SAKSHI ENCLAVE
by SAKSHI SAURABH DANT · Dahisar West, ThaneAlso near Borivali West, Dahisar East, I C Colony
Possession date of SAKSHI ENCLAVE: 30 September 2020, moved from 31 March 2019 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700009056. Status: Lapsed (registration period ended). 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (September 2020) has passed.
What do you want to know about SAKSHI ENCLAVE?
How the possession date of SAKSHI ENCLAVE has moved
31 March 2019
Completion date given when the project was registered
30 March 2020
Extended at the builder's request (MahaRERA application EXT51700003713)
Reason the builder gave MahaRERA: “DUE TO SHORTAGE OF SAND WE WERE NOT ABLE TO COMPLETE THE PROJECT ON TIME. WE REQUEST YOU TO GRANT US FURTHER EXTENSION FOR 12 MONTHS”
30 September 2020
Revised completion date on MahaRERA
Source: SAKSHI ENCLAVE’s extension records on MahaRERA (P51700009056), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAKSHI ENCLAVE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the September 2020 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700009056
- Status
- Lapsed (registration period ended)
- Builder
- SAKSHI SAURABH DANT
- Location
- Dahisar West, Thane · 400068
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- March 2019
- Latest completion date
- September 2020
- Delay so far
- 18 months
- Homes
- 21
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SAKSHI ENCLAVE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAKSHI ENCLAVE | 100% | 75% | 50% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAKSHI ENCLAVE every month.
SAKSHI ENCLAVE: buildings, flats and land, as filed on MahaRERA
- Buildings: SAKSHI ENCLAVE (18 floors)
- Land: 436 sq m (about 0.1 acres) · sanctioned built-up 1,027 sq m
- Boundaries filed include: PLAY GROUND
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAKSHI ENCLAVE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAKSHI ENCLAVE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAKSHI ENCLAVE
What is the possession date of SAKSHI ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAKSHI ENCLAVE in Dahisar West, Thane is 30 September 2020 — 18 months later than 31 March 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for SAKSHI ENCLAVE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAKSHI ENCLAVE's builder has filed on MahaRERA, the official one, is 30 September 2020, already 18 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAKSHI ENCLAVE extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SAKSHI ENCLAVE's builder applied to MahaRERA to extend the completion date once: to 30 March 2020, giving the reason "DUE TO SHORTAGE OF SAND WE WERE NOT ABLE TO COMPLETE THE PROJECT ON TIME. WE REQUEST YOU TO GRANT US FURTHER EXTENSION FOR 12 MONTHS".
What is the RERA number of SAKSHI ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAKSHI ENCLAVE in Dahisar West, Thane is P51700009056.
Is SAKSHI ENCLAVE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAKSHI ENCLAVE is registered as P51700009056 and its status is "Lapsed (registration period ended)".
What is the construction status of SAKSHI ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), SAKSHI ENCLAVE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAKSHI ENCLAVE is 75% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does SAKSHI ENCLAVE have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAKSHI ENCLAVE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SAKSHI ENCLAVE is registered on MahaRERA as P51700009056, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAKSHI ENCLAVE's possession date changes?
The latest dates are on SAKSHI ENCLAVE's MahaRERA page (P51700009056). GharKundli's Kundli Watch sends a free WhatsApp update on SAKSHI ENCLAVE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAKSHI ENCLAVE have?
According to GharKundli's check of MahaRERA records (updated November 2026), SAKSHI ENCLAVE has one building filed: SAKSHI ENCLAVE with 18 floors.
How big is the land of SAKSHI ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), SAKSHI ENCLAVE stands on 436 sq m of land (about 0.1 acres), with 1,027 sq m of sanctioned built-up area.
Where can I read reviews of SAKSHI ENCLAVE?
Google Maps has reviews of SAKSHI ENCLAVE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAKSHI ENCLAVE?
SAKSHI ENCLAVE by SAKSHI SAURABH DANT is in Dahisar West, Thane (pincode 400068), near Borivali West, Dahisar East, I C Colony, Maharashtra, and is registered on MahaRERA as P51700009056, per GharKundli's check of MahaRERA records. Its boundaries filed there include PLAY GROUND.
How many homes are in SAKSHI ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), SAKSHI ENCLAVE has 21 homes in 1 tower registered on MahaRERA.
When was SAKSHI ENCLAVE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAKSHI ENCLAVE was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SAKSHI ENCLAVE?
No court cases are listed for SAKSHI ENCLAVE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SAKSHI ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAKSHI SAURABH DANT.
Check it yourself on MahaRERA
- How to check the possession date of SAKSHI ENCLAVE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400068
- RAJHANS
- Royal Accord
- SHREE GANESH CHSL
- Ozone Residency
- BRINDAVAN CHSL
- RAJ CAPITAL
- EMPIRE HEIGHTS
- Nirali Lifespace
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.