by Tejas Tarun Vyas · Nr. St. Xaviers School, ThaneAlso near Mira Road East

Possession date of Foresta: 31 December 2027, moved from 30 December 2022 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800008744, and currently active. 20 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Foresta?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Foresta has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51700011396)

    Reason the builder gave MahaRERA:
    “Dear Authority, This is with reference to our Ongoing Project Named: Foresta situated at Plot Bearing /CTS/ Survey / Final Plot No. 89/1 at Kashigaon Mira Road East Mira¬Bhayandar (M Corp.), Thane, Thane, 401107. With MAHARERA Registration…” Read the full reason“Dear Authority, This is with reference to our Ongoing Project Named: Foresta situated at Plot Bearing /CTS/ Survey / Final Plot No. 89/1 at Kashigaon Mira Road East Mira¬Bhayandar (M Corp.), Thane, Thane, 401107. With MAHARERA Registration No. P51800008744. We request you to grant the extension to the above-mentioned project from 30th Dec 2022 to 31st Dec 2023. Herewith this letter we inform you that Because of the hardship of plot is causing hardship in the construction activities & agencies are not been able to work simultaneously thus we need more time to complete the project, As a resul…”
  3. 31 December 2027

    Extended at the builder's request (MahaRERA application EXT51700018665)

    Reason the builder gave MahaRERA:
    “To, Maharashtra Real Estate Regulatory Authority, Mumbai, Maharashtra Dear Authority, This is with reference to our Ongoing Project Named: Foresta situated at Plot Bearing /CTS/ Survey / Final Plot No. 89/1 at Kashigaon Mira Road East Mira¬…” Read the full reason“To, Maharashtra Real Estate Regulatory Authority, Mumbai, Maharashtra Dear Authority, This is with reference to our Ongoing Project Named: Foresta situated at Plot Bearing /CTS/ Survey / Final Plot No. 89/1 at Kashigaon Mira Road East Mira¬Bhayandar (M Corp.), Thane, Thane, 401107. With MAHARERA Registration No. P51800008744. We request you to grant the extension to the above-mentioned project from 30th Dec 2023 to 31st Dec 2027. Herewith this letter we inform you that Because of the hardship of plot is causing hardship in the construction activities & agencies are not been able to work sim…”

Source: Foresta’s extension records on MahaRERA (P51800008744), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Foresta

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 20 complaints, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800008744
Status
Registered and active
Builder
Tejas Tarun Vyas
Location
Nr. St. Xaviers School, Thane · 401107
Project type
Others
Registered on
19 Aug 2017
Completion date at registration
December 2022
Latest completion date
December 2027
Delay so far
60 months
Homes
230
Sold or booked
11%
Towers
2
Complaints on MahaRERA
20
Court cases listed
0
Appeals at the tribunal
10
Title report on file
Not found

Construction progress of Foresta, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building 1100%25%12%0%
Building 2100%25%12%0%

Commencement certificate (CC), as filed on MahaRERA

  • Building 1: covers 10TH FLOORS
  • Building 2: covers 9th Floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Foresta every month.

Foresta: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Foresta →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Foresta: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Foresta

What is the possession date of Foresta?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Foresta in Nr. St. Xaviers School, Thane is 31 December 2027 — 60 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Foresta?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Foresta's builder has filed on MahaRERA, the official one, is 31 December 2027, already 60 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Foresta extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Foresta's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2023, giving the reason "Dear Authority, This is with reference to our Ongoing Project Named: Foresta situated at Plot Bearing /CTS/ Survey / Final Plot No. 89/1 at Kashigaon Mira Road East Mira¬Bhayandar (M Corp.), Thane, Thane, 401107. With MAHARERA Registration No. P51800008744. We request you to grant the extension to the above-mentioned project from 30th Dec 2022 to 31st Dec 2023. Herewith this letter we inform you that Because of the hardship of plot is causing hardship in the construction activities & agencies are not been able to work simultaneously thus we need more time to complete the project, As a resul…"; to 31 December 2027, giving the reason "To, Maharashtra Real Estate Regulatory Authority, Mumbai, Maharashtra Dear Authority, This is with reference to our Ongoing Project Named: Foresta situated at Plot Bearing /CTS/ Survey / Final Plot No. 89/1 at Kashigaon Mira Road East Mira¬Bhayandar (M Corp.), Thane, Thane, 401107. With MAHARERA Registration No. P51800008744. We request you to grant the extension to the above-mentioned project from 30th Dec 2023 to 31st Dec 2027. Herewith this letter we inform you that Because of the hardship of plot is causing hardship in the construction activities & agencies are not been able to work sim…".

What is the RERA number of Foresta?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Foresta in Nr. St. Xaviers School, Thane is P51800008744.

Is Foresta registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Foresta is registered as P51800008744 and its status is "Registered and active".

What is the construction status of Foresta?

According to GharKundli's check of MahaRERA records (updated October 2026), Foresta's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 25% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Foresta have complaints on MahaRERA?

20 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Foresta safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Foresta is registered on MahaRERA as P51800008744, its completion date has moved 60 months since registration and 20 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Foresta's possession date changes?

The latest dates are on Foresta's MahaRERA page (P51800008744). GharKundli's Kundli Watch sends a free WhatsApp update on Foresta every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Foresta have?

According to GharKundli's check of MahaRERA records (updated October 2026), Foresta has 2 buildings filed: Building 1 with 29 floors and 120 units; Building 2 with 29 floors and 120 units.

How big is the land of Foresta?

According to GharKundli's check of MahaRERA records (updated October 2026), Foresta stands on 1,156 sq m of land (about 0.3 acres), with 7,708 sq m of sanctioned built-up area.

Where can I read reviews of Foresta?

Google Maps has reviews of Foresta written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 20 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Foresta?

Foresta by Tejas Tarun Vyas is in Nr. St. Xaviers School, Thane (pincode 401107), near Mira Road East, Maharashtra, and is registered on MahaRERA as P51800008744, per GharKundli's check of MahaRERA records.

How many homes are in Foresta?

According to GharKundli's check of MahaRERA records (updated October 2026), Foresta has 230 homes in 2 towers registered on MahaRERA, and 11% of them are sold or booked.

When was Foresta registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Foresta was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Foresta?

No court cases are listed for Foresta on MahaRERA, and 10 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Foresta?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Tejas Tarun Vyas.

All projects with possession due in 2027 in Thane →

Other projects in Thane

All 322 projects in Mira Road East (401107) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.