GAJANAN SAMRUDDHI PHASE II C WING
by SHREE GAJANAN DEVELOPERS · Khadegolavali, Thane
Possession date of GAJANAN SAMRUDDHI PHASE II C WING: 31 December 2025, moved from 30 December 2023 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700020312. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about GAJANAN SAMRUDDHI PHASE II C WING?
How the possession date of GAJANAN SAMRUDDHI PHASE II C WING has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51700019015)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”31 December 2025
Extended at the builder's request (MahaRERA application EA02072501926)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2025”
Source: GAJANAN SAMRUDDHI PHASE II C WING’s extension records on MahaRERA (P51700020312), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GAJANAN SAMRUDDHI PHASE II C WING
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700020312
- Status
- Lapsed (registration period ended)
- Builder
- SHREE GAJANAN DEVELOPERS
- Location
- Khadegolavali, Thane · 421306
- Project type
- Residential / Group Housing
- Registered on
- 5 Apr 2019
- Completion date at registration
- December 2023
- Latest completion date
- December 2025
- Delay so far
- 24 months
- Homes
- 58
- Sold or booked
- 94%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 8
Construction progress of GAJANAN SAMRUDDHI PHASE II C WING, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GAJANAN SAMRUDDHI PHASE II C WING | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- GAJANAN SAMRUDDHI PHASE II C WING: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GAJANAN SAMRUDDHI PHASE II C WING every month.
GAJANAN SAMRUDDHI PHASE II C WING: buildings, flats and land, as filed on MahaRERA
- Buildings: GAJANAN SAMRUDDHI PHASE II C WING (7 floors, 62 units)
- Land: 5,103 sq m (about 1.3 acres) · sanctioned built-up 1,800 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of GAJANAN SAMRUDDHI PHASE II C WING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GAJANAN SAMRUDDHI PHASE II C WING: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GAJANAN SAMRUDDHI PHASE II C WING
What is the possession date of GAJANAN SAMRUDDHI PHASE II C WING?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GAJANAN SAMRUDDHI PHASE II C WING in Khadegolavali, Thane is 31 December 2025 — 24 months later than 30 December 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for GAJANAN SAMRUDDHI PHASE II C WING?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GAJANAN SAMRUDDHI PHASE II C WING's builder has filed on MahaRERA, the official one, is 31 December 2025, already 24 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GAJANAN SAMRUDDHI PHASE II C WING extended?
According to GharKundli's check of MahaRERA records (updated October 2026), GAJANAN SAMRUDDHI PHASE II C WING's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 31 December 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2025".
What is the RERA number of GAJANAN SAMRUDDHI PHASE II C WING?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GAJANAN SAMRUDDHI PHASE II C WING in Khadegolavali, Thane is P51700020312.
Is GAJANAN SAMRUDDHI PHASE II C WING registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GAJANAN SAMRUDDHI PHASE II C WING is registered as P51700020312 and its status is "Lapsed (registration period ended)".
What is the construction status of GAJANAN SAMRUDDHI PHASE II C WING?
According to GharKundli's check of MahaRERA records (updated October 2026), GAJANAN SAMRUDDHI PHASE II C WING's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on GAJANAN SAMRUDDHI PHASE II C WING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does GAJANAN SAMRUDDHI PHASE II C WING have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is GAJANAN SAMRUDDHI PHASE II C WING safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GAJANAN SAMRUDDHI PHASE II C WING is registered on MahaRERA as P51700020312, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GAJANAN SAMRUDDHI PHASE II C WING's possession date changes?
The latest dates are on GAJANAN SAMRUDDHI PHASE II C WING's MahaRERA page (P51700020312). GharKundli's Kundli Watch sends a free WhatsApp update on GAJANAN SAMRUDDHI PHASE II C WING every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GAJANAN SAMRUDDHI PHASE II C WING have?
According to GharKundli's check of MahaRERA records (updated October 2026), GAJANAN SAMRUDDHI PHASE II C WING has one building filed: GAJANAN SAMRUDDHI PHASE II C WING with 7 floors and 62 units.
How big is the land of GAJANAN SAMRUDDHI PHASE II C WING?
According to GharKundli's check of MahaRERA records (updated October 2026), GAJANAN SAMRUDDHI PHASE II C WING stands on 5,103 sq m of land (about 1.3 acres), with 1,800 sq m of sanctioned built-up area.
Where can I read reviews of GAJANAN SAMRUDDHI PHASE II C WING?
Google Maps has reviews of GAJANAN SAMRUDDHI PHASE II C WING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GAJANAN SAMRUDDHI PHASE II C WING?
GAJANAN SAMRUDDHI PHASE II C WING by SHREE GAJANAN DEVELOPERS is in Khadegolavali, Thane (pincode 421306), Maharashtra, and is registered on MahaRERA as P51700020312, per GharKundli's check of MahaRERA records.
How many homes are in GAJANAN SAMRUDDHI PHASE II C WING?
According to GharKundli's check of MahaRERA records (updated October 2026), GAJANAN SAMRUDDHI PHASE II C WING has 58 homes in 1 tower registered on MahaRERA, and 94% of them are sold or booked.
When was GAJANAN SAMRUDDHI PHASE II C WING registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GAJANAN SAMRUDDHI PHASE II C WING was registered on MahaRERA on 5 April 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on GAJANAN SAMRUDDHI PHASE II C WING?
1 court case is listed for GAJANAN SAMRUDDHI PHASE II C WING on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of GAJANAN SAMRUDDHI PHASE II C WING?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE GAJANAN DEVELOPERS, which has 8 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of GAJANAN SAMRUDDHI PHASE II C WING
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kalyan
- TULSA PARK
- Royal Hills
- MAJESTY HEIGHTS
- Mangeshi Dhara
- VIDHI IMPRESSION
- Balaji Govind
- OM TRIMURTI DARSHAN
- SWAMI ELITE
Other projects by SHREE GAJANAN DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.