DAISY GARDENS SURVEY NO 12 PHASE I
by ANKITA BUILDERS · Khoj Gaon, ThaneAlso near Ambernath, Netaji Bazar
Possession date of DAISY GARDENS SURVEY NO 12 PHASE I: 30 June 2027, moved from 30 December 2020 (78 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700009528, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about DAISY GARDENS SURVEY NO 12 PHASE I?
How the possession date of DAISY GARDENS SURVEY NO 12 PHASE I has moved
30 December 2020
Completion date given when the project was registered
30 December 2021
Extended at the builder's request (MahaRERA application EXT51700008726)
Reason the builder gave MahaRERA:
“The project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the p…” Read the full reason
“The project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID – 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 30/12/2021 for our Project – “Daisy Gardens Survey No.12 Phase I” bearing Registration No. P51700009528.”30 June 2023
Extended at the builder's request (MahaRERA application EXT51700012029)
Reason the builder gave MahaRERA:
“The project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the p…” Read the full reason
“The project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID – 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 30/06/2023 for our Project – “Daisy Gardens Survey No.12 Phase I” bearing Registration No. P51700009528.”30 June 2024
Extended at the builder's request (MahaRERA application EXT51700016783)
Reason the builder gave MahaRERA:
“The project is under construction & we have completed almost work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the…” Read the full reason
“The project is under construction & we have completed almost work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID – 19 it is getting delayed.”30 June 2026
Extended at the builder's request (MahaRERA application EXT51700024091)
Reason the builder gave MahaRERA: “The project is completed in all aspects and we had applied for Occupancy Certificate. However for the Purpose of RERA Compliances we have applied for extension of Project due to expiry of Project Validity under MahaRERA.”
30 June 2027
Extended at the builder's request (MahaRERA application EA24062621493)
Reason the builder gave MahaRERA:
“1) Slow booking response from customer. 2) Because of slow down in booking response, we have work/act accordingly in above said building. But at present, we have completed our 95% Project & pending for necessary permission from various conc…” Read the full reason
“1) Slow booking response from customer. 2) Because of slow down in booking response, we have work/act accordingly in above said building. But at present, we have completed our 95% Project & pending for necessary permission from various concern Authorities for obtaining Completion Certificate from Ambernath Muncipal Council, Ambernath.”
Source: DAISY GARDENS SURVEY NO 12 PHASE I’s extension records on MahaRERA (P51700009528), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DAISY GARDENS SURVEY NO 12 PHASE I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- DAISY GARDENS SURVEY NO 11P51700005390 · possession 30 Oct 2026
- DAISY GARDENS SURVEY NO 12 PHASE IIP51700009095 · possession 30 Jul 2018
- MahaRERA registration
- P51700009528
- Status
- Registered and active
- Builder
- ANKITA BUILDERS
- Location
- Khoj Gaon, Thane · 421505
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- December 2020
- Latest completion date
- June 2027
- Delay so far
- 78 months
- Homes
- 113
- Sold or booked
- 64%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of DAISY GARDENS SURVEY NO 12 PHASE I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 10 | 100% | 100% | 100% | 93% |
| BUILDING NO 11 | 100% | 100% | 100% | 93% |
| BUILDING NO 12 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 10: covers 7 floors
- BUILDING NO 11: covers 7 floors
- BUILDING NO 12: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DAISY GARDENS SURVEY NO 12 PHASE I every month.
DAISY GARDENS SURVEY NO 12 PHASE I: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 10 (9 floors, 37 units) · BUILDING NO 11 (9 floors, 38 units) · BUILDING NO 12 (9 floors, 38 units)
- Land: 2,000 sq m (about 0.5 acres) · sanctioned built-up 4,499 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Ankita Builders has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 still being built, 3 past the promised date (typically 60 months late). No complaints on MahaRERA.
Read Google reviews of DAISY GARDENS SURVEY NO 12 PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DAISY GARDENS SURVEY NO 12 PHASE I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DAISY GARDENS SURVEY NO 12 PHASE I
What is the possession date of DAISY GARDENS SURVEY NO 12 PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DAISY GARDENS SURVEY NO 12 PHASE I in Khoj Gaon, Thane is 30 June 2027 — 78 months later than 30 December 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for DAISY GARDENS SURVEY NO 12 PHASE I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DAISY GARDENS SURVEY NO 12 PHASE I's builder has filed on MahaRERA, the official one, is 30 June 2027, already 78 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of DAISY GARDENS SURVEY NO 12 PHASE I extended?
According to GharKundli's check of MahaRERA records (updated October 2026), DAISY GARDENS SURVEY NO 12 PHASE I's builder applied to MahaRERA to extend the completion date 5 times: to 30 December 2021, giving the reason "The project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID – 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 30/12/2021 for our Project – “Daisy Gardens Survey No.12 Phase I” bearing Registration No. P51700009528."; to 30 June 2023, giving the reason "The project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID – 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 30/06/2023 for our Project – “Daisy Gardens Survey No.12 Phase I” bearing Registration No. P51700009528."; to 30 June 2024, giving the reason "The project is under construction & we have completed almost work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID – 19 it is getting delayed."; to 30 June 2026, giving the reason "The project is completed in all aspects and we had applied for Occupancy Certificate. However for the Purpose of RERA Compliances we have applied for extension of Project due to expiry of Project Validity under MahaRERA."; to 30 June 2027, giving the reason "1) Slow booking response from customer. 2) Because of slow down in booking response, we have work/act accordingly in above said building. But at present, we have completed our 95% Project & pending for necessary permission from various concern Authorities for obtaining Completion Certificate from Ambernath Muncipal Council, Ambernath.".
What is the RERA number of DAISY GARDENS SURVEY NO 12 PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DAISY GARDENS SURVEY NO 12 PHASE I in Khoj Gaon, Thane is P51700009528.
Is DAISY GARDENS SURVEY NO 12 PHASE I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DAISY GARDENS SURVEY NO 12 PHASE I is registered as P51700009528 and its status is "Registered and active".
What is the construction status of DAISY GARDENS SURVEY NO 12 PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), DAISY GARDENS SURVEY NO 12 PHASE I's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does DAISY GARDENS SURVEY NO 12 PHASE I have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is DAISY GARDENS SURVEY NO 12 PHASE I safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), DAISY GARDENS SURVEY NO 12 PHASE I is registered on MahaRERA as P51700009528, its completion date has moved 78 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does DAISY GARDENS SURVEY NO 12 PHASE I have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: DAISY GARDENS SURVEY NO 11 (P51700005390, possession 30 Oct 2026); DAISY GARDENS SURVEY NO 12 PHASE II (P51700009095, possession 30 Jul 2018). Check that your agreement names the registration of your own wing.
How can I get updates if DAISY GARDENS SURVEY NO 12 PHASE I's possession date changes?
The latest dates are on DAISY GARDENS SURVEY NO 12 PHASE I's MahaRERA page (P51700009528). GharKundli's Kundli Watch sends a free WhatsApp update on DAISY GARDENS SURVEY NO 12 PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DAISY GARDENS SURVEY NO 12 PHASE I have?
According to GharKundli's check of MahaRERA records (updated October 2026), DAISY GARDENS SURVEY NO 12 PHASE I has 3 buildings filed: BUILDING NO 10 with 9 floors and 37 units; BUILDING NO 11 with 9 floors and 38 units; BUILDING NO 12 with 9 floors and 38 units.
How big is the land of DAISY GARDENS SURVEY NO 12 PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), DAISY GARDENS SURVEY NO 12 PHASE I stands on 2,000 sq m of land (about 0.5 acres), with 4,499 sq m of sanctioned built-up area.
What is the track record of DAISY GARDENS SURVEY NO 12 PHASE I's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ankita Builders has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 still being built, 3 past the promised date (typically 60 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of DAISY GARDENS SURVEY NO 12 PHASE I?
Google Maps has reviews of DAISY GARDENS SURVEY NO 12 PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DAISY GARDENS SURVEY NO 12 PHASE I?
DAISY GARDENS SURVEY NO 12 PHASE I by ANKITA BUILDERS is in Khoj Gaon, Thane (pincode 421505), near Ambernath, Netaji Bazar, Maharashtra, and is registered on MahaRERA as P51700009528, per GharKundli's check of MahaRERA records.
How many homes are in DAISY GARDENS SURVEY NO 12 PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), DAISY GARDENS SURVEY NO 12 PHASE I has 113 homes in 3 towers registered on MahaRERA, and 64% of them are sold or booked.
When was DAISY GARDENS SURVEY NO 12 PHASE I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DAISY GARDENS SURVEY NO 12 PHASE I was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on DAISY GARDENS SURVEY NO 12 PHASE I?
No court cases are listed for DAISY GARDENS SURVEY NO 12 PHASE I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of DAISY GARDENS SURVEY NO 12 PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ANKITA BUILDERS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of DAISY GARDENS SURVEY NO 12 PHASE I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Ambarnath
- Nature Vista Building - 1
- MIDTOWN B AND C WING
- SAI UNIVERSE
- MERY VILLA CHSL
- MAHADEV HEIGHTS
- DATTATRAY RESIDENCY
- CHADHA RESIDENCY
- NEW NEELGAGAN CHS
Other projects by ANKITA BUILDERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.