by JEWEL ORIENT · Belavali, Badlapur West, Thane 421503

What’s in the report? →

Possession date of Orient Legacy (MahaRERA P51700021264): 30 June 2025, moved from 30 June 2022 (36 months later), and it has already passed. It has 141 homes, 67% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700021264. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51700021264, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2025) has passed.

What do you want to know about Orient Legacy?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Orient Legacy has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51700009422)

    Reason the builder gave MahaRERA: “Revision in plans due to changes in UDCR”
  3. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT51700012272)

    Reason the builder gave MahaRERA: “Revision in plans due to changes in UDCR”
  4. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51700027327)

    Reason the builder gave MahaRERA:
    “We would like to provide the following clarification for delay: 1. Project Structure and Status: The project "Orient Legacy" is registered as a single project under MahaRERA and comprises three wings: A, B, and C. o Wings B and C have alrea…” Read the full reason“We would like to provide the following clarification for delay: 1. Project Structure and Status: The project "Orient Legacy" is registered as a single project under MahaRERA and comprises three wings: A, B, and C. o Wings B and C have already been completed, and the Occupancy Certificates (OCs) for these wings were received earlier, dated 19-04-2022. o Additionally, societies for Wings B and C have already been formed. o Wing A is the only ongoing component of the project. 2. Consent for Extension: Given that Wings B and C are complete and only Wing A remains under development, we have take…”

Source: Orient Legacy’s extension records on MahaRERA (P51700021264), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Orient Legacy

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700021264
Status
Lapsed (registration period ended)
Builder
JEWEL ORIENT
Location
Belavali, Badlapur West, Thane · 421503
Project type
Others
Registered on
14 Jun 2019
Completion date at registration
June 2022
Latest completion date
June 2025
Delay so far
36 months
Homes
141
Sold or booked
67%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Orient Legacy, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%100%95%30%
WING B100%100%100%100%
WING C100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • WING A: covers 16 floors
  • WING B: covers Ground + 9 Floor
  • WING C: covers Ground + 5 Floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Orient Legacy every 1–2 months.

Orient Legacy: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING A (16 floors, 123 units) · WING B (11 floors, 56 units) · WING C (7 floors, 40 units)
  • Land: 4,980 sq m (about 1.2 acres) · sanctioned built-up 13,394 sq m
  • Land, as filed: S R NO 89 H NO 1 AND S R NO 90 H NO 4
  • Map: Get directions

The builder’s record and reviews

Ocorp Realty (a group of 3 linked companies) has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Orient Legacy →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Orient Legacy: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Orient Legacy

What is the possession date of Orient Legacy?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Orient Legacy in Belavali, Badlapur West, Thane is 30 June 2025 — 36 months later than 30 June 2022, the date given at registration. That date has already passed.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Orient Legacy?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Orient Legacy's builder has filed on MahaRERA, the official one, is 30 June 2025, already 36 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Orient Legacy extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Legacy's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2023, giving the reason "Revision in plans due to changes in UDCR"; to 30 December 2024, giving the reason "Revision in plans due to changes in UDCR"; to 30 June 2025, giving the reason "We would like to provide the following clarification for delay: 1. Project Structure and Status: The project "Orient Legacy" is registered as a single project under MahaRERA and comprises three wings: A, B, and C. o Wings B and C have already been completed, and the Occupancy Certificates (OCs) for these wings were received earlier, dated 19-04-2022. o Additionally, societies for Wings B and C have already been formed. o Wing A is the only ongoing component of the project. 2. Consent for Extension: Given that Wings B and C are complete and only Wing A remains under development, we have take…".

What is the RERA number of Orient Legacy?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Orient Legacy in Belavali, Badlapur West, Thane is P51700021264.

Is Orient Legacy registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Legacy is registered as P51700021264 and its status is "Lapsed (registration period ended)".

What is the current construction status of Orient Legacy? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Legacy's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Orient Legacy have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Orient Legacy safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Legacy is registered on MahaRERA as P51700021264, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Orient Legacy?

Orient Legacy isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Orient Legacy?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Orient Legacy: gharkundli.com/tools/property-cost-calculator

Has Orient Legacy received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Orient Legacy isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Orient Legacy?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Legacy's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Orient Legacy uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Orient Legacy was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Orient Legacy's possession date changes?

The latest dates are on Orient Legacy's MahaRERA page (P51700021264). GharKundli's Kundli Watch sends a free WhatsApp update on Orient Legacy every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Orient Legacy have?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Legacy has 3 buildings filed: WING A with 16 floors and 123 units; WING B with 11 floors and 56 units; WING C with 7 floors and 40 units.

How big is the land of Orient Legacy?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Legacy stands on 4,980 sq m of land (about 1.2 acres), with 13,394 sq m of sanctioned built-up area.

What is the track record of Orient Legacy's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ocorp Realty (a group of 3 linked companies) has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Orient Legacy?

Google Maps has reviews of Orient Legacy written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Orient Legacy?

Orient Legacy by JEWEL ORIENT is in Belavali, Badlapur West, Thane, pincode 421503, Maharashtra, and is registered on MahaRERA as P51700021264, per GharKundli's check of MahaRERA records. Its land is filed as S R NO 89 H NO 1 AND S R NO 90 H NO 4. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).

How many flats are in Orient Legacy, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Legacy has 141 homes in 3 towers registered on MahaRERA, and 67% of them are sold or booked.

When was Orient Legacy registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Legacy was registered on MahaRERA on 14 June 2019. GharKundli did not find a title report on the land on file there.

Does Orient Legacy have any legal issues or court cases?

No court cases are listed for Orient Legacy on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Orient Legacy?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JEWEL ORIENT.