by M/S Shubh Realty · BHayander, ThaneAlso near Mira Road East, Village Navghar, Mira Bhayandar

Possession date of Seven Square Avenue: 30 April 2029, moved from 30 March 2025 (45 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700020490, and currently active. Its completion date has moved from March 2025 to April 2029: 45 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Seven Square Avenue?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Seven Square Avenue has moved

  1. 30 March 2025

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EA11072502046)

    Reason the builder gave MahaRERA:
    “The delay in the completion of the Seven Square Avenue project, developed by M/s Shubh Realty, primarily arises from extensive structural and internal civil works required for three high-rise buildings (Ground + part stilt + 20 floors) as d…” Read the full reason“The delay in the completion of the Seven Square Avenue project, developed by M/s Shubh Realty, primarily arises from extensive structural and internal civil works required for three high-rise buildings (Ground + part stilt + 20 floors) as detailed in the PERT chart, coupled with incomplete internal and external development activities. As of the last certified date (31-03-2025), significant components such as internal plastering, flooring, door/windows installation, plumbing, waterproofing, sewerage systems, lift installations, fire fighting systems, and amenities like landscaping and compou…”
  3. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Seven Square Avenue’s extension records on MahaRERA (P51700020490), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Seven Square Avenue

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700020490
Status
Registered and active
Builder
M/S Shubh Realty
Location
BHayander, Thane · 401107
Project type
Others
Registered on
18 Apr 2019
Completion date at registration
March 2025
Latest completion date
April 2029
Delay so far
45 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
406
Sold or booked
35%
Towers
3
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of Seven Square Avenue, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building 10%0%0%0%
Building 20%0%0%0%
Building 30%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Building 1: covers 24 floors
  • Building 2: covers 24 floors
  • Building 3: covers 24 floors

Latest CC order on MahaRERA: dated 18/03/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Seven Square Avenue every month.

Seven Square Avenue: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building 1 (20 floors, 145 units) · Building 2 (20 floors, 146 units) · Building 3 (19 floors, 134 units)
  • Car parking: 95 covered, 344 open
  • Land: 8,638 sq m (about 2.1 acres) · sanctioned built-up 10,125 sq m · recreational space 1,296 sq m
  • Boundaries filed include: KS Mehta School
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Seven Square Avenue →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Seven Square Avenue: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Seven Square Avenue

What is the possession date of Seven Square Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Seven Square Avenue in BHayander, Thane is 30 April 2029 — 45 months later than 30 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Seven Square Avenue?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Seven Square Avenue's builder has filed on MahaRERA, the official one, is 30 April 2029, already 45 months later than the 30 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Seven Square Avenue extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Seven Square Avenue's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "The delay in the completion of the Seven Square Avenue project, developed by M/s Shubh Realty, primarily arises from extensive structural and internal civil works required for three high-rise buildings (Ground + part stilt + 20 floors) as detailed in the PERT chart, coupled with incomplete internal and external development activities. As of the last certified date (31-03-2025), significant components such as internal plastering, flooring, door/windows installation, plumbing, waterproofing, sewerage systems, lift installations, fire fighting systems, and amenities like landscaping and compou…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Seven Square Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Seven Square Avenue in BHayander, Thane is P51700020490.

Is Seven Square Avenue registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Seven Square Avenue is registered as P51700020490 and its status is "Registered and active".

What is the construction status of Seven Square Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), Seven Square Avenue's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Seven Square Avenue have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Seven Square Avenue safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Seven Square Avenue is registered on MahaRERA as P51700020490, its completion date has moved 45 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Seven Square Avenue's possession date changes?

The latest dates are on Seven Square Avenue's MahaRERA page (P51700020490). GharKundli's Kundli Watch sends a free WhatsApp update on Seven Square Avenue every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Seven Square Avenue have?

According to GharKundli's check of MahaRERA records (updated October 2026), Seven Square Avenue has 3 buildings filed: Building 1 with 20 floors and 145 units; Building 2 with 20 floors and 146 units; Building 3 with 19 floors and 134 units.

How much parking does Seven Square Avenue have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 95 covered and 344 open car parking spaces for Seven Square Avenue.

How big is the land of Seven Square Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), Seven Square Avenue stands on 8,638 sq m of land (about 2.1 acres), with 10,125 sq m of sanctioned built-up area and 1,296 sq m of recreational open space.

Where can I read reviews of Seven Square Avenue?

Google Maps has reviews of Seven Square Avenue written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Seven Square Avenue?

Seven Square Avenue by M/S Shubh Realty is in BHayander, Thane (pincode 401107), near Mira Road East, Village Navghar, Mira Bhayandar, Maharashtra, and is registered on MahaRERA as P51700020490, per GharKundli's check of MahaRERA records. Its boundaries filed there include KS Mehta School.

How many homes are in Seven Square Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), Seven Square Avenue has 406 homes in 3 towers registered on MahaRERA, and 35% of them are sold or booked.

When was Seven Square Avenue registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Seven Square Avenue was registered on MahaRERA on 18 April 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Seven Square Avenue?

No court cases are listed for Seven Square Avenue on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Seven Square Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S Shubh Realty.

All projects with possession due in 2029 in Thane →

Other projects in Thane

All 322 projects in Mira Road East (401107) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.