SUNRISE GLORY PHASE II

by SUNRISE LIFESPACES LLP · Village Shil, Thane

Possession: SUNRISE GLORY PHASE II is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700003397. Status: Completed. 8 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SUNRISE GLORY PHASE II?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on SUNRISE GLORY PHASE II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 8 complaints, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700003397
Status
Completed
Builder
SUNRISE LIFESPACES LLP
Location
Village Shil, Thane · 421204
Project type
Residential / Group Housing
Registered on
5 Aug 2017
Completion date at registration
December 2022
Latest completion date
December 2022
Homes
115
Towers
1
Complaints on MahaRERA
8
Court cases listed
0
Appeals at the tribunal
2
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of SUNRISE GLORY PHASE II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A3100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SUNRISE GLORY PHASE II every month.

SUNRISE GLORY PHASE II: buildings, flats and land, as filed on MahaRERA

  • Buildings: A3 (32 floors)
  • Land: 1,600 sq m (about 0.4 acres) · sanctioned built-up 5,999 sq m · recreational space 500 sq m

The builder’s record and reviews

Sunrise Lifespaces has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 3 finished, all within the promised date; 5 still being built, none past the promised date yet. 19 complaints on MahaRERA across 3 projects.

Read Google reviews of SUNRISE GLORY PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SUNRISE GLORY PHASE II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SUNRISE GLORY PHASE II

What is the possession date of SUNRISE GLORY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SUNRISE GLORY PHASE II in Village Shil, Thane is 30 December 2022.

Is the builder's possession date different from the MahaRERA date for SUNRISE GLORY PHASE II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SUNRISE GLORY PHASE II's builder has filed on MahaRERA, the official one, is 30 December 2022, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SUNRISE GLORY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SUNRISE GLORY PHASE II in Village Shil, Thane is P51700003397.

Is SUNRISE GLORY PHASE II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SUNRISE GLORY PHASE II is registered as P51700003397 and its status is "Completed".

What is the construction status of SUNRISE GLORY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), SUNRISE GLORY PHASE II's status on MahaRERA is "Completed". As filed by the builder, slab work on A3 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SUNRISE GLORY PHASE II have complaints on MahaRERA?

8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SUNRISE GLORY PHASE II safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SUNRISE GLORY PHASE II is registered on MahaRERA as P51700003397, its MahaRERA status is "Completed", its completion date has not been moved by the builder and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does SUNRISE GLORY PHASE II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Sunrise Glory - Phase I (P51700008298, possession 30 Jun 2018). Check that your agreement names the registration of your own wing.

How can I get updates if SUNRISE GLORY PHASE II's possession date changes?

The latest dates are on SUNRISE GLORY PHASE II's MahaRERA page (P51700003397). GharKundli's Kundli Watch sends a free WhatsApp update on SUNRISE GLORY PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SUNRISE GLORY PHASE II have?

According to GharKundli's check of MahaRERA records (updated November 2026), SUNRISE GLORY PHASE II has one building filed: A3 with 32 floors.

How big is the land of SUNRISE GLORY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), SUNRISE GLORY PHASE II stands on 1,600 sq m of land (about 0.4 acres), with 5,999 sq m of sanctioned built-up area and 500 sq m of recreational open space.

What is the track record of SUNRISE GLORY PHASE II's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunrise Lifespaces has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 3 finished, all within the promised date; 5 still being built, none past the promised date yet. 19 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SUNRISE GLORY PHASE II?

Google Maps has reviews of SUNRISE GLORY PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SUNRISE GLORY PHASE II?

SUNRISE GLORY PHASE II by SUNRISE LIFESPACES LLP is in Village Shil, Thane (pincode 421204), Maharashtra, and is registered on MahaRERA as P51700003397, per GharKundli's check of MahaRERA records.

How many homes are in SUNRISE GLORY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), SUNRISE GLORY PHASE II has 115 homes in 1 tower registered on MahaRERA.

When was SUNRISE GLORY PHASE II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SUNRISE GLORY PHASE II was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SUNRISE GLORY PHASE II?

No court cases are listed for SUNRISE GLORY PHASE II on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SUNRISE GLORY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SUNRISE LIFESPACES LLP, which has 5 other projects registered on MahaRERA.

Other projects in Thane

All 252 projects in Manpada (421204) →

Other projects by SUNRISE LIFESPACES LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.