Bhairaav Milestone Phase II
by Sharpmind Consultancy Services Private Limited (Bhairaav) · Wagale Estate, Thane 400604Also near Wagle Industrial Estate, Panchpakhadi, MIDC, Wagle Estate
What’s in the report? →Possession date of Bhairaav Milestone Phase II (MahaRERA P51700020951): 30 December 2026, moved from 30 December 2022 (48 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700020951, and currently active.
Source: MahaRERA website — records for P51700020951, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Bhairaav Milestone Phase II?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Bhairaav Milestone Phase II has moved
30 December 2022
Completion date given when the project was registered
30 December 2023
Extended at the builder's request (MahaRERA application EXT51700013170)
Reason the builder gave MahaRERA:
“The Project ‘Bhairaav Milestone’ is being developed in Phases. Phase I is already completed and OC received. For Phase II, Building is already completed as per approved plans and as per MIDC DCR- 2009. Also, Part OC has been received upto 5…” Read the full reason
“The Project ‘Bhairaav Milestone’ is being developed in Phases. Phase I is already completed and OC received. For Phase II, Building is already completed as per approved plans and as per MIDC DCR- 2009. Also, Part OC has been received upto 5th Floor. However, due to some technical & administrative reasons, NOC from the concerned authority is pending as per certain norms and requirements and thereby the OC for the 6th floor(Part) could not be obtained till date, although the building upto 6th Floor is complete in all respects as per the approved plans. Presently, seeking extension so that the…”30 December 2024
Extended at the builder's request (MahaRERA application EXT51700018454)
Reason the builder gave MahaRERA:
“We have already obtained part OC upto 5th Floor of the Project but due to some technical & administrative factors, NOC is pending as per certain norms and requirements, hence the OC for the 6th floor(Part) could not be obtained. However, th…” Read the full reason
“We have already obtained part OC upto 5th Floor of the Project but due to some technical & administrative factors, NOC is pending as per certain norms and requirements, hence the OC for the 6th floor(Part) could not be obtained. However, the building upto 6th Floor is complete as per the plans submitted in RERA. We will be applying for OC for the 6th Floor units shortly. As per UDPCR 2034, additional FSI has been sanctioned for construction of further floors in the building. Presently, seeking extension for one year so that necessary updating of details can be done to carry out the further…”30 December 2026
Extended at the builder's request (MahaRERA application EXT51700024608)
Reason the builder gave MahaRERA: “Construction upto Part 6 floor has been completed and Occupancy certificate has been duly obtained. Revised commencement certificate has been received from MIDC”
Source: Bhairaav Milestone Phase II’s extension records on MahaRERA (P51700020951), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Bhairaav Milestone Phase II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- BHAIRAAV MILESTONEP51700015119 · possession 31 Dec 2019
- MahaRERA registration
- P51700020951
- Status
- Registered and active
- Builder
- Sharpmind Consultancy Services Private Limited
- Location
- Wagale Estate, Thane · 400604
- Project type
- Commercial
- Registered on
- 23 May 2019
- Completion date at registration
- December 2022
- Latest completion date
- December 2026
- Delay so far
- 48 months
- Homes
- 0
- Sold or booked
- 77%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Bhairaav Milestone Phase II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BHAIRAAV MILESTONE | 100% | 100% | 98% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bhairaav Milestone Phase II every 1–2 months.
Bhairaav Milestone Phase II: buildings, flats and land, as filed on MahaRERA
- Buildings: BHAIRAAV MILESTONE (11 floors, 97 units)
- Land: 5,201 sq m (about 1.3 acres) · sanctioned built-up 14,632 sq m
- Land, as filed: PLOT NO. C-15 ROAD NO. 16, WAGALE ESTATE, THANE
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Bhairaav Kothari Realtors (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 12 months); 2 still being built, 2 past the promised date (typically 43 months late); 1 lapsed. 102 complaints on MahaRERA across 2 projects.
Read Google reviews of Bhairaav Milestone Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Bhairaav Milestone Phase II: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Bhairaav Milestone Phase II
What is the possession date of Bhairaav Milestone Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Bhairaav Milestone Phase II in Wagale Estate, Thane is 30 December 2026 — 48 months later than 30 December 2022, the date given at registration.
The date has already moved 48 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Bhairaav Milestone Phase II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Bhairaav Milestone Phase II's builder has filed on MahaRERA, the official one, is 30 December 2026, already 48 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Bhairaav Milestone Phase II extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhairaav Milestone Phase II's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2023, giving the reason "The Project ‘Bhairaav Milestone’ is being developed in Phases. Phase I is already completed and OC received. For Phase II, Building is already completed as per approved plans and as per MIDC DCR- 2009. Also, Part OC has been received upto 5th Floor. However, due to some technical & administrative reasons, NOC from the concerned authority is pending as per certain norms and requirements and thereby the OC for the 6th floor(Part) could not be obtained till date, although the building upto 6th Floor is complete in all respects as per the approved plans. Presently, seeking extension so that the…"; to 30 December 2024, giving the reason "We have already obtained part OC upto 5th Floor of the Project but due to some technical & administrative factors, NOC is pending as per certain norms and requirements, hence the OC for the 6th floor(Part) could not be obtained. However, the building upto 6th Floor is complete as per the plans submitted in RERA. We will be applying for OC for the 6th Floor units shortly. As per UDPCR 2034, additional FSI has been sanctioned for construction of further floors in the building. Presently, seeking extension for one year so that necessary updating of details can be done to carry out the further…"; to 30 December 2026, giving the reason "Construction upto Part 6 floor has been completed and Occupancy certificate has been duly obtained. Revised commencement certificate has been received from MIDC".
What is the RERA number of Bhairaav Milestone Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Bhairaav Milestone Phase II in Wagale Estate, Thane is P51700020951.
Is Bhairaav Milestone Phase II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhairaav Milestone Phase II is registered as P51700020951 and its status is "Registered and active".
What is the current construction status of Bhairaav Milestone Phase II? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhairaav Milestone Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BHAIRAAV MILESTONE is 100% done and internal work 98%. GharKundli's full report compares construction progress with the deadline.
Does Bhairaav Milestone Phase II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Bhairaav Milestone Phase II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhairaav Milestone Phase II is registered on MahaRERA as P51700020951, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Bhairaav Milestone Phase II?
Bhairaav Milestone Phase II is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Bhairaav Milestone Phase II?
For a flat in Bhairaav Milestone Phase II (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Bhairaav Milestone Phase II received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Bhairaav Milestone Phase II is still under construction, with 30 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Bhairaav Milestone Phase II uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Bhairaav Milestone Phase II was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Bhairaav Milestone Phase II have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: BHAIRAAV MILESTONE (P51700015119, possession 31 Dec 2019). Check that your agreement names the registration of your own wing.
How can I get updates if Bhairaav Milestone Phase II's possession date changes?
The latest dates are on Bhairaav Milestone Phase II's MahaRERA page (P51700020951). GharKundli's Kundli Watch sends a free WhatsApp update on Bhairaav Milestone Phase II every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Bhairaav Milestone Phase II have?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhairaav Milestone Phase II has one building filed: BHAIRAAV MILESTONE with 11 floors and 97 units.
How big is the land of Bhairaav Milestone Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhairaav Milestone Phase II stands on 5,201 sq m of land (about 1.3 acres), with 14,632 sq m of sanctioned built-up area.
What is the track record of Bhairaav Milestone Phase II's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhairaav Kothari Realtors (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 12 months); 2 still being built, 2 past the promised date (typically 43 months late); 1 lapsed. 102 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Bhairaav Milestone Phase II?
Google Maps has reviews of Bhairaav Milestone Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Bhairaav Milestone Phase II?
Bhairaav Milestone Phase II by Sharpmind Consultancy Services Private Limited (Bhairaav) is in Wagale Estate, Thane, pincode 400604 (near Wagle Industrial Estate, Panchpakhadi, MIDC, Wagle Estate), Maharashtra, and is registered on MahaRERA as P51700020951, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO. C-15 ROAD NO. 16, WAGALE ESTATE, THANE. GharKundli lists all 87 MahaRERA projects in Wagle Estate (400604).
How many flats are in Bhairaav Milestone Phase II, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhairaav Milestone Phase II has 0 homes in 1 tower registered on MahaRERA, and 77% of them are sold or booked.
When was Bhairaav Milestone Phase II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhairaav Milestone Phase II was registered on MahaRERA on 23 May 2019. GharKundli did not find a title report on the land on file there.
Does Bhairaav Milestone Phase II have any legal issues or court cases?
No court cases are listed for Bhairaav Milestone Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Bhairaav Milestone Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sharpmind Consultancy Services Private Limited, the company Bhairaav files this project under, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Bhairaav Milestone Phase II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Wagle Estate (400604)
- Meet It Park
- M Square IT Park
- White Rose
- Orabel Business Park
- Times Square
- Wagle Trade Square
- Meghna One
- Centurion
Other projects by Sharpmind Consultancy Services Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.