by RATNARAJ BUILDERS AND DEVELOPERS LLP · Sion, MumbaiAlso near Bandra East, Dharavi, Vidyanagari

Possession: SHRI ABHINANDAN is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900045297. Status: Completed. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHRI ABHINANDAN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHRI ABHINANDAN has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51900027325)

    Reason the builder gave MahaRERA:
    “The primary issue is the small size of the plot, which has limited our ability to efficiently carry out the construction work. This has been further compounded by restricted access to the site due to ongoing roadwork by the BMC, making it d…” Read the full reason“The primary issue is the small size of the plot, which has limited our ability to efficiently carry out the construction work. This has been further compounded by restricted access to the site due to ongoing roadwork by the BMC, making it difficult to bring in necessary equipment like a hydra for assembling the car parking system. The lack of proper road access has resulted in significant delays in both material and machinery transport. As a result of these challenges, we kindly request an extension of 6 months to ensure the project is completed to the highest standards, without compromisin…”

Source: SHRI ABHINANDAN’s extension records on MahaRERA (P51900045297), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHRI ABHINANDAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900045297
Status
Completed
Builder
RATNARAJ BUILDERS AND DEVELOPERS LLP
Location
Sion, Mumbai · 400022
Project type
Residential / Group Housing
Registered on
12 May 2022
Completion date at registration
December 2024
Latest completion date
December 2025
Delay so far
12 months
Homes
29
Sold or booked
24%
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of SHRI ABHINANDAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHRI ABHINANDAN100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • SHRI ABHINANDAN: covers THIS FURTHER C. C. (i.e. FULL C.C.) IS ENDORSED AS PER LAST APPROVED PLAN DATED. 21.08.2025

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRI ABHINANDAN every month.

SHRI ABHINANDAN: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK1,031 – 1,19710
2 BHK439 – 8649
1 BHK430 – 5639
Other2221
  • Buildings: SHRI ABHINANDAN (25 floors, 29 units)
  • Land: 414 sq m (about 0.1 acres) · sanctioned built-up 1,871 sq m

The builder’s record and reviews

Ratnaraj Blessing Milestone (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 1 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project.

Read Google reviews of SHRI ABHINANDAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHRI ABHINANDAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHRI ABHINANDAN

What is the possession date of SHRI ABHINANDAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHRI ABHINANDAN in Sion, Mumbai is 31 December 2025 — 12 months later than 31 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SHRI ABHINANDAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRI ABHINANDAN's builder has filed on MahaRERA, the official one, is 31 December 2025, already 12 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHRI ABHINANDAN extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ABHINANDAN's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "The primary issue is the small size of the plot, which has limited our ability to efficiently carry out the construction work. This has been further compounded by restricted access to the site due to ongoing roadwork by the BMC, making it difficult to bring in necessary equipment like a hydra for assembling the car parking system. The lack of proper road access has resulted in significant delays in both material and machinery transport. As a result of these challenges, we kindly request an extension of 6 months to ensure the project is completed to the highest standards, without compromisin…".

What is the RERA number of SHRI ABHINANDAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHRI ABHINANDAN in Sion, Mumbai is P51900045297.

Is SHRI ABHINANDAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ABHINANDAN is registered as P51900045297 and its status is "Completed".

What is the construction status of SHRI ABHINANDAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ABHINANDAN's status on MahaRERA is "Completed". As filed by the builder, slab work on SHRI ABHINANDAN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SHRI ABHINANDAN have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SHRI ABHINANDAN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ABHINANDAN is registered on MahaRERA as P51900045297, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHRI ABHINANDAN's possession date changes?

The latest dates are on SHRI ABHINANDAN's MahaRERA page (P51900045297). GharKundli's Kundli Watch sends a free WhatsApp update on SHRI ABHINANDAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHRI ABHINANDAN have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ABHINANDAN has one building filed: SHRI ABHINANDAN with 25 floors and 29 units.

What are the flat sizes (carpet area) in SHRI ABHINANDAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SHRI ABHINANDAN: 3 BHK: 1031 to 1197 sq ft carpet (10 homes); 2 BHK: 439 to 864 sq ft carpet (9 homes); 1 BHK: 430 to 563 sq ft carpet (9 homes); Other: 222 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of SHRI ABHINANDAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ABHINANDAN stands on 414 sq m of land (about 0.1 acres), with 1,871 sq m of sanctioned built-up area.

What is the track record of SHRI ABHINANDAN's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ratnaraj Blessing Milestone (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 1 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SHRI ABHINANDAN?

Google Maps has reviews of SHRI ABHINANDAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHRI ABHINANDAN?

SHRI ABHINANDAN by RATNARAJ BUILDERS AND DEVELOPERS LLP is in Sion, Mumbai (pincode 400022), near Bandra East, Dharavi, Vidyanagari, Maharashtra, and is registered on MahaRERA as P51900045297, per GharKundli's check of MahaRERA records.

How many homes are in SHRI ABHINANDAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ABHINANDAN has 29 homes in 1 tower registered on MahaRERA, and 24% of them are sold or booked.

When was SHRI ABHINANDAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ABHINANDAN was registered on MahaRERA on 12 May 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SHRI ABHINANDAN?

No court cases are listed for SHRI ABHINANDAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SHRI ABHINANDAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RATNARAJ BUILDERS AND DEVELOPERS LLP.

Other projects in pincode 400022

All 98 projects in Sion (400022) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.