AADI ARPAN
by AADI SHIKHAR LLP · Sion West, Mumbai
Registered on MahaRERA under P51900049501, and currently active. Its completion date has moved from July 2025 to November 2026, 16 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
- MahaRERA registration
- P51900049501
- Status
- Registered and active
- Builder
- AADI SHIKHAR LLP
- Location
- Sion West, Mumbai · 400022
- Project type
- Residential / Group Housing
- Registered on
- 15 Feb 2023
- Completion date at registration
- July 2025
- Latest completion date
- November 2026
- Delay so far
- 16 months
- Homes
- 44
- Sold or booked
- 43%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
GharKundli’s full report on AADI ARPAN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Kundli Watch
AADI ARPAN: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about AADI ARPAN
Is AADI ARPAN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AADI ARPAN is registered as P51900049501 and its status is "Registered and active".
Where is AADI ARPAN?
AADI ARPAN by AADI SHIKHAR LLP is in Sion West, Mumbai (pincode 400022), Maharashtra, and is registered on MahaRERA as P51900049501, per GharKundli's check of MahaRERA records.
When is possession of AADI ARPAN due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AADI ARPAN in Sion West, Mumbai is 30 November 2026 — 16 months later than 31 July 2025, the date given at registration.
Does AADI ARPAN have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of AADI ARPAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AADI SHIKHAR LLP, which has 1 other project registered on MahaRERA.
Other projects in pincode 400022
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.