Possession: RAHUL EXCELLENCE is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700012698. Status: Completed. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about RAHUL EXCELLENCE?
How the possession date of RAHUL EXCELLENCE has moved
31 December 2018
Completion date given when the project was registered
31 December 2021
Extended at the builder's request (MahaRERA application EXT51700005661)
Reason the builder gave MahaRERA:
“The Project was completed in December 2018 and application for Occupation Certificate has been made to the concerned authority in February 2019. However, till date Occupation Certificate has not been granted due to procedural delays on part…” Read the full reason
“The Project was completed in December 2018 and application for Occupation Certificate has been made to the concerned authority in February 2019. However, till date Occupation Certificate has not been granted due to procedural delays on part of the governmental authorities. It is pertinent to note that construction of the project has been completed and it is construed to be an ongoing project only on the ground that Occupation Certificate has not been issued. The Allottees of the project have given their consent to the promoter to extend the registration of the project. The reasons for delay…”30 December 2022
Revised completion date on MahaRERA
Source: RAHUL EXCELLENCE’s extension records on MahaRERA (P51700012698), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RAHUL EXCELLENCE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 2 court cases, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700012698
- Status
- Completed
- Builder
- SAROJ SHRAWANKUMAR BAGARIA
- Location
- Ambarnath, Thane · 421501
- Project type
- Others
- Registered on
- 7 Sep 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2022
- Delay so far
- 48 months
- Homes
- 38
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 2
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of RAHUL EXCELLENCE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RAHUL EXCELLENCE | 100% | 100% | 55% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RAHUL EXCELLENCE every month.
RAHUL EXCELLENCE: buildings, flats and land, as filed on MahaRERA
- Buildings: RAHUL EXCELLENCE (5 floors)
- Land: 953 sq m (about 0.2 acres) · sanctioned built-up 1,239 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of RAHUL EXCELLENCE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RAHUL EXCELLENCE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RAHUL EXCELLENCE
What is the possession date of RAHUL EXCELLENCE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RAHUL EXCELLENCE in Ambarnath, Thane is 30 December 2022 — 48 months later than 31 December 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for RAHUL EXCELLENCE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RAHUL EXCELLENCE's builder has filed on MahaRERA, the official one, is 30 December 2022, already 48 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RAHUL EXCELLENCE extended?
According to GharKundli's check of MahaRERA records (updated November 2026), RAHUL EXCELLENCE's builder applied to MahaRERA to extend the completion date once: to 31 December 2021, giving the reason "The Project was completed in December 2018 and application for Occupation Certificate has been made to the concerned authority in February 2019. However, till date Occupation Certificate has not been granted due to procedural delays on part of the governmental authorities. It is pertinent to note that construction of the project has been completed and it is construed to be an ongoing project only on the ground that Occupation Certificate has not been issued. The Allottees of the project have given their consent to the promoter to extend the registration of the project. The reasons for delay…".
What is the RERA number of RAHUL EXCELLENCE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RAHUL EXCELLENCE in Ambarnath, Thane is P51700012698.
Is RAHUL EXCELLENCE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAHUL EXCELLENCE is registered as P51700012698 and its status is "Completed".
What is the construction status of RAHUL EXCELLENCE?
According to GharKundli's check of MahaRERA records (updated November 2026), RAHUL EXCELLENCE's status on MahaRERA is "Completed". As filed by the builder, slab work on RAHUL EXCELLENCE is 100% done and internal work 55%. GharKundli's full report compares construction progress with the deadline.
Does RAHUL EXCELLENCE have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is RAHUL EXCELLENCE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), RAHUL EXCELLENCE is registered on MahaRERA as P51700012698, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RAHUL EXCELLENCE's possession date changes?
The latest dates are on RAHUL EXCELLENCE's MahaRERA page (P51700012698). GharKundli's Kundli Watch sends a free WhatsApp update on RAHUL EXCELLENCE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RAHUL EXCELLENCE have?
According to GharKundli's check of MahaRERA records (updated November 2026), RAHUL EXCELLENCE has one building filed: RAHUL EXCELLENCE with 5 floors.
How big is the land of RAHUL EXCELLENCE?
According to GharKundli's check of MahaRERA records (updated November 2026), RAHUL EXCELLENCE stands on 953 sq m of land (about 0.2 acres), with 1,239 sq m of sanctioned built-up area.
Where can I read reviews of RAHUL EXCELLENCE?
Google Maps has reviews of RAHUL EXCELLENCE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RAHUL EXCELLENCE?
RAHUL EXCELLENCE by SAROJ SHRAWANKUMAR BAGARIA is in Ambarnath, Thane (pincode 421501), near Additional Ambernath, Maharashtra, and is registered on MahaRERA as P51700012698, per GharKundli's check of MahaRERA records.
How many homes are in RAHUL EXCELLENCE?
According to GharKundli's check of MahaRERA records (updated November 2026), RAHUL EXCELLENCE has 38 homes in 1 tower registered on MahaRERA.
When was RAHUL EXCELLENCE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAHUL EXCELLENCE was registered on MahaRERA on 7 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on RAHUL EXCELLENCE?
2 court cases are listed for RAHUL EXCELLENCE on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of RAHUL EXCELLENCE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAROJ SHRAWANKUMAR BAGARIA.
Check it yourself on MahaRERA
- How to check the possession date of RAHUL EXCELLENCE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 421501
- NEELKANTH ROYALE PALMS - F WING PHASE II
- CHADHA RESIDENCY
- NEW NEELGAGAN CHS
- Mahadev Heights
- PARITOSH CO OPERATIVE HOUSING SOCIETY LIMITED
- NEXT CROWN LANDMARK
- ISHWAR JAY JAY SHANKARA CO-OP. HOUSING SOCIETY LTD.
- Panvelkar Daffodils-Plot No. 11,12,13
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.