Yug Heights
by M/s R. S. Constructions · Manpada, ThaneAlso near Vishnunagar
Possession date of Yug Heights: 30 April 2027, moved from 5 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700014553, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 39 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Yug Heights?
How the possession date of Yug Heights has moved
5 December 2023
Completion date given when the project was registered
4 December 2024
Extended at the builder's request (MahaRERA application EXT51700017553)
Reason the builder gave MahaRERA: “As per the attachment”
31 December 2026
Extended at the builder's request (MahaRERA application EXT51700025347)
Reason the builder gave MahaRERA:
“This extension application was scheduled for hearing on 15/12/2025. The Hon Chairperson, MahaRERA, has allowed the extension application and granted extension till 31.12.2026 vide order dated 30/12/2025. The said order is attached in sr. no…” Read the full reason
“This extension application was scheduled for hearing on 15/12/2025. The Hon Chairperson, MahaRERA, has allowed the extension application and granted extension till 31.12.2026 vide order dated 30/12/2025. The said order is attached in sr. no. 7 for your reference. Please take the order on your record and process the extension application.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Yug Heights’s extension records on MahaRERA (P51700014553), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Yug Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 39 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700014553
- Status
- Registered and active
- Builder
- M/s R. S. Constructions
- Location
- Manpada, Thane · 421204
- Project type
- Residential / Group Housing
- Registered on
- 12 Dec 2017
- Completion date at registration
- December 2023
- Latest completion date
- April 2027
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 1
- Complaints on MahaRERA
- 39
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of Yug Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Yug Heights | 100% | 100% | 70% | 8% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Yug Heights every month.
Yug Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: Yug Heights (19 floors)
- Land: 2,740 sq m (about 0.7 acres) · sanctioned built-up 7,431 sq m · recreational space 648 sq m
- Boundaries filed include: Recreation Garden, School
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Yug Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Yug Heights: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Yug Heights
What is the possession date of Yug Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Yug Heights in Manpada, Thane is 30 April 2027 — 36 months later than 5 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Yug Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Yug Heights's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 5 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Yug Heights extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Yug Heights's builder applied to MahaRERA to extend the completion date 2 times: to 4 December 2024, giving the reason "As per the attachment"; to 31 December 2026, giving the reason "This extension application was scheduled for hearing on 15/12/2025. The Hon Chairperson, MahaRERA, has allowed the extension application and granted extension till 31.12.2026 vide order dated 30/12/2025. The said order is attached in sr. no. 7 for your reference. Please take the order on your record and process the extension application.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Yug Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Yug Heights in Manpada, Thane is P51700014553.
Is Yug Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Yug Heights is registered as P51700014553 and its status is "Registered and active".
What is the construction status of Yug Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Yug Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Yug Heights is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does Yug Heights have complaints on MahaRERA?
39 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Yug Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Yug Heights is registered on MahaRERA as P51700014553, its completion date has moved 36 months since registration and 39 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Yug Heights's possession date changes?
The latest dates are on Yug Heights's MahaRERA page (P51700014553). GharKundli's Kundli Watch sends a free WhatsApp update on Yug Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Yug Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Yug Heights has one building filed: Yug Heights with 19 floors.
How big is the land of Yug Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Yug Heights stands on 2,740 sq m of land (about 0.7 acres), with 7,431 sq m of sanctioned built-up area and 648 sq m of recreational open space.
Where can I read reviews of Yug Heights?
Google Maps has reviews of Yug Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 39 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Yug Heights?
Yug Heights by M/s R. S. Constructions is in Manpada, Thane (pincode 421204), near Vishnunagar, Maharashtra, and is registered on MahaRERA as P51700014553, per GharKundli's check of MahaRERA records. Its boundaries filed there include Recreation Garden, School.
When was Yug Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Yug Heights was registered on MahaRERA on 12 December 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Yug Heights?
No court cases are listed for Yug Heights on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Yug Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s R. S. Constructions.
Check it yourself on MahaRERA
- How to check the possession date of Yug Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 421204
- Shanti Luxuria
- Palava Fresca J-K
- YESU ANAND HEIGHTS
- Runwal Gardens Phase 4 Bldg No. 33-34
- SHREE KRISHNA HEIGHTS
- ARISTA SKYLINE
- Chanakya A wing
- Chanakya C wing
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.