Guru Shiv Sidhhi Complex Wing A
by GURU OM CONSTRUCTION AND DEVELOPERS · Sant Tukaram Road, Thane 421204Registered on MahaRERA as “SHIV SIDHHI COMPLEX WING A”
What’s in the report? →Possession date of Guru Shiv Sidhhi Complex Wing A (MahaRERA P51700011748): 31 March 2031, moved from 30 December 2021 (111 months later). It has 28 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700011748, and currently active.
Source: MahaRERA website — records for P51700011748, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Guru Shiv Sidhhi Complex Wing A?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Guru Shiv Sidhhi Complex Wing A has moved
30 December 2021
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EXT51700019872)
Reason the builder gave MahaRERA:
“Subject: Extension of 24_months for Project “SHIV SIDHHI COMPLEX WING A ” videMahaRERA Project Registration Number P51700011748 under Section 5(6) of the Real Estate (Regulation and Development) Act, 2016. Respected Sir/Madam, This is to ce…” Read the full reason
“Subject: Extension of 24_months for Project “SHIV SIDHHI COMPLEX WING A ” videMahaRERA Project Registration Number P51700011748 under Section 5(6) of the Real Estate (Regulation and Development) Act, 2016. Respected Sir/Madam, This is to certify that project “SHIV SIDHHI COMPLEX WING A” developed by M/s. GURU OM CONSTRUCTION AND DEVELOPERS has been granted registration under MahaRERA vide registration no. P51700011748 dated 31.07.2017. In this case our first approvals for TMC were received on dated 07.06.2011 and the construction of the project was started on dated 10.07.2011, further the c…”31 March 2031
Extended at the builder's request (MahaRERA application EA23052621073)
Reason the builder gave MahaRERA:
“1. We have obtained the permissions for the project for Ground/Stilt+ 1st Floor from Thane Municipal Corporation. We have applied for further permissions till 7th Floor and the approval of the same is awaited. 2. The photos of present statu…” Read the full reason
“1. We have obtained the permissions for the project for Ground/Stilt+ 1st Floor from Thane Municipal Corporation. We have applied for further permissions till 7th Floor and the approval of the same is awaited. 2. The photos of present status of project are enclosed herewith.”
Source: Guru Shiv Sidhhi Complex Wing A’s extension records on MahaRERA (P51700011748), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Guru Shiv Sidhhi Complex Wing A
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700011748
- Status
- Registered and active
- Builder
- GURU OM CONSTRUCTION AND DEVELOPERS
- Location
- Sant Tukaram Road, Thane · 421204
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- March 2031
- Delay so far
- 111 months
- Homes
- 28
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Guru Shiv Sidhhi Complex Wing A, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHIV SIDDHI COMPLEX WING A | 100% | 50% | 10% | 5% |
Commencement certificate (CC), as filed on MahaRERA
- SHIV SIDDHI COMPLEX WING A: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Guru Shiv Sidhhi Complex Wing A every 1–2 months.
Guru Shiv Sidhhi Complex Wing A: buildings, flats and land, as filed on MahaRERA
- Buildings: SHIV SIDDHI COMPLEX WING A (2 floors, 28 units)
- Car parking: 6 open
- Land: 1,370 sq m (about 0.3 acres) · sanctioned built-up 1,321 sq m
- Land, as filed: 155 PART 10
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Guru Shiv Sidhhi Complex Wing A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Guru Shiv Sidhhi Complex Wing A: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Guru Shiv Sidhhi Complex Wing A
What is the possession date of Guru Shiv Sidhhi Complex Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Guru Shiv Sidhhi Complex Wing A in Sant Tukaram Road, Thane is 31 March 2031 — 111 months later than 30 December 2021, the date given at registration.
The date has already moved 111 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Guru Shiv Sidhhi Complex Wing A?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Guru Shiv Sidhhi Complex Wing A's builder has filed on MahaRERA, the official one, is 31 March 2031, already 111 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Guru Shiv Sidhhi Complex Wing A extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Guru Shiv Sidhhi Complex Wing A's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "Subject: Extension of 24_months for Project “SHIV SIDHHI COMPLEX WING A ” videMahaRERA Project Registration Number P51700011748 under Section 5(6) of the Real Estate (Regulation and Development) Act, 2016. Respected Sir/Madam, This is to certify that project “SHIV SIDHHI COMPLEX WING A” developed by M/s. GURU OM CONSTRUCTION AND DEVELOPERS has been granted registration under MahaRERA vide registration no. P51700011748 dated 31.07.2017. In this case our first approvals for TMC were received on dated 07.06.2011 and the construction of the project was started on dated 10.07.2011, further the c…"; to 31 March 2031, giving the reason "1. We have obtained the permissions for the project for Ground/Stilt+ 1st Floor from Thane Municipal Corporation. We have applied for further permissions till 7th Floor and the approval of the same is awaited. 2. The photos of present status of project are enclosed herewith.".
What is the RERA number of Guru Shiv Sidhhi Complex Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Guru Shiv Sidhhi Complex Wing A in Sant Tukaram Road, Thane is P51700011748.
Is Guru Shiv Sidhhi Complex Wing A registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Guru Shiv Sidhhi Complex Wing A is registered as P51700011748 and its status is "Registered and active".
What is the current construction status of Guru Shiv Sidhhi Complex Wing A? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Guru Shiv Sidhhi Complex Wing A's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHIV SIDDHI COMPLEX WING A is 50% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.
Does Guru Shiv Sidhhi Complex Wing A have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Guru Shiv Sidhhi Complex Wing A safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Guru Shiv Sidhhi Complex Wing A is registered on MahaRERA as P51700011748, its completion date has moved 111 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Guru Shiv Sidhhi Complex Wing A?
Guru Shiv Sidhhi Complex Wing A is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Guru Shiv Sidhhi Complex Wing A?
For a flat in Guru Shiv Sidhhi Complex Wing A (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Guru Shiv Sidhhi Complex Wing A received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Guru Shiv Sidhhi Complex Wing A is still under construction, with 31 March 2031 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Guru Shiv Sidhhi Complex Wing A uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Guru Shiv Sidhhi Complex Wing A was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Guru Shiv Sidhhi Complex Wing A's possession date changes?
The latest dates are on Guru Shiv Sidhhi Complex Wing A's MahaRERA page (P51700011748). GharKundli's Kundli Watch sends a free WhatsApp update on Guru Shiv Sidhhi Complex Wing A every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Guru Shiv Sidhhi Complex Wing A have?
According to GharKundli's check of MahaRERA records (updated October 2026), Guru Shiv Sidhhi Complex Wing A has one building filed: SHIV SIDDHI COMPLEX WING A with 2 floors and 28 units.
How much parking does Guru Shiv Sidhhi Complex Wing A have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 6 open car parking spaces for Guru Shiv Sidhhi Complex Wing A.
How big is the land of Guru Shiv Sidhhi Complex Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), Guru Shiv Sidhhi Complex Wing A stands on 1,370 sq m of land (about 0.3 acres), with 1,321 sq m of sanctioned built-up area.
What are the reviews of Guru Shiv Sidhhi Complex Wing A?
Google Maps has reviews of Guru Shiv Sidhhi Complex Wing A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Guru Shiv Sidhhi Complex Wing A?
Guru Shiv Sidhhi Complex Wing A by GURU OM CONSTRUCTION AND DEVELOPERS is in Sant Tukaram Road, Thane, pincode 421204, Maharashtra, and is registered on MahaRERA as P51700011748, per GharKundli's check of MahaRERA records. Its land is filed as 155 PART 10. GharKundli lists all 252 MahaRERA projects in Manpada (421204).
How many flats are in Guru Shiv Sidhhi Complex Wing A, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Guru Shiv Sidhhi Complex Wing A has 28 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Guru Shiv Sidhhi Complex Wing A registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Guru Shiv Sidhhi Complex Wing A was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Does Guru Shiv Sidhhi Complex Wing A have any legal issues or court cases?
No court cases are listed for Guru Shiv Sidhhi Complex Wing A on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Guru Shiv Sidhhi Complex Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GURU OM CONSTRUCTION AND DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Guru Shiv Sidhhi Complex Wing A
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Thane →
Other projects in Thane
- Veer Square (Thane)
- Raj Tattva Phase 1 Commercial
- Mauli Krupa
- Gurukrupa Nityam
- Lotus
- Urban Reserve Wing B
- Asavari Co Op HSG Soc LTD
- Panache
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.