Sky Gardens at Godrej Vihaa
by K. R. REAL ESTATE PVT. LTD. (Godrej) · Badlapur, Ambarnath, Thane
Possession: Sky Gardens at Godrej Vihaa is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700013329. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Sky Gardens at Godrej Vihaa?
How the possession date of Sky Gardens at Godrej Vihaa has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51700011020)
Reason the builder gave MahaRERA:
“The outbreak of COVID-19 had adversely affected the business and the project. We have faced numerous challenges with regard to availability of labour, raw material, restriction on travel, employment challenges, etc. which has impacted the s…” Read the full reason
“The outbreak of COVID-19 had adversely affected the business and the project. We have faced numerous challenges with regard to availability of labour, raw material, restriction on travel, employment challenges, etc. which has impacted the speed of construction. Due to the ongoing market slump coupled with the very low sales during the last 18-20 months due to covid-19 pandemic, there has been severe impact on collections from new sales. This has caused significant delay in construction progress of Tower 12. Hence, we hereby request for grant of extension under Section 6 of RERA Act of 12 mo…”29 December 2025
Extended at the builder's request (MahaRERA application EXT51700024467)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 51% allottees for purpose of extension of RERA registration period of the said project.”30 April 2026
Extended at the builder's request (MahaRERA application EA29012619628)
Reason the builder gave MahaRERA:
“The construction of the project has been fully completed, and the Occupancy Certificates for Buildings 10, 11 and 12 were issued on 09 January 2026. However, the said Occupancy Certificates were received 8 days after the approved MahaRERA c…” Read the full reason
“The construction of the project has been fully completed, and the Occupancy Certificates for Buildings 10, 11 and 12 were issued on 09 January 2026. However, the said Occupancy Certificates were received 8 days after the approved MahaRERA completion date, and therefore the project completion process under MahaRERA could not be finalized within the existing registration validity period. As a result, the Promoter was unable to apply for project completion and closure within the stipulated time, despite having completed the construction strictly in accordance with the sanctioned plans and appl…”30 September 2026
Extended at the builder's request (MahaRERA application EA20052621026)
Reason the builder gave MahaRERA:
“we, K. R. Real Estate Pvt. Ltd, hereby declare the following with respect to the project Sky Gardens at Godrej Vihaa bearing registration number P51700013329. registered under MahaRERA. The delay in the completion of the real estate project…” Read the full reason
“we, K. R. Real Estate Pvt. Ltd, hereby declare the following with respect to the project Sky Gardens at Godrej Vihaa bearing registration number P51700013329. registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 09/01/2026 and we have also initiated the process for the possession as well. However there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-u…”
Source: Sky Gardens at Godrej Vihaa’s extension records on MahaRERA (P51700013329), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sky Gardens at Godrej Vihaa
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the September 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700013329
- Status
- Completed
- Builder
- K. R. REAL ESTATE PVT. LTD.
- Location
- Badlapur, Ambarnath, Thane · 421502
- Project type
- Residential / Group Housing
- Registered on
- 22 Sep 2017
- Completion date at registration
- December 2023
- Latest completion date
- September 2026
- Delay so far
- 33 months
- Homes
- 495
- Sold or booked
- 77%
- Towers
- 3
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Sky Gardens at Godrej Vihaa, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 10 | 100% | 100% | 100% | 100% |
| Building No 11 | 100% | 100% | 100% | 100% |
| Building No 12 | 100% | 83% | 11% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Building No 10: covers 19 floors
- Building No 11: covers 19 floors
- Building No 12: covers 19 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sky Gardens at Godrej Vihaa every month.
Sky Gardens at Godrej Vihaa: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 10 (19 floors, 178 units) · Building No 11 (19 floors, 176 units) · Building No 12 (19 floors, 141 units)
- Car parking: 90 covered, 165 open
- Land: 9,125 sq m (about 2.3 acres) · sanctioned built-up 24,715 sq m · recreational space 405 sq m
- Boundaries filed include: Phase 2 Internal Layout Road
The builder’s record and reviews
Vakratunda Buildcon (a group of 10 linked companies) has 51 projects on MahaRERA since 2017, this one included. Of the 50 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 16 months); 38 still being built, 15 past the promised date (typically 6 months late); 5 lapsed. 454 complaints on MahaRERA across 32 projects.
Read Google reviews of Sky Gardens at Godrej Vihaa →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sky Gardens at Godrej Vihaa: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sky Gardens at Godrej Vihaa
What is the possession date of Sky Gardens at Godrej Vihaa?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sky Gardens at Godrej Vihaa in Badlapur, Ambarnath, Thane is 30 September 2026 — 33 months later than 30 December 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Sky Gardens at Godrej Vihaa?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sky Gardens at Godrej Vihaa's builder has filed on MahaRERA, the official one, is 30 September 2026, already 33 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sky Gardens at Godrej Vihaa extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sky Gardens at Godrej Vihaa's builder applied to MahaRERA to extend the completion date 4 times: to 29 December 2024, giving the reason "The outbreak of COVID-19 had adversely affected the business and the project. We have faced numerous challenges with regard to availability of labour, raw material, restriction on travel, employment challenges, etc. which has impacted the speed of construction. Due to the ongoing market slump coupled with the very low sales during the last 18-20 months due to covid-19 pandemic, there has been severe impact on collections from new sales. This has caused significant delay in construction progress of Tower 12. Hence, we hereby request for grant of extension under Section 6 of RERA Act of 12 mo…"; to 29 December 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 51% allottees for purpose of extension of RERA registration period of the said project."; to 30 April 2026, giving the reason "The construction of the project has been fully completed, and the Occupancy Certificates for Buildings 10, 11 and 12 were issued on 09 January 2026. However, the said Occupancy Certificates were received 8 days after the approved MahaRERA completion date, and therefore the project completion process under MahaRERA could not be finalized within the existing registration validity period. As a result, the Promoter was unable to apply for project completion and closure within the stipulated time, despite having completed the construction strictly in accordance with the sanctioned plans and appl…"; to 30 September 2026, giving the reason "we, K. R. Real Estate Pvt. Ltd, hereby declare the following with respect to the project Sky Gardens at Godrej Vihaa bearing registration number P51700013329. registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 09/01/2026 and we have also initiated the process for the possession as well. However there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-u…".
What is the RERA number of Sky Gardens at Godrej Vihaa?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sky Gardens at Godrej Vihaa in Badlapur, Ambarnath, Thane is P51700013329.
Is Sky Gardens at Godrej Vihaa registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sky Gardens at Godrej Vihaa is registered as P51700013329 and its status is "Completed".
What is the construction status of Sky Gardens at Godrej Vihaa?
According to GharKundli's check of MahaRERA records (updated October 2026), Sky Gardens at Godrej Vihaa's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 83% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Sky Gardens at Godrej Vihaa have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Sky Gardens at Godrej Vihaa safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sky Gardens at Godrej Vihaa is registered on MahaRERA as P51700013329, its MahaRERA status is "Completed", its completion date has moved 33 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Sky Gardens at Godrej Vihaa's possession date changes?
The latest dates are on Sky Gardens at Godrej Vihaa's MahaRERA page (P51700013329). GharKundli's Kundli Watch sends a free WhatsApp update on Sky Gardens at Godrej Vihaa every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sky Gardens at Godrej Vihaa have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sky Gardens at Godrej Vihaa has 3 buildings filed: Building No 10 with 19 floors and 178 units; Building No 11 with 19 floors and 176 units; Building No 12 with 19 floors and 141 units.
How much parking does Sky Gardens at Godrej Vihaa have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 90 covered and 165 open car parking spaces for Sky Gardens at Godrej Vihaa.
How big is the land of Sky Gardens at Godrej Vihaa?
According to GharKundli's check of MahaRERA records (updated October 2026), Sky Gardens at Godrej Vihaa stands on 9,125 sq m of land (about 2.3 acres), with 24,715 sq m of sanctioned built-up area and 405 sq m of recreational open space.
What is the track record of Sky Gardens at Godrej Vihaa's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vakratunda Buildcon (a group of 10 linked companies) has 51 projects on MahaRERA since 2017, this one included. Of the 50 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 16 months); 38 still being built, 15 past the promised date (typically 6 months late); 5 lapsed. 454 complaints on MahaRERA across 32 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Sky Gardens at Godrej Vihaa?
Google Maps has reviews of Sky Gardens at Godrej Vihaa written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sky Gardens at Godrej Vihaa?
Sky Gardens at Godrej Vihaa by K. R. REAL ESTATE PVT. LTD. (Godrej) is in Badlapur, Ambarnath, Thane (pincode 421502), Maharashtra, and is registered on MahaRERA as P51700013329, per GharKundli's check of MahaRERA records. Its boundaries filed there include Phase 2 Internal Layout Road.
How many homes are in Sky Gardens at Godrej Vihaa?
According to GharKundli's check of MahaRERA records (updated October 2026), Sky Gardens at Godrej Vihaa has 495 homes in 3 towers registered on MahaRERA, and 77% of them are sold or booked.
When was Sky Gardens at Godrej Vihaa registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sky Gardens at Godrej Vihaa was registered on MahaRERA on 22 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Sky Gardens at Godrej Vihaa?
No court cases are listed for Sky Gardens at Godrej Vihaa on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Sky Gardens at Godrej Vihaa?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is K. R. REAL ESTATE PVT. LTD., the company Godrej files this project under, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sky Gardens at Godrej Vihaa
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ambarnath
- Nature Vista Building - 1
- MIDTOWN B AND C WING
- SAI UNIVERSE
- MERY VILLA CHSL
- MAHADEV HEIGHTS
- DATTATRAY RESIDENCY
- CHADHA RESIDENCY
- NEW NEELGAGAN CHS
Other projects by K. R. REAL ESTATE PVT. LTD.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.