Mahalaxmi Heights Phase 2
by Mahalaxmi Builders & Developers · Near Swami Samarth Math, Thane 421201
What’s in the report? →Possession date of Mahalaxmi Heights Phase 2 (MahaRERA P51700020869): 31 December 2026, moved from 30 March 2021 (69 months later). It has 96 homes, 59% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700020869, and currently active.
Source: MahaRERA website — records for P51700020869, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Mahalaxmi Heights Phase 2?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Mahalaxmi Heights Phase 2 has moved
30 March 2021
Completion date given when the project was registered
31 December 2022
Extended at the builder's request (MahaRERA application EXT51700011298)
Reason the builder gave MahaRERA:
“Project could not be completed in stipulated time due to COVID 19 pandemic situation, Market conditions, delay from the contractor's side and scarcity of certain raw materials needed for civil work on site, which further delayed the constru…” Read the full reason
“Project could not be completed in stipulated time due to COVID 19 pandemic situation, Market conditions, delay from the contractor's side and scarcity of certain raw materials needed for civil work on site, which further delayed the construction process. Due to aforementioned circumstances, we are request to you goodself to grant Extension for date of completion for 1 year 9 months upto 31.12.2022”30 June 2025
Extended at the builder's request (MahaRERA application EXT51700017577)
Reason the builder gave MahaRERA:
“Project could not be completed in stipulated time due to COVID 19 pandemic situation, Market conditions, delay from the contractor's side and scarcity of certain raw materials needed for civil work on site, which further delayed the constru…” Read the full reason
“Project could not be completed in stipulated time due to COVID 19 pandemic situation, Market conditions, delay from the contractor's side and scarcity of certain raw materials needed for civil work on site, which further delayed the construction process. Due to aforementioned circumstances, we are request to you goodself to grant Extension for date of completion upto 30.06.2025.”31 December 2026
Extended at the builder's request (MahaRERA application EA29112518465)
Reason the builder gave MahaRERA: “Due to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/12/2026 to complete the project”
Source: Mahalaxmi Heights Phase 2’s extension records on MahaRERA (P51700020869), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mahalaxmi Heights Phase 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700020869
- Status
- Registered and active
- Builder
- Mahalaxmi Builders & Developers
- Location
- Near Swami Samarth Math, Thane · 421201
- Project type
- Residential / Group Housing
- Registered on
- 15 May 2019
- Completion date at registration
- March 2021
- Latest completion date
- December 2026
- Delay so far
- 69 months
- Homes
- 96
- Sold or booked
- 59%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Mahalaxmi Heights Phase 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Mahalaxmi Heights | 100% | 100% | 90% | 70% |
Commencement certificate (CC), as filed on MahaRERA
- Mahalaxmi Heights: covers G+12
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mahalaxmi Heights Phase 2 every 1–2 months.
Mahalaxmi Heights Phase 2: buildings, flats and land, as filed on MahaRERA
- Buildings: Mahalaxmi Heights (14 floors, 96 units)
- Land: 5,780 sq m (about 1.4 acres) · sanctioned built-up 2,331 sq m · recreational space 1,148 sq m
- Land, as filed: Survey No.13, Hissa No.7,8,10,12
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Mahalaxmi Heights Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mahalaxmi Heights Phase 2: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Mahalaxmi Heights Phase 2
What is the possession date of Mahalaxmi Heights Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mahalaxmi Heights Phase 2 in Near Swami Samarth Math, Thane is 31 December 2026 — 69 months later than 30 March 2021, the date given at registration.
The date has already moved 69 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Mahalaxmi Heights Phase 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mahalaxmi Heights Phase 2's builder has filed on MahaRERA, the official one, is 31 December 2026, already 69 months later than the 30 March 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Mahalaxmi Heights Phase 2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights Phase 2's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2022, giving the reason "Project could not be completed in stipulated time due to COVID 19 pandemic situation, Market conditions, delay from the contractor's side and scarcity of certain raw materials needed for civil work on site, which further delayed the construction process. Due to aforementioned circumstances, we are request to you goodself to grant Extension for date of completion for 1 year 9 months upto 31.12.2022"; to 30 June 2025, giving the reason "Project could not be completed in stipulated time due to COVID 19 pandemic situation, Market conditions, delay from the contractor's side and scarcity of certain raw materials needed for civil work on site, which further delayed the construction process. Due to aforementioned circumstances, we are request to you goodself to grant Extension for date of completion upto 30.06.2025."; to 31 December 2026, giving the reason "Due to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/12/2026 to complete the project".
What is the RERA number of Mahalaxmi Heights Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mahalaxmi Heights Phase 2 in Near Swami Samarth Math, Thane is P51700020869.
Is Mahalaxmi Heights Phase 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights Phase 2 is registered as P51700020869 and its status is "Registered and active".
What is the current construction status of Mahalaxmi Heights Phase 2? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights Phase 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Mahalaxmi Heights is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does Mahalaxmi Heights Phase 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Mahalaxmi Heights Phase 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights Phase 2 is registered on MahaRERA as P51700020869, its completion date has moved 69 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Mahalaxmi Heights Phase 2?
Mahalaxmi Heights Phase 2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Mahalaxmi Heights Phase 2?
For a flat in Mahalaxmi Heights Phase 2 (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Mahalaxmi Heights Phase 2 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights Phase 2 is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Mahalaxmi Heights Phase 2 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Mahalaxmi Heights Phase 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Mahalaxmi Heights Phase 2's possession date changes?
The latest dates are on Mahalaxmi Heights Phase 2's MahaRERA page (P51700020869). GharKundli's Kundli Watch sends a free WhatsApp update on Mahalaxmi Heights Phase 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mahalaxmi Heights Phase 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights Phase 2 has one building filed: Mahalaxmi Heights with 14 floors and 96 units.
How big is the land of Mahalaxmi Heights Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights Phase 2 stands on 5,780 sq m of land (about 1.4 acres), with 2,331 sq m of sanctioned built-up area and 1,148 sq m of recreational open space.
What are the reviews of Mahalaxmi Heights Phase 2?
Google Maps has reviews of Mahalaxmi Heights Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Mahalaxmi Heights Phase 2?
Mahalaxmi Heights Phase 2 by Mahalaxmi Builders & Developers is in Near Swami Samarth Math, Thane, pincode 421201, Maharashtra, and is registered on MahaRERA as P51700020869, per GharKundli's check of MahaRERA records. Its land is filed as Survey No.13, Hissa No.7,8,10,12. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).
How many flats are in Mahalaxmi Heights Phase 2, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights Phase 2 has 96 homes in 1 tower registered on MahaRERA, and 59% of them are sold or booked.
When was Mahalaxmi Heights Phase 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights Phase 2 was registered on MahaRERA on 15 May 2019. GharKundli did not find a title report on the land on file there.
Does Mahalaxmi Heights Phase 2 have any legal issues or court cases?
No court cases are listed for Mahalaxmi Heights Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Mahalaxmi Heights Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mahalaxmi Builders & Developers, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Mahalaxmi Heights Phase 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kalyan
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Balaji Govind
- Swami Elite
- Om Trimurti Darshan
- Ram Janki
Other projects by Mahalaxmi Builders & Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.