by PATIL GROUP BUILDERS AND DEVELOPERS · Titwala, Thane 421605Also near Manda, KalyanRegistered on MahaRERA as “MAMTA 1351”

What’s in the report? →

Possession date of Patil Mamta 1351 (MahaRERA P51700007648): 31 December 2026, moved from 30 December 2022 (48 months later). It has 16 homes, 63% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700007648, and currently active.

Source: MahaRERA website — records for P51700007648, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Patil Mamta 1351?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Patil Mamta 1351 has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 15 August 2025

    Extended at the builder's request (MahaRERA application EXT51700017388)

    Reason the builder gave MahaRERA: “Resp. Sir, We Wish to Extend the Project completion date as plan is revised and thus saome extra time is required to complete project. And For the same Consent of Existing customers have been taken. Thank You”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA22122518902)

    Reason the builder gave MahaRERA: “Resp. Sir, We Wish to extend the Project completion date as plan is revised and thus some extra time is required to complete the project. And for the same Consent of existing customers have been taken. Thank You”

Source: Patil Mamta 1351’s extension records on MahaRERA (P51700007648), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Patil Mamta 1351

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700007648
Status
Registered and active
Builder
PATIL GROUP BUILDERS AND DEVELOPERS
Location
Titwala, Thane · 421605
Project type
Others
Registered on
17 Aug 2017
Completion date at registration
December 2022
Latest completion date
December 2026
Delay so far
48 months
Homes
16
Sold or booked
63%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Patil Mamta 1351, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KDMC BUS STOP100%100%100%100%
MAMTA 1351100%100%70%40%

Commencement certificate (CC), as filed on MahaRERA

  • KDMC BUS STOP: covers 3 floors
  • MAMTA 1351: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Patil Mamta 1351 every 1–2 months.

Patil Mamta 1351: buildings, flats and land, as filed on MahaRERA

  • Buildings: KDMC BUS STOP (3 floors, 4 units) · MAMTA 1351 (7 floors, 80 units)
  • Land: 1,593 sq m (about 0.4 acres) · sanctioned built-up 3,545 sq m
  • Boundaries filed include: MUNICIPAL ROAD
  • Land, as filed: CTS NO 773, 774, 775
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Patil Mamta 1351 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Patil Mamta 1351: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Patil Mamta 1351

What is the possession date of Patil Mamta 1351?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Patil Mamta 1351 in Titwala, Thane is 31 December 2026 — 48 months later than 30 December 2022, the date given at registration.

The date has already moved 48 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Patil Mamta 1351?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Patil Mamta 1351's builder has filed on MahaRERA, the official one, is 31 December 2026, already 48 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Patil Mamta 1351 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Patil Mamta 1351's builder applied to MahaRERA to extend the completion date 2 times: to 15 August 2025, giving the reason "Resp. Sir, We Wish to Extend the Project completion date as plan is revised and thus saome extra time is required to complete project. And For the same Consent of Existing customers have been taken. Thank You"; to 31 December 2026, giving the reason "Resp. Sir, We Wish to extend the Project completion date as plan is revised and thus some extra time is required to complete the project. And for the same Consent of existing customers have been taken. Thank You".

What is the RERA number of Patil Mamta 1351?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Patil Mamta 1351 in Titwala, Thane is P51700007648.

Is Patil Mamta 1351 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Patil Mamta 1351 is registered as P51700007648 and its status is "Registered and active".

What is the current construction status of Patil Mamta 1351? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Patil Mamta 1351's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Patil Mamta 1351 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Patil Mamta 1351 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Patil Mamta 1351 is registered on MahaRERA as P51700007648, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Patil Mamta 1351?

Patil Mamta 1351 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Patil Mamta 1351?

For a flat in Patil Mamta 1351 (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Patil Mamta 1351 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Patil Mamta 1351 is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Patil Mamta 1351 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Patil Mamta 1351 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Patil Mamta 1351's possession date changes?

The latest dates are on Patil Mamta 1351's MahaRERA page (P51700007648). GharKundli's Kundli Watch sends a free WhatsApp update on Patil Mamta 1351 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Patil Mamta 1351 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Patil Mamta 1351 has 2 buildings filed: KDMC BUS STOP with 3 floors and 4 units; MAMTA 1351 with 7 floors and 80 units.

How big is the land of Patil Mamta 1351?

According to GharKundli's check of MahaRERA records (updated October 2026), Patil Mamta 1351 stands on 1,593 sq m of land (about 0.4 acres), with 3,545 sq m of sanctioned built-up area.

What are the reviews of Patil Mamta 1351?

Google Maps has reviews of Patil Mamta 1351 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Patil Mamta 1351?

Patil Mamta 1351 by PATIL GROUP BUILDERS AND DEVELOPERS is in Titwala, Thane, pincode 421605 (near Manda, Kalyan), Maharashtra, and is registered on MahaRERA as P51700007648, per GharKundli's check of MahaRERA records. Its boundaries filed there include MUNICIPAL ROAD. Its land is filed as CTS NO 773, 774, 775. GharKundli lists all 174 MahaRERA projects in Titwala (421605).

How many flats are in Patil Mamta 1351, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Patil Mamta 1351 has 16 homes in 2 towers registered on MahaRERA, and 63% of them are sold or booked.

When was Patil Mamta 1351 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Patil Mamta 1351 was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Does Patil Mamta 1351 have any legal issues or court cases?

No court cases are listed for Patil Mamta 1351 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Patil Mamta 1351?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PATIL GROUP BUILDERS AND DEVELOPERS.

All projects with possession due in 2026 in Thane →

Other projects in Titwala (421605)

All 174 projects in Titwala (421605) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.