White Rose
by M/s Eeshan Enterprises (Samrin) · Louis Wadi, ThaneAlso near Panchpakhadi, Naupada, Thane West
Possession date of White Rose: 31 December 2026, moved from 30 March 2024 (33 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700019187, and currently active. 8 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about White Rose?
How the possession date of White Rose has moved
30 March 2024
Completion date given when the project was registered
31 December 2024
Extended at the builder's request (MahaRERA application EXT51700017519)
Reason the builder gave MahaRERA:
“Due to covid outbreak for the period March 2020 to February 2022 the project got impacted due to unavailability of labour and material hence project got delayed therefore we seek extension till 31.12.24 to complete the project. Request you…” Read the full reason
“Due to covid outbreak for the period March 2020 to February 2022 the project got impacted due to unavailability of labour and material hence project got delayed therefore we seek extension till 31.12.24 to complete the project. Request you to please grant the extension.”31 December 2025
Extended at the builder's request (MahaRERA application EXT51700025250)
Reason the builder gave MahaRERA:
“• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump chall…” Read the full reason
“• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Due to unavailability of skilled labour and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. • The geopolitical tension around the globe has led…”31 December 2026
Extended at the builder's request (MahaRERA application EA05022619732)
Reason the builder gave MahaRERA:
“•The extension is essential to maintain the validity of the project registration. Without the extension, the registration will lapse, which will: halt ongoing construction work, stall disbursement of home loans by banks / financial institut…” Read the full reason
“•The extension is essential to maintain the validity of the project registration. Without the extension, the registration will lapse, which will: halt ongoing construction work, stall disbursement of home loans by banks / financial institutions Institutions, prevent registration of new agreements for sale, and result in severe cash flow disruption, adversely affecting allottees. •The project has been delayed due to circumstances beyond the control of the Promoter, such as shortage of labour and demand slump triggered by market volatility. Unavailability of skilled labour and labour migratio…”
Source: White Rose’s extension records on MahaRERA (P51700019187), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on White Rose
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 8 complaints, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700019187
- Status
- Registered and active
- Builder
- M/s Eeshan Enterprises
- Location
- Louis Wadi, Thane · 400604
- Project type
- Others
- Registered on
- 9 Jan 2019
- Completion date at registration
- March 2024
- Latest completion date
- December 2026
- Delay so far
- 33 months
- Homes
- 141
- Sold or booked
- 89%
- Towers
- 2
- Complaints on MahaRERA
- 8
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of White Rose, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| White Rose Building No B2 | 100% | 100% | 90% | 80% |
| Krantinagar Rahivashi Sangh Sahakari Grihanirman Sanstha | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- White Rose Building No B2: covers Plinth+Ground+29(Pt.)
- Krantinagar Rahivashi Sangh Sahakari Grihanirman Sanstha: covers Basement+Gr.+24 Floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on White Rose every month.
White Rose: buildings, flats and land, as filed on MahaRERA
- Buildings: White Rose Building No B2 (31 floors, 159 units) · Krantinagar Rahivashi Sangh Sahakari Grihanirman Sanstha (26 floors, 5 units)
- Land: 2,061 sq m (about 0.5 acres) · recreational space 190 sq m
- Boundaries filed include: Service Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Samrin Dreamspaces (a group of 7 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 4 past the promised date (typically 12 months late); 3 lapsed. 37 complaints on MahaRERA across 6 projects.
Read Google reviews of White Rose →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
White Rose: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about White Rose
What is the possession date of White Rose?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for White Rose in Louis Wadi, Thane is 31 December 2026 — 33 months later than 30 March 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for White Rose?
Builders and listing sites often quote an earlier "target" date for handover. The completion date White Rose's builder has filed on MahaRERA, the official one, is 31 December 2026, already 33 months later than the 30 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of White Rose extended?
According to GharKundli's check of MahaRERA records (updated October 2026), White Rose's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2024, giving the reason "Due to covid outbreak for the period March 2020 to February 2022 the project got impacted due to unavailability of labour and material hence project got delayed therefore we seek extension till 31.12.24 to complete the project. Request you to please grant the extension."; to 31 December 2025, giving the reason "• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Due to unavailability of skilled labour and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. • The geopolitical tension around the globe has led…"; to 31 December 2026, giving the reason "•The extension is essential to maintain the validity of the project registration. Without the extension, the registration will lapse, which will: halt ongoing construction work, stall disbursement of home loans by banks / financial institutions Institutions, prevent registration of new agreements for sale, and result in severe cash flow disruption, adversely affecting allottees. •The project has been delayed due to circumstances beyond the control of the Promoter, such as shortage of labour and demand slump triggered by market volatility. Unavailability of skilled labour and labour migratio…".
What is the RERA number of White Rose?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of White Rose in Louis Wadi, Thane is P51700019187.
Is White Rose registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), White Rose is registered as P51700019187 and its status is "Registered and active".
What is the construction status of White Rose?
According to GharKundli's check of MahaRERA records (updated October 2026), White Rose's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does White Rose have complaints on MahaRERA?
8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is White Rose safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), White Rose is registered on MahaRERA as P51700019187, its completion date has moved 33 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if White Rose's possession date changes?
The latest dates are on White Rose's MahaRERA page (P51700019187). GharKundli's Kundli Watch sends a free WhatsApp update on White Rose every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does White Rose have?
According to GharKundli's check of MahaRERA records (updated October 2026), White Rose has 2 buildings filed: White Rose Building No B2 with 31 floors and 159 units; Krantinagar Rahivashi Sangh Sahakari Grihanirman Sanstha with 26 floors and 5 units.
How big is the land of White Rose?
According to GharKundli's check of MahaRERA records (updated October 2026), White Rose stands on 2,061 sq m of land (about 0.5 acres) and 190 sq m of recreational open space.
What is the track record of White Rose's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Dreamspaces (a group of 7 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 4 past the promised date (typically 12 months late); 3 lapsed. 37 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of White Rose?
Google Maps has reviews of White Rose written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is White Rose?
White Rose by M/s Eeshan Enterprises (Samrin) is in Louis Wadi, Thane (pincode 400604), near Panchpakhadi, Naupada, Thane West, Maharashtra, and is registered on MahaRERA as P51700019187, per GharKundli's check of MahaRERA records. Its boundaries filed there include Service Road.
How many homes are in White Rose?
According to GharKundli's check of MahaRERA records (updated October 2026), White Rose has 141 homes in 2 towers registered on MahaRERA, and 89% of them are sold or booked.
When was White Rose registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), White Rose was registered on MahaRERA on 9 January 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on White Rose?
No court cases are listed for White Rose on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of White Rose?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s Eeshan Enterprises, the company Samrin files this project under.
Check it yourself on MahaRERA
- How to check the possession date of White Rose
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Thane
- RAJ TATTVA PHASE 1 COMMERCIAL
- Veer Square (Thane)
- GURUKRUPA NITYAM
- MAULI KRUPA
- ASAVARI CO OP HSG SOC LTD
- LOTUS
- Panache
- Mahavir Breeze Phase 1
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.