by M S DEVELOPERS · Kamba, Thane 421301

What’s in the report? →

Possession date of Green Valley (MahaRERA P51700017701): 30 April 2028, moved from 30 December 2023 (48 months later). No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700017701, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700017701, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Green Valley?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Green Valley has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51700018677)

    Reason the builder gave MahaRERA:
    “The completion of project is delayed due to manpower shortage created during and post Pandemic COVID-19. Due to reverse migration of laborers to their native places and break in supply chain of construction material have adversely impacted…” Read the full reason“The completion of project is delayed due to manpower shortage created during and post Pandemic COVID-19. Due to reverse migration of laborers to their native places and break in supply chain of construction material have adversely impacted the construction activities. Further due to financial crisis because of low booking and less realization of receipts from customers there has been funds shortage as raising of funds have been a problem. Currently the construction is going in full swing and work is progressing rapidly and we are expecting the project to be completed in the extended period…”
  3. 31 December 2027

    Extended at the builder's request (MahaRERA application EXT51700027837)

    Reason the builder gave MahaRERA:
    “Our project comprises of five buildings, of which the construction work of two buildings is nearly complete as can be seen from the Architects Certificate issued in Form-1 dated 31.03.2025. However, certain critical and unforeseen challenge…” Read the full reason“Our project comprises of five buildings, of which the construction work of two buildings is nearly complete as can be seen from the Architects Certificate issued in Form-1 dated 31.03.2025. However, certain critical and unforeseen challenges have significantly impacted our ability to complete the remaining work within the earlier approved timeline. The following key factors have contributed to the delay: 1. Change in Partnership Structure: Initially, there were nine partners in the firm. However, w.e.f. Jul’22, only two partners remain, as the rest have exited the partnership. This has resu…”
  4. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Green Valley’s extension records on MahaRERA (P51700017701), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Green Valley

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700017701
Status
Registered and active
Builder
M S DEVELOPERS
Location
Kamba, Thane · 421301
Project type
Others
Registered on
6 Sep 2018
Completion date at registration
December 2023
Latest completion date
April 2028
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
5
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Green Valley, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LOTUS100%0%0%0%
ORCHID100%100%96%0%
LILY100%100%85%0%
ROSE100%0%0%0%
CLOVER100%100%95%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Green Valley every 1–2 months.

Green Valley: buildings, flats and land, as filed on MahaRERA

  • Buildings: LOTUS (22 floors) · ORCHID (15 floors) · LILY (8 floors) · ROSE (22 floors) · CLOVER (15 floors)
  • Land: 5,340 sq m (about 1.3 acres) · recreational space 500 sq m
  • Boundaries filed include: LAYOUT ROAD
  • Map: Get directions

The builder’s record and reviews

Navaditya Developers (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 14 months); 1 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA.

Read Google reviews of Green Valley →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Green Valley: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Green Valley

What is the possession date of Green Valley?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Green Valley in Kamba, Thane is 30 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 48 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Green Valley?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Green Valley's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Green Valley extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Green Valley's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "The completion of project is delayed due to manpower shortage created during and post Pandemic COVID-19. Due to reverse migration of laborers to their native places and break in supply chain of construction material have adversely impacted the construction activities. Further due to financial crisis because of low booking and less realization of receipts from customers there has been funds shortage as raising of funds have been a problem. Currently the construction is going in full swing and work is progressing rapidly and we are expecting the project to be completed in the extended period…"; to 31 December 2027, giving the reason "Our project comprises of five buildings, of which the construction work of two buildings is nearly complete as can be seen from the Architects Certificate issued in Form-1 dated 31.03.2025. However, certain critical and unforeseen challenges have significantly impacted our ability to complete the remaining work within the earlier approved timeline. The following key factors have contributed to the delay: 1. Change in Partnership Structure: Initially, there were nine partners in the firm. However, w.e.f. Jul’22, only two partners remain, as the rest have exited the partnership. This has resu…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Green Valley?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Green Valley in Kamba, Thane is P51700017701.

Is Green Valley registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Green Valley is registered as P51700017701 and its status is "Registered and active".

What is the current construction status of Green Valley? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Green Valley's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does Green Valley have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Green Valley safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Green Valley is registered on MahaRERA as P51700017701, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Green Valley?

Green Valley is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Green Valley?

For a flat in Green Valley (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Green Valley received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Green Valley is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Green Valley uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Green Valley was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Green Valley's possession date changes?

The latest dates are on Green Valley's MahaRERA page (P51700017701). GharKundli's Kundli Watch sends a free WhatsApp update on Green Valley every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Green Valley have?

According to GharKundli's check of MahaRERA records (updated October 2026), Green Valley has 5 buildings filed: LOTUS with 22 floors; ORCHID with 15 floors; LILY with 8 floors; ROSE with 22 floors; CLOVER with 15 floors.

How big is the land of Green Valley?

According to GharKundli's check of MahaRERA records (updated October 2026), Green Valley stands on 5,340 sq m of land (about 1.3 acres) and 500 sq m of recreational open space.

What is the track record of Green Valley's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Navaditya Developers (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 14 months); 1 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Green Valley?

Google Maps has reviews of Green Valley written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Green Valley?

Green Valley by M S DEVELOPERS is in Kamba, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700017701, per GharKundli's check of MahaRERA records. Its boundaries filed there include LAYOUT ROAD. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).

When was Green Valley registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Green Valley was registered on MahaRERA on 6 September 2018. GharKundli did not find a title report on the land on file there.

Does Green Valley have any legal issues or court cases?

No court cases are listed for Green Valley on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Green Valley?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M S DEVELOPERS, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Kalyan

All 582 projects in Kalyan (421301) →

Other projects by M S DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.