lack of liquidity and defaulter allottees we are lagging behind to complete the project or on before 31/05/2019. We expect to deliver the project on or before 31/05/2020".
What is the RERA number of KARRM RESIDENCY -4?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KARRM RESIDENCY -4 in Shahapur S.O (Thane), Thane is P51700003215.
Is KARRM RESIDENCY -4 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KARRM RESIDENCY -4 is registered as P51700003215 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of KARRM RESIDENCY -4?
According to GharKundli's check of MahaRERA records (updated November 2026), KARRM RESIDENCY -4's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 14 towers. GharKundli's full report compares construction progress with the deadline.
Does KARRM RESIDENCY -4 have complaints on MahaRERA?
47 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is KARRM RESIDENCY -4 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), KARRM RESIDENCY -4 is registered on MahaRERA as P51700003215, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration, 47 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KARRM RESIDENCY -4's possession date changes?
The latest dates are on KARRM RESIDENCY -4's MahaRERA page (P51700003215). GharKundli's Kundli Watch sends a free WhatsApp update on KARRM RESIDENCY -4 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KARRM RESIDENCY -4 have?
According to GharKundli's check of MahaRERA records (updated November 2026), KARRM RESIDENCY -4 has 14 buildings filed: DARPAN with 5 floors; SATHI with 5 floors; AAZAD with 5 floors; ANURODH with 5 floors; ANCHAL with 5 floors; ANDAAZ with 5 floors; and 8 more.
How big is the land of KARRM RESIDENCY -4?
According to GharKundli's check of MahaRERA records (updated November 2026), KARRM RESIDENCY -4 stands on 36,867 sq m of land (about 9.1 acres), with 30,605 sq m of sanctioned built-up area and 22,208 sq m of recreational open space.
What is the track record of KARRM RESIDENCY -4's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Karrm Infrastructure has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 5 lapsed. 140 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of KARRM RESIDENCY -4?
Google Maps has reviews of KARRM RESIDENCY -4 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 47 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KARRM RESIDENCY -4?
KARRM RESIDENCY -4 by KARRM INFRASTRUCTURE PRIVATE LIMITED is in Shahapur S.O (Thane), Thane (pincode 421601), Maharashtra, and is registered on MahaRERA as P51700003215, per GharKundli's check of MahaRERA records.
How many homes are in KARRM RESIDENCY -4?
According to GharKundli's check of MahaRERA records (updated November 2026), KARRM RESIDENCY -4 has 740 homes in 14 towers registered on MahaRERA.
When was KARRM RESIDENCY -4 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KARRM RESIDENCY -4 was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on KARRM RESIDENCY -4?
1 court case is listed for KARRM RESIDENCY -4 on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of KARRM RESIDENCY -4?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KARRM INFRASTRUCTURE PRIVATE LIMITED, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of KARRM RESIDENCY -4
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 421601
- MIRADOR UTSAV PHASE 1
- Aghav Resideny
- CHINTAMANI MEADOWS
- ICON APARTMENT
- Pitruchhaya Apartment
- Visava
- SAI ANAND APARTMENT
- CHINTAMANI HABITAT (FORTUNA BUNGALOW)
Other projects by KARRM INFRASTRUCTURE PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.