Airyaman Terraces

by Airyaman Developers LLP · Sitla Devi Temple Road, Mumbai 400016Also near Mahim, Dadar West, Shivaji Park

What’s in the report? →

Possession date of Airyaman Terraces (MahaRERA P51900048609): 30 April 2027, moved from 31 December 2024 (24 months later). No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900048609, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51900048609, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Airyaman Terraces?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Airyaman Terraces has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51900027411)

    Reason the builder gave MahaRERA:
    “The present project Airyaman Terraces is one of redevelopment with five old tenants requiring rehabilitation. As of date, Permanent Alternate Accommodation Agreements have been registered for four tenants out of five. The date for handing o…” Read the full reason“The present project Airyaman Terraces is one of redevelopment with five old tenants requiring rehabilitation. As of date, Permanent Alternate Accommodation Agreements have been registered for four tenants out of five. The date for handing over possession of the said Flats comprised in the rehab component is agreed between the parties to be 31st July, 2026. Further, only one flat out of the Freesale component has been agreed to be sold and the date of possession therein is stated to be 31st March, 2026. However, when the project was registered, the Promoter believed that the project can be c…”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Airyaman Terraces’s extension records on MahaRERA (P51900048609), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Airyaman Terraces

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900048609
Status
Registered and active
Builder
Airyaman Developers LLP
Location
Sitla Devi Temple Road, Mumbai · 400016
Project type
Residential / Group Housing
Registered on
10 Jan 2023
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Airyaman Terraces, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AIRYAMAN TERRACES100%100%85%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Airyaman Terraces every 1–2 months.

Airyaman Terraces: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Airyaman Terraces →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Airyaman Terraces: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Airyaman Terraces

What is the possession date of Airyaman Terraces?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Airyaman Terraces in Sitla Devi Temple Road, Mumbai is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Airyaman Terraces?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Airyaman Terraces's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Airyaman Terraces extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Airyaman Terraces's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The present project Airyaman Terraces is one of redevelopment with five old tenants requiring rehabilitation. As of date, Permanent Alternate Accommodation Agreements have been registered for four tenants out of five. The date for handing over possession of the said Flats comprised in the rehab component is agreed between the parties to be 31st July, 2026. Further, only one flat out of the Freesale component has been agreed to be sold and the date of possession therein is stated to be 31st March, 2026. However, when the project was registered, the Promoter believed that the project can be c…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Airyaman Terraces?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Airyaman Terraces in Sitla Devi Temple Road, Mumbai is P51900048609.

Is Airyaman Terraces registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Airyaman Terraces is registered as P51900048609 and its status is "Registered and active".

What is the current construction status of Airyaman Terraces? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Airyaman Terraces's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AIRYAMAN TERRACES is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does Airyaman Terraces have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Airyaman Terraces safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Airyaman Terraces is registered on MahaRERA as P51900048609, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Airyaman Terraces?

Airyaman Terraces is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Airyaman Terraces?

For a flat in Airyaman Terraces (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Airyaman Terraces received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Airyaman Terraces is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Airyaman Terraces a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Airyaman Terraces's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Airyaman Terraces uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Airyaman Terraces was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Airyaman Terraces's possession date changes?

The latest dates are on Airyaman Terraces's MahaRERA page (P51900048609). GharKundli's Kundli Watch sends a free WhatsApp update on Airyaman Terraces every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Airyaman Terraces have?

According to GharKundli's check of MahaRERA records (updated October 2026), Airyaman Terraces has one building filed: AIRYAMAN TERRACES with 28 floors.

How big is the land of Airyaman Terraces?

According to GharKundli's check of MahaRERA records (updated October 2026), Airyaman Terraces stands on 435 sq m of land (about 0.1 acres), with 1,330 sq m of sanctioned built-up area.

What are the reviews of Airyaman Terraces?

Google Maps has reviews of Airyaman Terraces written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Airyaman Terraces?

Airyaman Terraces by Airyaman Developers LLP is in Sitla Devi Temple Road, Mumbai, pincode 400016 (near Mahim, Dadar West, Shivaji Park), Maharashtra, and is registered on MahaRERA as P51900048609, per GharKundli's check of MahaRERA records. Its boundaries filed there include SITLA DEVI TEMPLE ROAD. Its land is filed as F.P. No. 385. GharKundli lists all 84 MahaRERA projects in Mahim (400016).

When was Airyaman Terraces registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Airyaman Terraces was registered on MahaRERA on 10 January 2023. GharKundli did not find a title report on the land on file there.

Does Airyaman Terraces have any legal issues or court cases?

No court cases are listed for Airyaman Terraces on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Airyaman Terraces?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Airyaman Developers LLP.

All projects with possession due in 2027 in Mumbai City →

Other projects in Ward GNorth

All 84 projects in Mahim (400016) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.