GUNDECHA-KBK-MAGNUM PHASE I

by GundechaConstructionPvtLtd · Lalbaug, MumbaiAlso near Parel, Delisle Road, Prabhadevi

Possession date of GUNDECHA-KBK-MAGNUM PHASE I: 31 July 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900034493, and currently active. Its completion date is now July 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about GUNDECHA-KBK-MAGNUM PHASE I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GUNDECHA-KBK-MAGNUM PHASE I has moved

  1. 31 March 2027

    Completion date given when the project was registered

  2. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: GUNDECHA-KBK-MAGNUM PHASE I’s extension records on MahaRERA (P51900034493), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GUNDECHA-KBK-MAGNUM PHASE I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints and 2 court cases, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900034493
Status
Registered and active
Builder
GundechaConstructionPvtLtd
Location
Lalbaug, Mumbai · 400012
Project type
Residential / Group Housing
Registered on
11 Apr 2022
Completion date at registration
March 2027
Latest completion date
July 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
170
Sold or booked
60%
Towers
1
Complaints on MahaRERA
2
Court cases listed
2
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of GUNDECHA-KBK-MAGNUM PHASE I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GUNDECHA KBK MAGNUM A WING100%85%60%0%

Commencement certificate (CC), as filed on MahaRERA

  • GUNDECHA KBK MAGNUM A WING: covers 40th

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GUNDECHA-KBK-MAGNUM PHASE I every month.

GUNDECHA-KBK-MAGNUM PHASE I: buildings, flats and land, as filed on MahaRERA

  • Buildings: GUNDECHA KBK MAGNUM A WING (52 floors, 170 units)
  • Land: 11,737 sq m (about 2.9 acres) · sanctioned built-up 22,799 sq m · recreational space 287 sq m

The builder’s record and reviews

Gundechaconstructionpvtltd (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 3 months late). 6 complaints on MahaRERA across 3 projects.

Read Google reviews of GUNDECHA-KBK-MAGNUM PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GUNDECHA-KBK-MAGNUM PHASE I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GUNDECHA-KBK-MAGNUM PHASE I

What is the possession date of GUNDECHA-KBK-MAGNUM PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GUNDECHA-KBK-MAGNUM PHASE I in Lalbaug, Mumbai is 31 July 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for GUNDECHA-KBK-MAGNUM PHASE I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GUNDECHA-KBK-MAGNUM PHASE I's builder has filed on MahaRERA, the official one, is 31 July 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of GUNDECHA-KBK-MAGNUM PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GUNDECHA-KBK-MAGNUM PHASE I in Lalbaug, Mumbai is P51900034493.

Is GUNDECHA-KBK-MAGNUM PHASE I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GUNDECHA-KBK-MAGNUM PHASE I is registered as P51900034493 and its status is "Registered and active".

What is the construction status of GUNDECHA-KBK-MAGNUM PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), GUNDECHA-KBK-MAGNUM PHASE I's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GUNDECHA KBK MAGNUM A WING is 85% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does GUNDECHA-KBK-MAGNUM PHASE I have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is GUNDECHA-KBK-MAGNUM PHASE I safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), GUNDECHA-KBK-MAGNUM PHASE I is registered on MahaRERA as P51900034493, its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GUNDECHA-KBK-MAGNUM PHASE I's possession date changes?

The latest dates are on GUNDECHA-KBK-MAGNUM PHASE I's MahaRERA page (P51900034493). GharKundli's Kundli Watch sends a free WhatsApp update on GUNDECHA-KBK-MAGNUM PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GUNDECHA-KBK-MAGNUM PHASE I have?

According to GharKundli's check of MahaRERA records (updated November 2026), GUNDECHA-KBK-MAGNUM PHASE I has one building filed: GUNDECHA KBK MAGNUM A WING with 52 floors and 170 units.

How big is the land of GUNDECHA-KBK-MAGNUM PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), GUNDECHA-KBK-MAGNUM PHASE I stands on 11,737 sq m of land (about 2.9 acres), with 22,799 sq m of sanctioned built-up area and 287 sq m of recreational open space.

What is the track record of GUNDECHA-KBK-MAGNUM PHASE I's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Gundechaconstructionpvtltd (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 3 months late). 6 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of GUNDECHA-KBK-MAGNUM PHASE I?

Google Maps has reviews of GUNDECHA-KBK-MAGNUM PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GUNDECHA-KBK-MAGNUM PHASE I?

GUNDECHA-KBK-MAGNUM PHASE I by GundechaConstructionPvtLtd is in Lalbaug, Mumbai (pincode 400012), near Parel, Delisle Road, Prabhadevi, Maharashtra, and is registered on MahaRERA as P51900034493, per GharKundli's check of MahaRERA records.

How many homes are in GUNDECHA-KBK-MAGNUM PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), GUNDECHA-KBK-MAGNUM PHASE I has 170 homes in 1 tower registered on MahaRERA, and 60% of them are sold or booked.

When was GUNDECHA-KBK-MAGNUM PHASE I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GUNDECHA-KBK-MAGNUM PHASE I was registered on MahaRERA on 11 April 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on GUNDECHA-KBK-MAGNUM PHASE I?

2 court cases are listed for GUNDECHA-KBK-MAGNUM PHASE I on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of GUNDECHA-KBK-MAGNUM PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GundechaConstructionPvtLtd, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Mumbai City →

Other projects in pincode 400012

All 65 projects in Parel (400012) →

Other projects by GundechaConstructionPvtLtd

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.