Possession date of M Square IT Park: 30 January 2027, moved from 30 March 2024 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700025102, and currently active. Its completion date has moved from March 2024 to January 2027: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about M Square IT Park?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of M Square IT Park has moved

  1. 30 March 2024

    Completion date given when the project was registered

  2. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51700019365)

    Reason the builder gave MahaRERA: “We are attaching herewith a detailed note stating reasons for delay and necessary extension for the project.”
  3. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT51700028159)

    Reason the builder gave MahaRERA: “DUE TO CHANGE IN APPROVALS AND OTHER REASON MORE PARTICULARLY MENTIONED IN ATTACHED COVERING LETTER.”
  4. 30 September 2026

    Extended at the builder's request (MahaRERA application EA29062621602)

    Reason the builder gave MahaRERA:
    “The overall construction schedule was extended due to delays in receiving authority approvals for the additional floors. With only minor works remaining and the Occupancy Certificate (OC) pending, we kindly request a short extension of the…” Read the full reason“The overall construction schedule was extended due to delays in receiving authority approvals for the additional floors. With only minor works remaining and the Occupancy Certificate (OC) pending, we kindly request a short extension of the project validity until September 30, 2026. Attaching herewith requisite customer consents for your perusal.”
  5. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: M Square IT Park’s extension records on MahaRERA (P51700025102), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on M Square IT Park

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700025102
Status
Registered and active
Builder
Paper Flutings
Location
Wagle Industrial Estate, Thane · 400604
Project type
Commercial
Registered on
18 Mar 2020
Completion date at registration
March 2024
Latest completion date
January 2027
Delay so far
30 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
70%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of M Square IT Park, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
M Square IT Park100%100%90%95%

Commencement certificate (CC), as filed on MahaRERA

  • M Square IT Park: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on M Square IT Park every month.

M Square IT Park: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space1,289 – 9,14040
Shops1,004 – 5,2533
  • Buildings: M Square IT Park (11 floors, 43 units)
  • Car parking: 88 covered
  • Land: 2,576 sq m (about 0.6 acres) · sanctioned built-up 9,677 sq m
  • Boundaries filed include: ESIC Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of M Square IT Park →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

M Square IT Park: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about M Square IT Park

What is the possession date of M Square IT Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for M Square IT Park in Wagle Industrial Estate, Thane is 30 January 2027 — 30 months later than 30 March 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for M Square IT Park?

Builders and listing sites often quote an earlier "target" date for handover. The completion date M Square IT Park's builder has filed on MahaRERA, the official one, is 30 January 2027, already 30 months later than the 30 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of M Square IT Park extended?

According to GharKundli's check of MahaRERA records (updated October 2026), M Square IT Park's builder applied to MahaRERA to extend the completion date 3 times: to 31 March 2025, giving the reason "We are attaching herewith a detailed note stating reasons for delay and necessary extension for the project."; to 31 March 2026, giving the reason "DUE TO CHANGE IN APPROVALS AND OTHER REASON MORE PARTICULARLY MENTIONED IN ATTACHED COVERING LETTER."; to 30 September 2026, giving the reason "The overall construction schedule was extended due to delays in receiving authority approvals for the additional floors. With only minor works remaining and the Occupancy Certificate (OC) pending, we kindly request a short extension of the project validity until September 30, 2026. Attaching herewith requisite customer consents for your perusal.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of M Square IT Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of M Square IT Park in Wagle Industrial Estate, Thane is P51700025102.

Is M Square IT Park registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), M Square IT Park is registered as P51700025102 and its status is "Registered and active".

What is the construction status of M Square IT Park?

According to GharKundli's check of MahaRERA records (updated October 2026), M Square IT Park's status on MahaRERA is "Registered and active". As filed by the builder, slab work on M Square IT Park is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does M Square IT Park have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is M Square IT Park safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), M Square IT Park is registered on MahaRERA as P51700025102, its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if M Square IT Park's possession date changes?

The latest dates are on M Square IT Park's MahaRERA page (P51700025102). GharKundli's Kundli Watch sends a free WhatsApp update on M Square IT Park every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does M Square IT Park have?

According to GharKundli's check of MahaRERA records (updated October 2026), M Square IT Park has one building filed: M Square IT Park with 11 floors and 43 units.

How much parking does M Square IT Park have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 88 covered car parking spaces for M Square IT Park.

How big is the land of M Square IT Park?

According to GharKundli's check of MahaRERA records (updated October 2026), M Square IT Park stands on 2,576 sq m of land (about 0.6 acres), with 9,677 sq m of sanctioned built-up area.

Where can I read reviews of M Square IT Park?

Google Maps has reviews of M Square IT Park written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is M Square IT Park?

M Square IT Park by Paper Flutings is in Wagle Industrial Estate, Thane (pincode 400604), near Wagle Estate, Thane West, Panchpakhadi, Maharashtra, and is registered on MahaRERA as P51700025102, per GharKundli's check of MahaRERA records. Its boundaries filed there include ESIC Road.

How many homes are in M Square IT Park?

According to GharKundli's check of MahaRERA records (updated October 2026), M Square IT Park has 0 homes in 1 tower registered on MahaRERA, and 70% of them are sold or booked.

When was M Square IT Park registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), M Square IT Park was registered on MahaRERA on 18 March 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on M Square IT Park?

No court cases are listed for M Square IT Park on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of M Square IT Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Paper Flutings.

All projects with possession due in 2027 in Thane →

Other projects in pincode 400604

All 87 projects in Wagle Estate (400604) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.