Possession date of Crystal Homes: 30 December 2023. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700007282. Status: Lapsed (registration period ended). 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about Crystal Homes?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Crystal Homes

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700007282
Status
Lapsed (registration period ended)
Builder
Shreedham Construction Private Limited
Location
Chincholi Bunder, Thane · 421401
Project type
Plotted
Registered on
17 Aug 2017
Completion date at registration
December 2023
Latest completion date
December 2023
Complaints on MahaRERA
4
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
2

Crystal Homes: buildings, flats and land, as filed on MahaRERA

  • Land: 36,423 sq m (about 9.0 acres) · recreational space 4,461 sq m

The builder’s record and reviews

Shreedham Construction (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 2 still being built, none past the promised date yet; 3 lapsed. 14 complaints on MahaRERA across 5 projects.

Read Google reviews of Crystal Homes →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Crystal Homes: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Crystal Homes

What is the possession date of Crystal Homes?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Crystal Homes in Chincholi Bunder, Thane is 30 December 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Crystal Homes?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Crystal Homes's builder has filed on MahaRERA, the official one, is 30 December 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Crystal Homes?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Crystal Homes in Chincholi Bunder, Thane is P51700007282.

Is Crystal Homes registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Crystal Homes is registered as P51700007282 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of Crystal Homes?

According to GharKundli's check of MahaRERA records (updated November 2026), Crystal Homes's status on MahaRERA is "Lapsed (registration period ended)". GharKundli's full report compares construction progress with the deadline.

Does Crystal Homes have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Crystal Homes safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Crystal Homes is registered on MahaRERA as P51700007282, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder, 4 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Crystal Homes's possession date changes?

The latest dates are on Crystal Homes's MahaRERA page (P51700007282). GharKundli's Kundli Watch sends a free WhatsApp update on Crystal Homes every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Crystal Homes?

According to GharKundli's check of MahaRERA records (updated November 2026), Crystal Homes stands on 36,423 sq m of land (about 9.0 acres) and 4,461 sq m of recreational open space.

What is the track record of Crystal Homes's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Shreedham Construction (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 2 still being built, none past the promised date yet; 3 lapsed. 14 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Crystal Homes?

Google Maps has reviews of Crystal Homes written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Crystal Homes?

Crystal Homes by Shreedham Construction Private Limited is in Chincholi Bunder, Thane (pincode 421401), Maharashtra, and is registered on MahaRERA as P51700007282, per GharKundli's check of MahaRERA records.

When was Crystal Homes registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Crystal Homes was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Crystal Homes?

No court cases are listed for Crystal Homes on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Crystal Homes?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shreedham Construction Private Limited, which has 2 other projects registered on MahaRERA.

Other projects in Murbad

All 42 projects in Murbad (421401) →

Other projects by Shreedham Construction Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.