PARTH LAKEFRONT
by PARTH WORLD LLP · Dighe, ThaneAlso near Kalwa
Possession: PARTH LAKEFRONT is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700018725. Status: Completed. 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about PARTH LAKEFRONT?
How the possession date of PARTH LAKEFRONT has moved
31 December 2022
Completion date given when the project was registered
31 December 2023
Extended at the builder's request (MahaRERA application EXT51700003927)
Reason the builder gave MahaRERA: “WE HAVE RECEIVED ADDITIONAL 0.5 FSI COMMENCEMENT CERTIFICATE 10 TH APRIL 2019 SO WE WOULD LIKE TO CHANGE PROJECT COMPLETION DATE”
30 December 2024
Revised completion date on MahaRERA
Source: PARTH LAKEFRONT’s extension records on MahaRERA (P51700018725), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PARTH LAKEFRONT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700018725
- Status
- Completed
- Builder
- PARTH WORLD LLP
- Location
- Dighe, Thane · 400605
- Project type
- Residential / Group Housing
- Registered on
- 29 Nov 2018
- Completion date at registration
- December 2022
- Latest completion date
- December 2024
- Delay so far
- 24 months
- Homes
- 173
- Towers
- 1
- Complaints on MahaRERA
- 5
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of PARTH LAKEFRONT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PARTH LAKEFRONT | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PARTH LAKEFRONT every month.
PARTH LAKEFRONT: buildings, flats and land, as filed on MahaRERA
- Buildings: PARTH LAKEFRONT (27 floors)
- Land: 3,620 sq m (about 0.9 acres) · sanctioned built-up 5,400 sq m
- Boundaries filed include: GARDEN
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Parth World has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 9 months); 1 still being built, none past the promised date yet. 5 complaints on MahaRERA across 1 project.
Read Google reviews of PARTH LAKEFRONT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PARTH LAKEFRONT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PARTH LAKEFRONT
What is the possession date of PARTH LAKEFRONT?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PARTH LAKEFRONT in Dighe, Thane is 30 December 2024 — 24 months later than 31 December 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for PARTH LAKEFRONT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PARTH LAKEFRONT's builder has filed on MahaRERA, the official one, is 30 December 2024, already 24 months later than the 31 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PARTH LAKEFRONT extended?
According to GharKundli's check of MahaRERA records (updated November 2026), PARTH LAKEFRONT's builder applied to MahaRERA to extend the completion date once: to 31 December 2023, giving the reason "WE HAVE RECEIVED ADDITIONAL 0.5 FSI COMMENCEMENT CERTIFICATE 10 TH APRIL 2019 SO WE WOULD LIKE TO CHANGE PROJECT COMPLETION DATE".
What is the RERA number of PARTH LAKEFRONT?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PARTH LAKEFRONT in Dighe, Thane is P51700018725.
Is PARTH LAKEFRONT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PARTH LAKEFRONT is registered as P51700018725 and its status is "Completed".
What is the construction status of PARTH LAKEFRONT?
According to GharKundli's check of MahaRERA records (updated November 2026), PARTH LAKEFRONT's status on MahaRERA is "Completed". As filed by the builder, slab work on PARTH LAKEFRONT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does PARTH LAKEFRONT have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PARTH LAKEFRONT safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), PARTH LAKEFRONT is registered on MahaRERA as P51700018725, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PARTH LAKEFRONT's possession date changes?
The latest dates are on PARTH LAKEFRONT's MahaRERA page (P51700018725). GharKundli's Kundli Watch sends a free WhatsApp update on PARTH LAKEFRONT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PARTH LAKEFRONT have?
According to GharKundli's check of MahaRERA records (updated November 2026), PARTH LAKEFRONT has one building filed: PARTH LAKEFRONT with 27 floors.
How big is the land of PARTH LAKEFRONT?
According to GharKundli's check of MahaRERA records (updated November 2026), PARTH LAKEFRONT stands on 3,620 sq m of land (about 0.9 acres), with 5,400 sq m of sanctioned built-up area.
What is the track record of PARTH LAKEFRONT's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Parth World has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 9 months); 1 still being built, none past the promised date yet. 5 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of PARTH LAKEFRONT?
Google Maps has reviews of PARTH LAKEFRONT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PARTH LAKEFRONT?
PARTH LAKEFRONT by PARTH WORLD LLP is in Dighe, Thane (pincode 400605), near Kalwa, Maharashtra, and is registered on MahaRERA as P51700018725, per GharKundli's check of MahaRERA records. Its boundaries filed there include GARDEN.
How many homes are in PARTH LAKEFRONT?
According to GharKundli's check of MahaRERA records (updated November 2026), PARTH LAKEFRONT has 173 homes in 1 tower registered on MahaRERA.
When was PARTH LAKEFRONT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PARTH LAKEFRONT was registered on MahaRERA on 29 November 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on PARTH LAKEFRONT?
No court cases are listed for PARTH LAKEFRONT on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of PARTH LAKEFRONT?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PARTH WORLD LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PARTH LAKEFRONT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
- PYRAMID ELEMENTS
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- MAULI KRUPA
- GURUKRUPA NITYAM
- Panache
- LOTUS
- ASAVARI CO OP HSG SOC LTD
Other projects by PARTH WORLD LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.