Padamavati Royal Phase 2

by Sujeet Kumar Singh · Titwala, Thane 421605Also near Manda

What’s in the report? →

Possession date of Padamavati Royal Phase 2 (MahaRERA P51700023536): 30 April 2030, moved from 28 November 2025 (49 months later). It has 600 homes, 72% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700023536, and currently active. Its completion date has moved from November 2025 to April 2030: 49 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700023536, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Padamavati Royal Phase 2?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Padamavati Royal Phase 2 has moved

  1. 28 November 2025

    Completion date given when the project was registered

  2. 31 December 2029

    Extended at the builder's request (MahaRERA application EA28112518462)

    Reason the builder gave MahaRERA: “There are total 10 building, out of 10 7 buildings are completed and development of 3 building is pending due to financial issue. Due to financial issue, there was shortage of material issue, labour issue.”
  3. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Padamavati Royal Phase 2’s extension records on MahaRERA (P51700023536), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Padamavati Royal Phase 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700023536
Status
Registered and active
Builder
Sujeet Kumar Singh
Location
Titwala, Thane · 421605
Project type
Residential / Group Housing
Registered on
18 Dec 2019
Completion date at registration
November 2025
Latest completion date
April 2030
Delay so far
49 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
600
Sold or booked
72%
Towers
10
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Padamavati Royal Phase 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING 01100%100%100%100%
BUILDING 02100%100%100%100%
BUILDING 03100%100%100%100%
BUILDING 10100%5%0%0%
BUILDING 11100%50%0%0%
BUILDING 12100%100%100%100%
BUILDING 13100%100%100%100%
BUILDING 14100%100%100%100%
BUILDING 15100%100%100%100%
BUILDING 16100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING 01: covers 8 floors
  • BUILDING 02: covers 8 floors
  • BUILDING 03: covers 8 floors
  • BUILDING 10: covers 17 floors
  • BUILDING 11: covers 17 floors
  • BUILDING 12: covers 17 floors
  • BUILDING 13: covers 8 floors
  • BUILDING 14: covers 8 floors
  • BUILDING 15: covers 8 floors
  • BUILDING 16: covers 8 floors

Latest CC order on MahaRERA: dated 13/09/2023.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Padamavati Royal Phase 2 every 1–2 months.

Padamavati Royal Phase 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING 01 (8 floors, 46 units) · BUILDING 02 (8 floors, 46 units) · BUILDING 03 (8 floors, 46 units) · BUILDING 10 (17 floors, 94 units) · BUILDING 11 (17 floors, 94 units) · BUILDING 12 (17 floors, 94 units) · BUILDING 13 (8 floors, 45 units) · BUILDING 14 (8 floors, 45 units) · and 2 more
  • Land: 16,629 sq m (about 4.1 acres) · sanctioned built-up 31,528 sq m · recreational space 2,373 sq m
  • Land, as filed: 81/1, 98/3A, 101/2, 102, 103/1
  • Map: Get directions

The builder’s record and reviews

Sujeet Kumar Singh has 4 projects on MahaRERA since 2018, this one included. Of the 4 GharKundli has checked: 3 still being built, 1 past the promised date (typically 25 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Padamavati Royal Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Padamavati Royal Phase 2: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Padamavati Royal Phase 2

What is the possession date of Padamavati Royal Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Padamavati Royal Phase 2 in Titwala, Thane is 30 April 2030 — 49 months later than 28 November 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 49 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Padamavati Royal Phase 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Padamavati Royal Phase 2's builder has filed on MahaRERA, the official one, is 30 April 2030, already 49 months later than the 28 November 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Padamavati Royal Phase 2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Royal Phase 2's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "There are total 10 building, out of 10 7 buildings are completed and development of 3 building is pending due to financial issue. Due to financial issue, there was shortage of material issue, labour issue.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Padamavati Royal Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Padamavati Royal Phase 2 in Titwala, Thane is P51700023536.

Is Padamavati Royal Phase 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Royal Phase 2 is registered as P51700023536 and its status is "Registered and active".

What is the current construction status of Padamavati Royal Phase 2? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Royal Phase 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 5% to 100% across 10 towers. GharKundli's full report compares construction progress with the deadline.

Does Padamavati Royal Phase 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Padamavati Royal Phase 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Royal Phase 2 is registered on MahaRERA as P51700023536, its completion date has moved 49 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Padamavati Royal Phase 2?

Padamavati Royal Phase 2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Padamavati Royal Phase 2?

For a flat in Padamavati Royal Phase 2 (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Padamavati Royal Phase 2 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Royal Phase 2 is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Padamavati Royal Phase 2 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Padamavati Royal Phase 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Padamavati Royal Phase 2 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Padamavati Royal Phase 1 (P51700023535, possession 28 Nov 2025). Check that your agreement names the registration of your own wing.

How can I get updates if Padamavati Royal Phase 2's possession date changes?

The latest dates are on Padamavati Royal Phase 2's MahaRERA page (P51700023536). GharKundli's Kundli Watch sends a free WhatsApp update on Padamavati Royal Phase 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Padamavati Royal Phase 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Royal Phase 2 has 10 buildings filed: BUILDING 01 with 8 floors and 46 units; BUILDING 02 with 8 floors and 46 units; BUILDING 03 with 8 floors and 46 units; BUILDING 10 with 17 floors and 94 units; BUILDING 11 with 17 floors and 94 units; BUILDING 12 with 17 floors and 94 units; and 4 more.

How big is the land of Padamavati Royal Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Royal Phase 2 stands on 16,629 sq m of land (about 4.1 acres), with 31,528 sq m of sanctioned built-up area and 2,373 sq m of recreational open space.

What is the track record of Padamavati Royal Phase 2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sujeet Kumar Singh has 4 projects on MahaRERA since 2018, this one included. Of the 4 GharKundli has checked: 3 still being built, 1 past the promised date (typically 25 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Padamavati Royal Phase 2?

Google Maps has reviews of Padamavati Royal Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Padamavati Royal Phase 2?

Padamavati Royal Phase 2 by Sujeet Kumar Singh is in Titwala, Thane, pincode 421605 (near Manda), Maharashtra, and is registered on MahaRERA as P51700023536, per GharKundli's check of MahaRERA records. Its land is filed as 81/1, 98/3A, 101/2, 102, 103/1. GharKundli lists all 174 MahaRERA projects in Titwala (421605).

How many flats are in Padamavati Royal Phase 2, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Royal Phase 2 has 600 homes in 10 towers registered on MahaRERA, and 72% of them are sold or booked.

When was Padamavati Royal Phase 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Royal Phase 2 was registered on MahaRERA on 18 December 2019. GharKundli did not find a title report on the land on file there.

Does Padamavati Royal Phase 2 have any legal issues or court cases?

No court cases are listed for Padamavati Royal Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Padamavati Royal Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sujeet Kumar Singh, which has 1 other project registered on MahaRERA.

All projects with possession due in 2030 in Thane →

Other projects in Titwala (421605)

All 174 projects in Titwala (421605) →

Other projects by Sujeet Kumar Singh

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.