GALAXY WING 5
by BRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED · Padale Village, ThaneAlso near Manpada, Vishnunagar
Possession date of GALAXY WING 5: 31 December 2025, moved from 31 December 2019 (72 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700009788. Status: Lapsed (registration period ended). 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about GALAXY WING 5?
How the possession date of GALAXY WING 5 has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51700005078)
Reason the builder gave MahaRERA:
“Paucity of funds on account of lack of sales of unsold inventory owned by Company and delay in receipt of outstanding payments due and payable by purchasers towards at the time of handover of their alloted units in building no.1 & 2. Since…” Read the full reason
“Paucity of funds on account of lack of sales of unsold inventory owned by Company and delay in receipt of outstanding payments due and payable by purchasers towards at the time of handover of their alloted units in building no.1 & 2. Since July 2017, the Company has witnessed lack luster sales which has burdened the Company financial position. The said sub sequence of events had the Company in turbulent financial situation and on the verge of Bankruptcy. Nonetheless the Company in tireless working of the option to shore up funds to aid the completion of building no.5 , a fact established be…”30 June 2023
Extended at the builder's request (MahaRERA application EXT51700010126)
Reason the builder gave MahaRERA:
“We sought an extension for project completion due to the main reason listed below: 1. Our project is badly affected by Covid impact. 2. Due to Skilled labour unavailability and labour migration issues, project is affected a lot. Even contra…” Read the full reason
“We sought an extension for project completion due to the main reason listed below: 1. Our project is badly affected by Covid impact. 2. Due to Skilled labour unavailability and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. 3. Customers are also facing financial problems There are huge receivable from the customers but we are unable to receive the same, which in turn has affected our financial position as well. Customers and we both are highly affected in last 1 and half year. 4. Even there is a long delay fro…”30 June 2024
Extended at the builder's request (MahaRERA application EXT51700017529)
Reason the builder gave MahaRERA:
“The project got delayed due to delay in collection of Sales receivable and delay in sales of unsold units. Due to this financial issues, vendor and supplier payments got delayed. Due to non-receipt of timely payments suppliers/vendors have…” Read the full reason
“The project got delayed due to delay in collection of Sales receivable and delay in sales of unsold units. Due to this financial issues, vendor and supplier payments got delayed. Due to non-receipt of timely payments suppliers/vendors have also not completed the activities on time. Therefore, project could not be completed as planned. We have obtained consent from allottees for project extension. Requesting you to grant the extension. Thanking you”30 June 2025
Extended at the builder's request (MahaRERA application EXT51700025106)
Reason the builder gave MahaRERA:
“We are facing hindrance for construction work of Building 5 of project galaxy, due to various issues raised by landlords and legal proceedings in court of law from first notice served by their Advocate Mr. Nitin Mhatre on 28.11.2022. They i…” Read the full reason
“We are facing hindrance for construction work of Building 5 of project galaxy, due to various issues raised by landlords and legal proceedings in court of law from first notice served by their Advocate Mr. Nitin Mhatre on 28.11.2022. They instituted a Special Civil Suit against us in the month of August 2023 in the court of 3rd Joint Civil judge Senior Division Thane. Further They served Notice of demand for Rs. 15000000/- we moved to Mumbai High Court for appointment of arbitrator under section 9 and section 17. The Honorable High Court has passed an order for appointment of Arbitrator on…”31 December 2025
Extended at the builder's request (MahaRERA application EA30112518472)
Reason the builder gave MahaRERA:
“We had faced hindrance for construction work of Building 5 of project galaxy, due to various issues raised by landlords and legal proceedings in court of law from first notice served by their Advocate Mr. Nitin Mhatre on 28.11.2022. They in…” Read the full reason
“We had faced hindrance for construction work of Building 5 of project galaxy, due to various issues raised by landlords and legal proceedings in court of law from first notice served by their Advocate Mr. Nitin Mhatre on 28.11.2022. They instituted a Special Civil Suit against us in the month of August 2023 in the court of 3rd Joint Civil judge Senior Division Thane. Further They served Notice of demand for Rs. 15000000/- we moved to Mumbai High Court for appointment of arbitrator under section 9 and section 17. The Honorable High Court has passed an order for appointment of Arbitrator on 2…”
Source: GALAXY WING 5’s extension records on MahaRERA (P51700009788), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GALAXY WING 5
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints and 1 court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- GALAXY BLDG 1 AND 2P51700005683 · possession 30 Apr 2019
- MahaRERA registration
- P51700009788
- Status
- Lapsed (registration period ended)
- Builder
- BRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED
- Location
- Padale Village, Thane · 421204
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2025
- Delay so far
- 72 months
- Homes
- 77
- Sold or booked
- 97%
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 1
- Appeals at the tribunal
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of GALAXY WING 5, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GALAXY WING 5 | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- GALAXY WING 5: covers 20 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GALAXY WING 5 every month.
GALAXY WING 5: buildings, flats and land, as filed on MahaRERA
- Buildings: GALAXY WING 5 (22 floors, 77 units)
- Car parking: 24 covered, 27 open
- Land: 1,383 sq m (about 0.3 acres) · sanctioned built-up 2,924 sq m
The builder’s record and reviews
Bright SKY Heights Builders AND Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 10 months); 1 lapsed. 8 complaints on MahaRERA across 2 projects.
Read Google reviews of GALAXY WING 5 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GALAXY WING 5: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GALAXY WING 5
What is the possession date of GALAXY WING 5?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GALAXY WING 5 in Padale Village, Thane is 31 December 2025 — 72 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for GALAXY WING 5?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GALAXY WING 5's builder has filed on MahaRERA, the official one, is 31 December 2025, already 72 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GALAXY WING 5 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), GALAXY WING 5's builder applied to MahaRERA to extend the completion date 5 times: to 30 December 2020, giving the reason "Paucity of funds on account of lack of sales of unsold inventory owned by Company and delay in receipt of outstanding payments due and payable by purchasers towards at the time of handover of their alloted units in building no.1 & 2. Since July 2017, the Company has witnessed lack luster sales which has burdened the Company financial position. The said sub sequence of events had the Company in turbulent financial situation and on the verge of Bankruptcy. Nonetheless the Company in tireless working of the option to shore up funds to aid the completion of building no.5 , a fact established be…"; to 30 June 2023, giving the reason "We sought an extension for project completion due to the main reason listed below: 1. Our project is badly affected by Covid impact. 2. Due to Skilled labour unavailability and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. 3. Customers are also facing financial problems There are huge receivable from the customers but we are unable to receive the same, which in turn has affected our financial position as well. Customers and we both are highly affected in last 1 and half year. 4. Even there is a long delay fro…"; to 30 June 2024, giving the reason "The project got delayed due to delay in collection of Sales receivable and delay in sales of unsold units. Due to this financial issues, vendor and supplier payments got delayed. Due to non-receipt of timely payments suppliers/vendors have also not completed the activities on time. Therefore, project could not be completed as planned. We have obtained consent from allottees for project extension. Requesting you to grant the extension. Thanking you"; to 30 June 2025, giving the reason "We are facing hindrance for construction work of Building 5 of project galaxy, due to various issues raised by landlords and legal proceedings in court of law from first notice served by their Advocate Mr. Nitin Mhatre on 28.11.2022. They instituted a Special Civil Suit against us in the month of August 2023 in the court of 3rd Joint Civil judge Senior Division Thane. Further They served Notice of demand for Rs. 15000000/- we moved to Mumbai High Court for appointment of arbitrator under section 9 and section 17. The Honorable High Court has passed an order for appointment of Arbitrator on…"; to 31 December 2025, giving the reason "We had faced hindrance for construction work of Building 5 of project galaxy, due to various issues raised by landlords and legal proceedings in court of law from first notice served by their Advocate Mr. Nitin Mhatre on 28.11.2022. They instituted a Special Civil Suit against us in the month of August 2023 in the court of 3rd Joint Civil judge Senior Division Thane. Further They served Notice of demand for Rs. 15000000/- we moved to Mumbai High Court for appointment of arbitrator under section 9 and section 17. The Honorable High Court has passed an order for appointment of Arbitrator on 2…".
What is the RERA number of GALAXY WING 5?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GALAXY WING 5 in Padale Village, Thane is P51700009788.
Is GALAXY WING 5 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GALAXY WING 5 is registered as P51700009788 and its status is "Lapsed (registration period ended)".
What is the construction status of GALAXY WING 5?
According to GharKundli's check of MahaRERA records (updated October 2026), GALAXY WING 5's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on GALAXY WING 5 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does GALAXY WING 5 have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is GALAXY WING 5 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GALAXY WING 5 is registered on MahaRERA as P51700009788, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 72 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does GALAXY WING 5 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: GALAXY BLDG 1 AND 2 (P51700005683, possession 30 Apr 2019). Check that your agreement names the registration of your own wing.
How can I get updates if GALAXY WING 5's possession date changes?
The latest dates are on GALAXY WING 5's MahaRERA page (P51700009788). GharKundli's Kundli Watch sends a free WhatsApp update on GALAXY WING 5 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GALAXY WING 5 have?
According to GharKundli's check of MahaRERA records (updated October 2026), GALAXY WING 5 has one building filed: GALAXY WING 5 with 22 floors and 77 units.
How much parking does GALAXY WING 5 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 24 covered and 27 open car parking spaces for GALAXY WING 5.
How big is the land of GALAXY WING 5?
According to GharKundli's check of MahaRERA records (updated October 2026), GALAXY WING 5 stands on 1,383 sq m of land (about 0.3 acres), with 2,924 sq m of sanctioned built-up area.
What is the track record of GALAXY WING 5's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Bright SKY Heights Builders AND Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 10 months); 1 lapsed. 8 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of GALAXY WING 5?
Google Maps has reviews of GALAXY WING 5 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GALAXY WING 5?
GALAXY WING 5 by BRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED is in Padale Village, Thane (pincode 421204), near Manpada, Vishnunagar, Maharashtra, and is registered on MahaRERA as P51700009788, per GharKundli's check of MahaRERA records.
How many homes are in GALAXY WING 5?
According to GharKundli's check of MahaRERA records (updated October 2026), GALAXY WING 5 has 77 homes in 1 tower registered on MahaRERA, and 97% of them are sold or booked.
When was GALAXY WING 5 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GALAXY WING 5 was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on GALAXY WING 5?
1 court case is listed for GALAXY WING 5 on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of GALAXY WING 5?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of GALAXY WING 5
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 421204
- Shanti Luxuria
- Palava Fresca J-K
- YESU ANAND HEIGHTS
- Runwal Gardens Phase 4 Bldg No. 33-34
- SHREE KRISHNA HEIGHTS
- ARISTA SKYLINE
- Chanakya A wing
- Chanakya C wing
Other projects by BRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.