How the possession date of MEET IT PARK has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51700018437)

    Reason the builder gave MahaRERA:
    “Due to COVID 19 , the purchasing power of the middle class group is highly impacted on account of loss of job opportunities. Due to this entire cash flow has been affected resulting in delay in construction activities coupled with issues of…” Read the full reason“Due to COVID 19 , the purchasing power of the middle class group is highly impacted on account of loss of job opportunities. Due to this entire cash flow has been affected resulting in delay in construction activities coupled with issues of covid 19 outbreak. We seek extension u/s 6 of the Act to complete the project with in extended timeline. We assure you that we shall complete the construction with in extended timeline and hence request your good selves to kindly grant us extension looking at various force majure conditions and factors beyond our control.”
  3. 31 October 2025

    Extended at the builder's request (MahaRERA application EXT51700025180)

    Reason the builder gave MahaRERA:
    “The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, cau…” Read the full reason“The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 31-10-2025. We hereby submit this application seeking an extension of the project under section 7 (3) of Maharera”
  4. 30 June 2026

    Extended at the builder's request (MahaRERA application EA29122519072)

    Reason the builder gave MahaRERA:
    “The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, cau…” Read the full reason“The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 30-06-2026. After careful consideration of the current circumstances and the challenges faced, we propose a revised complet…”

Source: MEET IT PARK’s extension records on MahaRERA (P51700024237), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MEET IT PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700024237
Status
Completed
Builder
MEET INFRA
Location
Waghle Estate, Thane · 400604
Project type
Commercial
Registered on
27 Jan 2020
Completion date at registration
December 2023
Latest completion date
June 2026
Delay so far
30 months
Homes
0
Sold or booked
39%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MEET IT PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MEET BUSINESS PARK100%100%100%0%

Commencement certificate (CC), as filed on MahaRERA

  • MEET BUSINESS PARK: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MEET IT PARK every month.

MEET IT PARK: buildings, flats and land, as filed on MahaRERA

  • Buildings: MEET BUSINESS PARK (9 floors, 57 units)
  • Car parking: 60 covered
  • Land: 1,351 sq m (about 0.3 acres) · sanctioned built-up 5,308 sq m · recreational space 752 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MEET IT PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MEET IT PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MEET IT PARK

What is the possession date of MEET IT PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MEET IT PARK in Waghle Estate, Thane is 30 June 2026 — 30 months later than 30 December 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for MEET IT PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MEET IT PARK's builder has filed on MahaRERA, the official one, is 30 June 2026, already 30 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MEET IT PARK extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MEET IT PARK's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "Due to COVID 19 , the purchasing power of the middle class group is highly impacted on account of loss of job opportunities. Due to this entire cash flow has been affected resulting in delay in construction activities coupled with issues of covid 19 outbreak. We seek extension u/s 6 of the Act to complete the project with in extended timeline. We assure you that we shall complete the construction with in extended timeline and hence request your good selves to kindly grant us extension looking at various force majure conditions and factors beyond our control."; to 31 October 2025, giving the reason "The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 31-10-2025. We hereby submit this application seeking an extension of the project under section 7 (3) of Maharera"; to 30 June 2026, giving the reason "The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 30-06-2026. After careful consideration of the current circumstances and the challenges faced, we propose a revised complet…".

What is the RERA number of MEET IT PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MEET IT PARK in Waghle Estate, Thane is P51700024237.

Is MEET IT PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MEET IT PARK is registered as P51700024237 and its status is "Completed".

What is the construction status of MEET IT PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), MEET IT PARK's status on MahaRERA is "Completed". As filed by the builder, slab work on MEET BUSINESS PARK is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does MEET IT PARK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is MEET IT PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MEET IT PARK is registered on MahaRERA as P51700024237, its MahaRERA status is "Completed", its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MEET IT PARK's possession date changes?

The latest dates are on MEET IT PARK's MahaRERA page (P51700024237). GharKundli's Kundli Watch sends a free WhatsApp update on MEET IT PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MEET IT PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), MEET IT PARK has one building filed: MEET BUSINESS PARK with 9 floors and 57 units.

How much parking does MEET IT PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 60 covered car parking spaces for MEET IT PARK.

How big is the land of MEET IT PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), MEET IT PARK stands on 1,351 sq m of land (about 0.3 acres), with 5,308 sq m of sanctioned built-up area and 752 sq m of recreational open space.

Where can I read reviews of MEET IT PARK?

Google Maps has reviews of MEET IT PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MEET IT PARK?

MEET IT PARK by MEET INFRA is in Waghle Estate, Thane (pincode 400604), near Wagle I.E, Thane East, Maharashtra, and is registered on MahaRERA as P51700024237, per GharKundli's check of MahaRERA records.

How many homes are in MEET IT PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), MEET IT PARK has 0 homes in 1 tower registered on MahaRERA, and 39% of them are sold or booked.

When was MEET IT PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MEET IT PARK was registered on MahaRERA on 27 January 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on MEET IT PARK?

No court cases are listed for MEET IT PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MEET IT PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MEET INFRA.

Other projects in pincode 400604

All 87 projects in Wagle Estate (400604) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.