by TEJUKAYA CORP PRIVATE LIMITED · Lalbaug, Mumbai 400012Also near Lower Parel, Ramnagar, Pimpri

What’s in the report? →

Possession date of The Edge (MahaRERA P51900032613): 30 April 2031, moved from 31 December 2028 (24 months later). It has 363 homes (2 BHK, 3 BHK and 4 BHK, 800–2605 sq ft carpet), 63% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900032613, and currently active. Its completion date has moved from December 2028 to April 2031: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51900032613, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about The Edge?

6 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of The Edge has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 31 December 2030

    Extended at the builder's request (MahaRERA application EXT51900024247)

    Reason the builder gave MahaRERA: “The project has been transferred under section 15. Therefore, the intending promoter will complete the project latest by 31.12.2030”
  3. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: The Edge’s extension records on MahaRERA (P51900032613), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The Edge

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 6 court cases, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900032613
Status
Registered and active
Builder
TEJUKAYA CORP PRIVATE LIMITED
Location
Lalbaug, Mumbai · 400012
Project type
Others
Registered on
14 Jan 2022
Completion date at registration
December 2028
Latest completion date
April 2031
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
363
Sold or booked
63%
Towers
3
Complaints on MahaRERA
0
Court cases listed
6
Title report on file
Not found

Construction progress of The Edge, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TOWER 1100%0%0%0%
TOWER 20%0%0%0%
REHAB SALE WING100%76%20%0%

Commencement certificate (CC), as filed on MahaRERA

  • TOWER 1: covers Plinth i.e. top of 9th podium level
  • TOWER 2: covers Plinth i.e. top of 9th podium level
  • REHAB SALE WING: covers UPTO 2ND FLOOR

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Edge every 1–2 months.

The Edge: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK800 – 1,250148
3 BHK1,180 – 1,763139
4 BHK1,773 – 2,60576
Office Space55 – 48916
  • Buildings: TOWER 1 (55 floors, 228 units) · TOWER 2 (55 floors, 135 units) · REHAB SALE WING (2 floors, 16 units)
  • Car parking: 795 covered
  • Land: 10,055 sq m (about 2.5 acres) · sanctioned built-up 48,892 sq m
  • Boundaries filed include: DR BABASAHEB AMBEDKAR ROAD
  • Land, as filed: 3/52, 3A/52, 3A1/52 AND 3B/52
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Tejukaya Realty (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 18 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of The Edge →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Edge: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about The Edge

What is the possession date of The Edge?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Edge in Lalbaug, Mumbai is 30 April 2031 — 24 months later than 31 December 2028, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for The Edge?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Edge's builder has filed on MahaRERA, the official one, is 30 April 2031, already 24 months later than the 31 December 2028 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of The Edge extended?

According to GharKundli's check of MahaRERA records (updated October 2026), The Edge's builder applied to MahaRERA to extend the completion date once: to 31 December 2030, giving the reason "The project has been transferred under section 15. Therefore, the intending promoter will complete the project latest by 31.12.2030". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of The Edge?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Edge in Lalbaug, Mumbai is P51900032613.

Is The Edge registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Edge is registered as P51900032613 and its status is "Registered and active".

What is the current construction status of The Edge? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), The Edge's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 76% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does The Edge have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is The Edge safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), The Edge is registered on MahaRERA as P51900032613, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in The Edge?

The Edge is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in The Edge start at 800 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in The Edge?

For a flat in The Edge (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has The Edge received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), The Edge is still under construction, with 30 April 2031 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has The Edge uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for The Edge was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if The Edge's possession date changes?

The latest dates are on The Edge's MahaRERA page (P51900032613). GharKundli's Kundli Watch sends a free WhatsApp update on The Edge every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Edge have?

According to GharKundli's check of MahaRERA records (updated October 2026), The Edge has 3 buildings filed: TOWER 1 with 55 floors and 228 units; TOWER 2 with 55 floors and 135 units; REHAB SALE WING with 2 floors and 16 units.

What are the flat sizes (carpet area) in The Edge?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for The Edge: 2 BHK: 800 to 1250 sq ft carpet (148 homes); 3 BHK: 1180 to 1763 sq ft carpet (139 homes); 4 BHK: 1773 to 2605 sq ft carpet (76 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does The Edge have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 795 covered car parking spaces for The Edge.

How big is the land of The Edge?

According to GharKundli's check of MahaRERA records (updated October 2026), The Edge stands on 10,055 sq m of land (about 2.5 acres), with 48,892 sq m of sanctioned built-up area.

What is the track record of The Edge's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Tejukaya Realty (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 18 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of The Edge?

Google Maps has reviews of The Edge written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of The Edge?

The Edge by TEJUKAYA CORP PRIVATE LIMITED is in Lalbaug, Mumbai, pincode 400012 (near Lower Parel, Ramnagar, Pimpri), Maharashtra, and is registered on MahaRERA as P51900032613, per GharKundli's check of MahaRERA records. Its boundaries filed there include DR BABASAHEB AMBEDKAR ROAD. Its land is filed as 3/52, 3A/52, 3A1/52 AND 3B/52. GharKundli lists all 65 MahaRERA projects in Parel (400012).

How many flats are in The Edge, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), The Edge has 363 homes in 3 towers registered on MahaRERA, and 63% of them are sold or booked.

When was The Edge registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Edge was registered on MahaRERA on 14 January 2022. GharKundli did not find a title report on the land on file there.

Does The Edge have any legal issues or court cases?

6 court cases are listed for The Edge on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of The Edge?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TEJUKAYA CORP PRIVATE LIMITED.

All projects with possession due in 2031 in Mumbai City →

Other projects in Parel (400012)

All 65 projects in Parel (400012) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.